  1. Slide 1: Quarterly Activities Presentation

    Nickel Industries Limited (ASX:NIC) Quarterly Activities Presentation For the period ended 30 September 2024

  2. Slide 2: Safety and Sustainability

    Safety and Sustainability ▪ The Company-wide 12-month lost time injury frequency rate (LTIFR) as at end of September 2024, was 0.12, with one LTI occurring during the quarter, against 4.6 million work hours registered ▪ The Company-wide 12-month rolling total recordable injury frequency rate (TRIFR)

  3. Slide 3: September quarter review

    September quarter review US$108.4M EBITDA from Operations ▪ RKEF nickel metal production of 30,663 tonnes (100% basis) – 4.1% lower than June quarter (31,975 tonnes) due to 8 days scheduled maintenance at RNI, and RKAB licence-related issues ▪ RKEF EBITDA of US$60.0M – 43.5% higher than June quarter

  4. Slide 4: Stable RKEF production continues across our operations

    Stable RKEF production continues across our operations ▪ RKEF quarterly production of 30,663 tonnes of nickel metal, down 4.1% from June quarter (31,975 tonnes) – operations impacted by scheduled maintenance at RNI and ongoing RKAB licence-related issues ▪ Additionally, 2,125 tonnes of Ni in MHP fro

  5. Slide 5: NPI pricing – continuing to recover from March quarter lows

    NPI pricing – continuing to recover from March quarter lows ▪ Realised contract prices increased 3.9% from the June quarter as prices continued to improve from recent lows seen in the March quarter – prices increased each month of the quarter, and continued to increase in Q4 5

  6. Slide 6: ENC construction progress – key equipment now arriving on site

    ENC construction progress – key equipment now arriving on site ▪ Project site now fully prepped for the arrival of key long lead items and critical process equipment that has been sourced and procured from leading equipment manufacturers from around the world including Australia, China, Germany, Net

  7. Slide 7: Hengjaya Mine – improved weather conditions underpins strong financial result

    Hengjaya Mine – improved weather conditions underpins strong financial result June quarter September quarter Production summary 2024 2024 Saprolite mined wmt 879,280 1,468,914 Limonite mined wmt 2,090,072 4,280,938 Nickel ore mined wmt 2,969,352 5,749,852 Overburden mined BCM(1) 370,204 634,851 Stri

  8. Slide 8: Conditional acquisition of Sampala Project

    Conditional acquisition of Sampala Project ▪ In September, the Company announced it had signed CSPA’s for the acquisition of the Sampala Project - three highly prospective, advanced and contiguous, nickel-cobalt projects totalling 6,654ha in combined size, namely ETL, MJN and GF ▪ The Sampala Projec

  9. Slide 9: Corporate

    Corporate Completion of initial 51% interest in Siduarsi Project (1) ▪ Completed the acquisition of an initial 51% interest (increasing to 100%) in the Siduarsi Project for four million shares in Nickel Industries, in-line with the MoA signed in September 2021 ▪ Announced a JORC-compliant Mineral Re

  10. Slide 10: Further information

    Further information Justin Werner Cameron Peacock Managing Director Investor Relations and Business Development jwerner@nickelindustries.com cpeacock@nickelindustries.com 10

Nickel Industries — Q3 2024 Earnings Presentation on 6ix