Construcciones El Condor SA · BVC:ELCONDOR

Construcciones El Condor SA — Q1 2022 Earnings Presentation

19 slides from Construcciones El Condor SA's earnings presentation, 2022

  1. Slide 1: Financial Results 1Q-2022

    Slide 1: Financial Results 1Q-2022

    Financial Results 1Q-2022 Construcciones EL CONDOR S.A. }) Ingenieria de Infraestructura e Inversiones 75 ooo Wwww.elcondor.com: Ruta Al Mar Pacifico 2

  2. Slide 2: Disclaimer

    Slide 2: Disclaimer

    Disclaimer This document contains forward-looking statements on the intentions, expectations or forecasts of Construcciones El Condor S.A. at the time the document was drawn up and in reference to various matters including, among others, its performanceandothermattersrelatingtothecompanyactivitiesan

  3. Slide 3: Index

    Slide 3: Index

    1. Relevant Events 2021 Index 2. Trends of the Construction Industry 3. Financial Analysis 4. Backlog 5. Investment Portfolio 6. Shareholding Composition 7. Stock Volatility 8. Structuring of new projects

  4. Slide 4: 1. Relevant Events 1T 2022

    Slide 4: 1. Relevant Events 1T 2022

    1. Relevant Events 1T 2022 Construcciones el Cóndor is going to build 100% of the EPC due to the approval of the UF1 adjudication. $50,000 MM  Release of the EPC contract guarantee withholding $756,357 MM $70,000 MM  These resources were replaced by a guarantee of equal value. Maximum Absolut Pric

  5. Slide 5: 2. Trends of the Construction Industry

    Slide 5: 2. Trends of the Construction Industry

    2. Trends of the Construction Industry Signs of recovery in the construction sector drive dynamics of the companies that integrate it: Construction GDP Continues Growth Trend (+4,35%) compared to the same period in 2021 Recovery of Civil Works GDP: +1,27% last 12 months As investors and executors, w

  6. Slide 6: 3. Financial Analysis 1Q22 EBITDA

    Slide 6: 3. Financial Analysis 1Q22 EBITDA

    3.Financial Analysis 1Q22 EBITDA $12.606 $160.985 $(133.040) Positive evolution in revenues from the different main business $14.360 continue to drive 2022 results $10.855 $34.583 Cost optimization, greater dynamics of work execution and $64.540 $84 strategic synergies continue to drive EBITDA. $10.

  7. Slide 7: 3. Financial Analysis 1Q22 P&L

    Slide 7: 3. Financial Analysis 1Q22 P&L

    3.Financial Analysis 1Q22 P&L 20.8% Construction EBITDA Margin $33.418 27% Results generated by method of EBITDA Margin participation (IFRIC 12) 14% (includes interest on It doesn't represent an impact on the Operating Margin subordinated debt) operation cash flow $22.445 $10.091 $(16.385) 4.30% Net

  8. Slide 8: 3. Financial Analysis 1Q22 Assets

    Slide 8: 3. Financial Analysis 1Q22 Assets

    3.Financial Analysis 1Q22 Assets Growth in assets consolidates the Solvency of the Company: $1.110.515 $(5.865) $(1.104.650) $2.073.305* The increase in accounts receivable + inventories and in Property, Plant and Equipment, are the reflection of a greater dynamic at the level of execution of work $

  9. Slide 9: 3. Financial Analysis 1Q22 Liabilities

    Slide 9: 3. Financial Analysis 1Q22 Liabilities

    3. Financial Analysis 1Q22 Liabilities 15% Equipment Financed by Leasing  Concessions investment: $1.1 Bn  Asset Booking Value: $313,565 MM  Associated financial debt: $101,299 MM  Financial debt: $341,800 MM Total Financial Source of payment: sale of the 50% Debt share of Pacífico 3 (48%) $678,

  10. Slide 10: 4. Backlog

    Slide 10: 4. Backlog

    4. Backlog Backlog distribution (COP MM) EPC´s own Concessions 7% Backlog evolution (COP 000’ MM) Public Works 3.5 26% 3.3 $3.5 Bn* EPC´s concessions with others 67% 2021 2022 No equity contributions required *Adjusted backlog does not include projections of Cantera Agregados San Javier or Cóndor In

  11. Slide 11: 5. Investment Portfolio

    Slide 11: 5. Investment Portfolio

    5. Investment Portfolio y, Construcciones ) " o0o°o | z www.elcondor.com Pacifico 2

  12. Slide 12: Pacifico 2 construction progress and collection

    Slide 12: Pacifico 2 construction progress and collection

    Construction progress 82.4% March 2022 Source: Arup Both the traffic and the collection of this concession are getting closer and closer to the projected results, driven mainly by cargo vehicles: Traffic (thousands of vehicles) 86% Collection (COP MM) 84% 88% 88% 93% 87% Relevant facts: $50,118 MM $

  13. Slide 13: Construction progress, traffic and collection

    Slide 13: Construction progress, traffic and collection

    Construction progress 92% March 2022 Source: Arup Traffic and collection continue to show signs of recovery and better dynamics: Traffic (thousands of vehicles) Collection (COP MM) 132% 95% 79% 112% 81% 112% Relevant facts: The 5-star rating is received, which aims to We finish disbursing all Guaico

  14. Slide 14: Progress in the Cashout process of Vinus

    Slide 14: Progress in the Cashout process of Vinus

    Progress in the Cashout process of Vinus We continue to take important steps in the refinancing: $1.45 - $1,5 Bn $120,000 MM Total refinancing Cashout for el Cóndor Tenor: 22 years Transaction status and next steps: Tickets were assigned to the following financial institutions: Term sheet sent to fu

  15. Slide 15: 6. Shareholders composition and floating evolution

    Slide 15: 6. Shareholders composition and floating evolution

    6. Shareholders composition and floating evolution Total number of shareholders: 714

  16. Slide 16: 7. Share performance

    Slide 16: 7. Share performance

    7. Share performance  Share price does not yet reflect the Share price Company's economic reality or the strategies underway  The company decided not to pay dividends in 2022 to focus on its deleveraging strategy $402,056 MM Market Cap

  17. Slide 17: 8. Structuring of new projects

    Slide 17: 8. Structuring of new projects

    8. Structuring of new projects We continue to work together with ISA in the Constant generation of backlog through private following projects: initiatives and public works: 5G projects: Troncales del Magdalena 1 & 2 We continue working on 3 private initiative projects:  1 in feasibility  2 in pre-

  18. Slide 18: Contacts

    Slide 18: Contacts

    Contacts Luz María Eduardo López Correa Vargas Vélez CEO CFO luz.correa@elcondor.com eduardo.lopez@elcondor.com

  19. Slide 19: Construcciones El Condor

    Slide 19: Construcciones El Condor

    Construcciones EL CONDOR S.A. 00°0 www.elcondor.com

Source: Internet Archive copy of elcondor.com