Slide 1: Kibali…unlocking value in the North East of the DRC
Operated by Kibali…unlocking value in the North East of the DRC
Slide 2: Cautionary Statement on Forward-Looking Information
Cautionary Statement on Forward-Looking Information… Certain information contained in this presentation, including any information as to Barrick’s strategy, plans, or future financial or operating performance, constitutes “forward-looking statements”. All statements, other than statements of histori
Slide 3: Barrick… setting a new frontier in the North-East of the DRC
Barrick… setting a new frontier in the North-East of the DRC DRC portfolio Kibali Gold Mine (45%) N Kilo JV : exploration on the Ngayu belt N Kilo JV Kibali Loulo-Gounkoto (80%) Jabal Sayid (50%) Mombasa 1800 km Dar es Massawai Kibali (45%) Salaam 1950 km Tongon (89.7%) North Mara (84%) Bulyanhulu (
Slide 4: Kibali… what we found and what we've established
Kibali … what we found and what we’ve established
Slide 5: Kibali… what we found and what we've established
Kibali … what we found and what we’ve established
Slide 6: Kibali… what we found and what we've established
Kibali … what we found and what we’ve established
Slide 7: Durba today...
Durba today... qn
Slide 8: Kibali…our history
Kibali…our history 2015 2016 Q4 2016 Q2 2018 Q1 2019 Q2 2020 Q4 2020 Full year UG ramp up + First power from First power from Randgold – Commissioned grid Achieves record production at throughput ramp up to Ambarau Azambi Barrick stabilizer battery quarterly and annual design specs full sulphide cir
Slide 9: Kibali…Safety, Health and Environment
Kibali…Safety, Health and Environment ISO 45001 accredited ISO 14001 accredited Malaria incidence significantly brought down HIV programs in place Strong biodiversity program in place LTIFRi per million Malaria Incidence HIV Positivity Rate Water use efficiency hours worked Rate (%) (%) 2013 - 2019
Slide 10: Kibali … operational update
Kibali … operational update Kibali achieved the top-end of production guidance by delivering 808,134 ouncesi in 2020 Consistent performance from UG mining despite personnel movement interruptions from Covid-19 travel restrictions Process plant stability ensured another year of above planned recoveri
Slide 11: Kibali Underground
Kibali Underground… 750 meters deep UG ore tonnes Q4 2020i Operated on an owner mining basis 400 Ore tonnes hoisted - shaft Ore tonnes mined - decline National workforce trained to the next level of technology Tonnes (000s) 300 NEWTRAX – An electronic tag board system that tracks the position of und
Slide 12: Kibali gold production
Kibali…gold production Kibali Gold Production (100%) (Koz) 900 800 700 600 KOunces 500 400 300 200 100 0 2013 2014 2015 2016 2017 2018 2019 2020
Slide 13: Kibali Employees
Kibali Employees … Expat Contractors Expat 97 (2%) National Casuals Employees 162 (3%) 227 (4%) National Employees National 1,575 (31%) Contractors 3,006 (59%) Nationals : 4,743 (94%) Expatriates: 324 (6%)
Slide 14: In country investment… $3.4 billion paid by Kibali
In country investment… 2010 to 2020 $3.4 billion paid by Kibali in the form of taxes, permits, Nzoro Powerline Road infrastructure, salaries and payments to local suppliers ARU - Ariwara Road US$ million Northern By-pass road Visible contributions directly Southern By-pass road in the area of the pr
Slide 15: Committed to our partnership philosophy…
Committed to our partnership philosophy… local and international spendi Specialist contracts Construction General services Total contract Shaft sinking contract and supply chain spend Underground mining contract Master drilling $ million $ million $ million $ million 3,000 300 1,000 4,000 900 3,500
Slide 16: Kibali makes a difference… our CSR
Kibali makes a difference… our CSR Infrastructure development and maintenance Durba concrete project: first section (1.2 km) completed and handed over to the government Local Economic Development Projects Various income generating schemes in place with communities Education Over 60 schools built in
Slide 17: Agribusiness…local supply to Kibali
Agribusiness…local supply to Kibali Agribusiness Piggery projects Poultry projects Fish ponds Gardening for capacity building Coffee and cocoa projects Piggery Renzi gardens
Slide 18: Barrick…People, Partnerships and Sustainable Profitability
Barrick…People, Partnerships and Sustainable Profitability CEO with exploration team Barrick’s 10 year vision built on 5 year foundation Automation - Newtrax Efficiencies reducing carbon footprint water Licence to operate our partnerships sustainability Hydropower Covid-19 isolation centre