Sunrise Energy Metals Limited · ASX:SRL

Sunrise Energy Metals — Corporate Update (December 2025)

23 slides from Sunrise Energy Metals's corporate update, Dec 2, 2025

  1. Slide 1: Sunrise Project Community Consultative Committee

    Sunrise Project Community Consultative Committee 2 December 2025

  2. Slide 2: Contents

    Contents 1 2 Finance/Market Update Syerston Scandium Update 3 Sunrise Project Project 4 Community Update 5 Environmental Management Update 6 CCC Member Questions 2 Powering innovation | December 25

  3. Slide 3: Finance/Market Update

    01 Finance/Market Update 3 Powering innovation | December 25

  4. Slide 4: Syerston Scandium Project

    02 Syerston Scandium Project 4 Powering innovation | December 25

  5. Slide 5: What is Scandium?

    What is Scandium? › Scandium is a chemical element with the symbol Sc and atomic number 21 › Scandium is used in a range of strategic technology markets, including high performance alloys, fuel cells and semiconductors 5 Powering innovation | December 25

  6. Slide 6: Syerston Scandium Project

    Syerston Scandium Project › The Syerston Scandium Project comprises small- scale mining of multiple high-grade zones of scandium mineralisation that are hosted within the larger nickel-cobalt resource and subsequent processing to produce scandium oxide. › A Feasibility Study for a standalone Scandiu

  7. Slide 7: Syerston Scandium Project – Mineral Resource Estimate (MRE)

    Syerston Scandium Project – Mineral Resource Estimate (MRE) › MRE was updated in September following a successful 125 hole Reverse Circulation (RC) drilling program in April/May See the Company’s ASX Announcement of 9th September 2025 for further details 7 Powering innovation | December 25

  8. Slide 8: Syerston Scandium Project – Ore Reserves Estimate & Mine Plan

    Syerston Scandium Project – Ore Reserves Estimate & Mine Plan › The Ore Reserves Estimate & Mine Plan was updated in October following the completion of the MRE 8 Powering innovation | December 25

  9. Slide 9: Syerston Scandium Project – Feasibility Study

    Syerston Scandium Project – Feasibility Study The Update to the Feasibility Study is nearing completion with a target completion in early 2026 Completed In Progress  Project Overview  Ore Reserves & Mine Plan – Reporting  Geology and Mineral Resource Estimate  Mining and Ore Reserves & Mine Plan

  10. Slide 10: Syerston Scandium Project – Next Steps

    Syerston Scandium Project – Next Steps The aim of these activities is to derisk the critical path for project delivery and ultimately support a final investment decision  Planning for a modification to the current project approvals  Hire key roles within the owner's team for project delivery  Com

  11. Slide 11: Syerston Scandium Project – Proposed Optimisations

    Syerston Scandium Project – Proposed Optimisations › Project optimisations identified during Feasibility Study update include: • Minor changes to the site layout within the New Site approved Surface Development Area, Revised Pit Access Road including the locations of small-scale Scandium Layouts Ope

  12. Slide 12: Syerston Scandium Project – Approval Requirements

    Syerston Scandium Project – Approval Requirements › The approval pathway likely be a modification to existing Development Consent under s 4.55(2) of the NSW EP&A Act. › The modification application will likely require the following supporting technical studies: • Road Transport Assessment for the re

  13. Slide 13: Syerston Scandium Project – Sunrise Ni/Co Comparison

    Syerston Scandium Project – Sunrise Ni/Co Comparison 13 Powering innovation | December 25

  14. Slide 14: Syerston Scandium Project – Sunrise Ni/Co Comparison

    Syerston Scandium Project – Sunrise Ni/Co Comparison Sunrise Ni/Co Syerston Scandium Project Project (preliminary data) Construction Workforce 1900 (Approx) 105 Operations Workforce 350 60 Heavy Vehicle 90 4 Traffic/Day Processed Ore / Year 2500 kT/a 64 kT/a Capital Cost (AUD) $2,400 M $185 M Water

  15. Slide 15: Sunrise Project Update

    03 Sunrise Project Update 15 Powering innovation | December 25

  16. Slide 16: Community Update

    04 Community Update 16 Powering innovation | December 25

  17. Slide 17: Community – Working Together

    Community – Working Together › Community Events – Supported the Trundle Bush Tucker Day on 6 September sponsoring the dog jump – Supported the 2025 agricultural shows – Tullamore, Trundle, Bedgerabong, Condobolin, Parkes & Forbes › Presented on the Syerston Scandium project for the Central West and

  18. Slide 18: Keeping People Informed

    Keeping People Informed › Community Communication – Parkes and Condobolin shopfronts are open, first and third Tuesday/Thursday of the month › Sunrise Energy Metals website (NEW) – Complaints register published monthly, with zero complaints YTD – Community Complaints line listed on our website – 180

  19. Slide 19: Environmental Management Update

    05 Environmental Management Update 19 Powering innovation | December 25

  20. Slide 20: Environmental Monitoring

    Environmental Monitoring › Continuing environmental monitoring: – Air Quality – Surface Water – Groundwater (June 2025) – Meteorological › Depositional dust and Particulate Matter (PM10 and PM2.5) › Surface water monitoring events – No flows so far in 2025 › Groundwater monitoring – Next round sched

  21. Slide 21: Government Contact/Correspondence

    Government Contact/Correspondence › Dept Industry, Science & Resources – Major Projects Facilitation Agency – quarterly updates › Crown Lands – Licence application and update on discussions with Condobolin Local Aboriginal Land Council › NSW Resources – Sunrise Project / Syerston Scandium Project up

  22. Slide 22: CCC Member Questions

    06 CCC Member Questions 22 Powering innovation | December 25

  23. Slide 23: Thank you

    Thank you 0. sunrise energy metals