Sandfire Resources Ltd · ASX:SFR

Sandfire Resources — Investor Presentation (March 2012)

39 slides from Sandfire Resources's investor presentation, Mar 8, 2012

  1. Slide 1: Australia's newest copper-gold producer

    For personal use only Australia’s newest copper-gold producer: Start of mining at DeGrussa opens a new chapter of growth Sandfire Resources – Global Investor Update – March 2012

  2. Slide 2: Important information and disclaimer

    Important information and disclaimer Competent Person’s Statement • The information in this public presentation that relates to Exploration Results and Mineral Resources is based on information compiled by Mr John Evans who is a Fellow of For personal use only the Australasian Institute of Mining an

  3. Slide 3: Sandfire – corporate snapshot

    Sandfire – corporate snapshot For personal use only • Issued capital: 151.1M ordinary shares, 9.2M options • Market capitalisation: ~$1.2 billion (at $8.00/share) • Key project: DeGrussa (Doolgunna) • Strategic partner: POSCO • Product customers: POSCO, Yunnan Copper, MRI Trading Board Derek La Ferl

  4. Slide 4: Sandfire – the vision

    Sandfire – the vision For personal use only • To deliver superior returns to our owners from the premier high-grade DeGrussa VMS copper-gold mine • To discover additional VMS deposits within the emerging Doolgunna mineral field • To explore for, develop and mine key raw materials, in Australia and o

  5. Slide 5: Sandfire – a highly experienced team

    Sandfire – a highly experienced team Mr Karl M Simich Managing Director and Chief Executive Officer - Qualifications B.Comm, FCA, F.Fin For personal use only Experience and other directorships Mr Simich is an experienced international mining executive who has been involved in the financing, construc

  6. Slide 6: Production...the "sweet spot" for investors

    Production...the “sweet spot” for investors For personal use only Production: Financial Performance: Growth: • First DSO and underground ore • Forecast $2.4 billion operating cash • Organic growth – exploration mined – February 2012 flow, $4.2 billion revenue (DFS: life- of-mine) success • First DSO

  7. Slide 7: Production

    For personal use only Production • First DSO and underground ore mined – February 2012 • First DSO shipment – April 2012 • Plant commissioning – Q3 2012 • Ramp-up to 70-80ktpa Cu, 36kozpa Au by year end 7

  8. Slide 8: DeGrussa: a new era of growth begins

    DeGrussa: a new era of growth begins • 900km NE of Perth, established mining district For personal use only • Discovery to first production in <3 years • Open pit and underground mining operation: +7 year mine life • 100% debt funded through $390M ANZ facility • Conventional 1.5Mtpa on-site concentr

  9. Slide 9: Current status

    DeGrussa – current status For personal use only Construction of mine and infrastructure +65% complete 9

  10. Slide 10: Current status

    DeGrussa – current status For personal use only First DSO mined on 17 February 2012 10

  11. Slide 11: Current status

    DeGrussa – current status For personal use only Open pit well advanced with 5.7Mbcm mined to date including oxide copper – currently 70% complete 11

  12. Slide 12: Current status

    DeGrussa – current status For personal use only Evans Decline advanced to +1,200m from portal – first ore mined on 29 February 2012 12

  13. Slide 13: Current status

    DeGrussa – current status For personal use only Process plant construction +50% complete and all key infrastructure in place 13

  14. Slide 14: Current status

    DeGrussa – current status For personal use only On track for first ore to SAG Mill in Q3 of CY 2012 14

  15. Slide 15: Current status

    DeGrussa – current status For personal use only Product sales agreements in place for all DSO 15

  16. Slide 16: Current status

    DeGrussa – current status For personal use only Discussions well advanced for concentrate sale 16

  17. Slide 17: Growth potential

    DeGrussa – growth potential For personal use only • Oxide copper resources in open pit being stockpiled for proposed processing: • 44,000t of contained copper • 56,000oz of contained gold • Positive results from metallurgical testwork – further testwork continuing • Objective of testing is to conver

  18. Slide 18: Development timetable

    DeGrussa – development timetable For personal use only Pre-Feasibility Definitive Feasibility Study Project Financing Infrastructure Construction Major Equipment Concentrator Construction Open Pit Direct Shipping Ore Underground Massive Sulphide Concentrator Ramp-up Shipment 18

  19. Slide 19: Financial Performance

    For personal use only Financial Performance • Forecast $2.4 billion operating cash flow, $4.2 billion revenue (DFS: life-of-mine) • 77kt (170Mlb) payable copper metal per annum in first three years • Current spot price US$8,500/t, US$3.85/lb 19

  20. Slide 20: Cashflow – a mid-tier mining powerhouse

    Cashflow – a mid-tier mining powerhouse For personal use only DFS Outcomes First Production Q1 2012 (DSO), Q3 2012 (Conc.) 10.72Mt @ 5.1% Cu, 1.7g/t Au Life-of-mine extraction from Ore (541,000t contained copper, Reserves and Mineral Resources 599,000oz contained gold) discovered to date 93% Mineral

  21. Slide 21: Annual grade and C1 cost profile

    DeGrussa – annual grade and C1 cost profile For personal use only 21

  22. Slide 22: Annual grade and C1 cost profile

    DeGrussa – annual grade and C1 cost profile For personal use only • Definitive Feasibility Study optimises project cash flows • Higher grades + lower C1 costs in first three years = increased cash flow 22

  23. Slide 23: Growth

    For personal use only Growth • Organic growth – exploration success • Joint Venture opportunities • Acquisitions – Business Development Team 23

  24. Slide 24: Growth – future catalysts

    Growth – future catalysts • Organic growth – exploration success: For personal use only • Extensive bank of information now accumulated within prospective DeGrussa mine corridor • Prospective corridor extended to +30km, providing outstanding exploration upside • Regional exploration across Australia

  25. Slide 25: Mineral Field – regional exploration

    DeGrussa Mineral Field – regional exploration For personal use only 25

  26. Slide 26: Major exploration push

    DeGrussa – major exploration push For personal use only • Developing regional geology model from: • Deep drilling • Sterilisation & pre-development drilling • Mapping & geophysical interpretation • Priority VMS corridor extends for +30km • Lithogeochemistry program underway to aid target vectoring •

  27. Slide 27: Unlocking the "Corridor of Riches"

    DeGrussa – unlocking the “Corridor of Riches” For personal use only + 30km strike length prospective for VMS mineralisation • 30km long, 1.2km wide prospective corridor which can be explored to +2km vertical depth • Of this, only 1.2km strike length has been intensively explored to 600m vertical dep

  28. Slide 28: Global VMS camps

    Global VMS camps • Most significant VMS deposits occur in clusters that For personal use only define major mining camps – major source of global copper, zinc, lead production, eg: • Bathurst (New Brunswick) – 229.8Mt @ 0.46% Cu, 7.66% Zn, 3.01% Pb, 91g/t Ag, 0.46g/t Au (camp discovered 1952) • Kidd

  29. Slide 29: DeGrussa is a VMS deposit

    DeGrussa is a VMS deposit • Four lenses of mineralisation typical of VMS For personal use only deposit cluster • Classic host sequence of intra-volcanic sediments • Typical seafloor alteration with regionally extensive litho-geochemical signature • Classic VMS sulphide textures, including remnant ch

  30. Slide 30: Potential of Global VMS Camps

    Potential of Global VMS Camps Volcanic District No. of Deposits Million Tonnes Ore Million Tonnes Metal Area of District (km²) For personal use only Hokuroku, Japan 18 90 6.2 720 Bathurst No1, Canada 12 180 15.1 880 Bathurst No2, Canada 15 98 5.8 1150 Flin Flon, Canada 10 65 4.3 560 Snow Lake, Canad

  31. Slide 31: Growth – Joint Ventures

    Growth – Joint Ventures For personal use only • Reviewing asset-driven exploration opportunities in Australia and abroad • First opportunity secured: • Farm-in agreement with Global Resources Corporation (ASX: GRM) • Kennedy Highway Project (North Queensland) • $3M expenditure to earn 60%, with opti

  32. Slide 32: Growth – Acquisitions

    Growth – Acquisitions • Highly skilled in-house Business Development Team: For personal use only • Headed up by Technical Director John Evans • New Exploration Manager – Australia: Bruce Hooper • Business Analyst supported by strong technical team of 4-6 geologists and mining professionals • Ability

  33. Slide 33: Summary – a new global mining company in the making

    Summary – a new global mining company in the making • Flagship DeGrussa Project moving into production: For personal use only • First truck of DSO – 17 February 2012 • First truck of underground ore – 29 February 2012 • First ore in the SAG mill – Q3 2012 • High-margin production profile • Regional

  34. Slide 34: Appendix: Competent Person's Statements

    Appendix: Competent Person’s Statements Competent Person’s Statement – Mineral Resources For personal use only • The information in this report that relates to Mineral Resources (except the Indicated Resource of Supergene Chalcocite) is based on information compiled by Diederik Speijers who is a Fel

  35. Slide 35: Australia's newest copper-gold producer

    For personal use only Australia’s newest copper-gold producer: Start of mining at DeGrussa opens a new chapter of growth Sandfire Resources – Global Investor Update – March 2012

  36. Slide 36: Appendix – DeGrussa: Financial Evaluation and Price Assumptions

    Appendix – DeGrussa: Financial Evaluation and Price Assumptions Life-of-mine (LOM) For personal use only $ Billion Project revenue 4.2 Royalties (5% weighted average) (0.2) Operating costs and sustaining capital (1.6) Project operating cash flow (pre-tax) 2.4 Pre-production capital expenditure (0.4)

  37. Slide 37: Appendix – DeGrussa: Capital and Operating Costs

    Appendix – DeGrussa: Capital and Operating Costs For personal use only Capital Cost Breakdown A$M Construction (plant, equipment and infrastructure) 267 Open pit mining to access DSO 44 Underground mine development 56 Other pre-production 17 Total pre-production capital 384 Life-of-Mine Operating Co

  38. Slide 38: Appendix – DeGrussa: Mineral Resources

    Appendix – DeGrussa: Mineral Resources Table 1: DeGrussa Copper-Gold Project – March 2011 JORC Resource Statement For personal use only Resource Contained Contained Competent Zone Location Tonnes (Mt) Copper (%) Gold (g/t) Category Copper (t) Gold (oz) Person Gold Measured Open Pit 0.14 - 1.5 - 7,00

  39. Slide 39: Appendix – DeGrussa: Ore Reserves

    Appendix – DeGrussa: Ore Reserves Table 2: DeGrussa Copper-Gold Project – March 2011 Ore Reserve Statement Reserve Mining Contained Copper Contained Gold For personal use only Deposit Tonnes (Mt) Copper (%) Gold (g/t) Category Method (t) (oz) Open Pit - DeGrussa Probable 0.14 25.6 2.5 37,000 12,000