Outline BBM Project Corporate Description – Overview Priority Development Other Company Community Activity Development 3 Investor Presentation

Slide 4: Our Focus
Our Focus Building a Global Metallurgical Coal Business Positive and Agile Decision Making Respect for all Stakeholders Ethical Decision Making Strong Indonesian Team Technical Skills for Innovative Solutions Results Orientated 4 Investor Presentation

Slide 5: Strong Board Coal Pedigree
Strong Board Coal Pedigree Peter Lynch - Chairman and CEO, Mining Engineer, 25 years experience in mining; MIM, Shell Coal, MacArthur Coal, Open Cut & Underground, TSX and ASX:WCI. Pat Hanna - Executive Director, Geologist, over 30 years experience all coal; Globally consulting on over 40 projects;

Slide 6: Diverse & Experienced Management
Diverse & Experienced Management Yoga Suryanegara - Resource Manager Indonesia, Geologist, international experience, responsible for overseeing multi-million dollar exploration programs in Queensland and Kalimantan; more than 10 years experience in Berau Coal (fifth largest open cut thermal coal in

Slide 7: Executive Summary
Executive Summary Cokal Limited (CKA) Cokal Capital • Listed on the ASX in December 2010 Structure • Developing Metallurgical Coal Projects in Central ASX Code CKA Kalimantan Shares on Issue 471.1M • Objective: Metallurgical coal producer by H1 2014 Options on Issue 22.1M Debt nil Bumi Barito Minera

Slide 8: Project Locations - Indonesia
Project Locations - Indonesia 8 Investor Presentation

Slide 9: BBM, TBAR and BBP Tenements
BBM, TBAR and BBP Tenements INDONESIA 9 Investor Presentation

Slide 10: BBM – Priority Project
BBM – Priority Project Advanced developm ent plan: I n Feasibility phase Near term production High quality coking coal with Low cash significant upside operating cost potential Investment Highlights Experienced Management team Flexible development with a strong record of plans – low delivering high

Slide 11: BBM – Project Timeline
BBM – Project Timeline Stage 2 is an aspirational plan. There is insufficient Resource to support this plan at present. Current logistics planning takes into account possible expansion at a time when Studies and data support such an expansion plan. 11 Investor Presentation

Slide 12: Study Outcomes
Study Outcomes Stage 1: Real NPV of $US497M (100% Project) • Stand-alone Development ASSET DESCRIPTION Study at BBM recently Project BBM, Central Kalimantan, completed by SMEC Indonesia 264Mt JORC Resources 10.5Mt Measured, 13.5Mt • Capable of rapid expansion Indicated + 240Mt Inferred) (Stage 2) Pr

Slide 13: Mine Costs
Mine Costs US$ Operating Cost US$ Development Capital (Million) (excluding 7% Royalty) /t Avg Stage 1: Direct ship to start Stage 1: Direct ship to start 50 72.17 production production - Ramp up to 2Mtpa 50 - Average first 5 years 67.84 TOTAL 100 Stage 1: Stand-alone case (LOM) 89.58 Highly Competit

Slide 14: BBM Approvals
BBM Approvals Current Approvals IUP (Exploration), on ‘Clean & Clear’ List PT BBM approved Foreign Owned company (PMA status) Cokal Shareholding of PT BBM approved by BKPM (Central Government Foreign Investment Co-ordination Board) Exploration Forestry Permit (IPPKH Izin Pinjam Pakai) Envi

Slide 15: On the Doorstep of the Biggest MET Coal Markets
On the Doorstep of the Biggest MET Coal Markets Fastest and lowest cost shipping to key customers Dalandzangad Mongolia Coos Bay United S. Korea Japan Seoul China Seoul States Tokyo Shanghai India Guangzhou Mumbai Mumbai Mumbai Mumbai Vietnam China Seoul Ho Chi Min C

Slide 16: Developing a new Coking Coal Province
Developing a new Coking Coal Province Indonesian Coal Reserves 16 Investor Presentation

Slide 17: BBM Resources – 264Mt
BBM Resources – 264Mt1 Sufficient R esource to underw rite 2M tpa initial open cut production plan Resources by Seam and Category Seam Seam Thickness Measured Indicated Inferred Total Resources Name (m) Resource (Mt) Resources (Mt) Resources (Mt) (Mt) J 1.34 10.5 13.5 30.0 54.0 D 1.37 75.0 75.0 C 1.

Slide 18: BBM Premium Quality Coking and PCI Coal
BBM Premium Quality Coking and PCI Coal In-situ Average Coking Coal Quality, ‘J’ Seam (% adb) Inherent Volatile Fixed Calorific Value Relative Phos- Product Yield Ash Total Sulphur CSN Moisture Matter Carbon (Kcal/kg) Density phorus Raw Coal 100 0.9 6.5-23.2 15.6-18.9 58.4-74.8 0.31-0.55 6500-8100 9

Slide 19: BBM – Potential to Increase Resource Size
BBM – Potential to Increase Resource Size This potential is in addition to the current 264Mt JORC Measured, Indicated and Inferred Resources Comprised of 13 Seams in the Eastern Block of BBM (40% of the tenement area) 19 Investor Presentation

Slide 20: Planned Mining Operations
Planned Mining Operations Truck / Excavator Operation • Contractor operated • Direct Ship from Pit to Jetty Seam Outcrop on the Surface • Significant length of outcrop • J Seam ~ 1.4m thick • In-pit sizing / screening 20 Investor Presentation

Slide 21: Infrastructure and Transport
Infrastructure and Transport Coal to be transported in three phases, accounting for ~ 774km from the mine site to the Java Sea • 55km haul road from mine to the Barito River • 500km down the Barito River to the Intermediate Stockpile Port at Kelanis • Ocean-going barges to transport coal ~ 200km to

Slide 22: Truck Haulage
Truck Haulage • 55km road route, 2 studies done • Detail work underway • Maximum grade planned @ 8% • All weather surface • 120t per truck planned • Dual trailer, side tipping proposal • Ease of loading, unloading, reliability • Excellent balance of operating and capital costs 22 Investor Presentati

Slide 23: Barge Loading
Barge Loading • Plan for direct load from trucks to barges • Spare barges enable efficient system • Stockpiling capability • Front End Loader hoppers for re- loading from stockpile • Low capital, low operating cost • Minimises coal degradation 23 Investor Presentation

Slide 24: Shallow Draft Barges
Shallow Draft Barges • River designed barge system for safe, reliable and economic transport • Indonesian system currently uses towed ocean going barges • Mississippi style allows flexibility, for manoeuvring and cargo sizes USA: 40,000 km of rivers; 2.7m draft; $5B economic impact; 624Mtpa Transfer

Slide 25: Shallow Draft Barges
Shallow Draft Barges • Stage 1 – 6,000t convoys (4 x 1,500t barges) – 500km • Shallow draft: down to 2.3m water level • 3 Studies completed • Full bathymetric survey of river • Daily river height data for over 10 years used • 6 tugs and barge sets for Tug and 4 Barge Convoy 2Mtpa • Spare barge set a

Slide 26: Deep Water Barge to Shiploader
Deep Water Barge to Shiploader Deep Water Barges to Floating Crane in Java Sea • 12,000t now common (matches 2 x 6,000t upper river shallow barge convoys) • Matches common ship hatch size Operators • Many Barge operators at this point • Many Floating crane operators offshore • Low cost, efficient 26

Slide 27: Other Tenements – Central Kalimantan, Indonesia
Other Tenements Central Kalimantan, INDONESIA TBAR – Agreement signed 75/25 with local owners. 19,000ha adjoins BBM, which doubles the size of the exploration area available. Potential for BBM seams extend into TBAR Tenement is on the Clean and Clear List issued by the Directorate General of Min

Slide 28: BBM Project Conclusions
BBM Project Conclusions Low capital High quality Low operating investment coking product cost required Good margin Geographically Early and quick well production payback positioned Experienced Potential for Executive expansion team 28 Investor Presentation

Slide 29: Developing Infrastructure
Developing Infrastructure Two river ports and two coal -fired power stations to facilitate metallurgical coal production Working together for mutual benefit with the Murung Raya Regency Dr Willy Yoseph (Head of Regency), Jim Middleton and Domenic Martino (Cokal Director) CSR program on education and

Slide 30: Corporate Social Responsibility
Corporate Social Responsibility Local Schools • Assisted with materials and labour to make repairs to the Tumbang Tuan Village Jnr Elementary School • Provided an emergency generator to ensure reliable electricity for the local school • Sponsored four teachers for the Tumbang Tuan Jnr High School Sp

Slide 31: Project Location – West Kalimantan, Indonesia
Project Location West Kalimantan, INDONESIA Cokal 75.2% interest in PT Silangkop Nusa Raya (SNR) Three IUPs in Singtang Regency, West Kalimantan covers an area of 13,000ha Outcrop samples show high volatile, low ash, moderate sulphur and low phosphorus coking coal 31 Investor Presentation

Slide 32: Summary
Summary Executive Team with strong track record Plans for High Margin becoming a Metallurgical Coal Significant confirmed Metallurgical Coal Producer Assets with Good Plans to develop Potential the portfolio BBM on track for production in 2014, with significant upside potential 32 Investor Presentat
Source: Internet Archive copy of cokal.com.au
More decks from Cokal Limited
Investor Presentation (August 2026)21 slides · Aug 13, 2026
Shareholder Meeting (November 2025)28 slides · Nov 21, 2025
Investor Presentation (August 2025)14 slides · Aug 5, 2025
Shareholder Meeting (November 2024)18 slides · Nov 29, 2024
Investor Presentation (August 2024)12 slides · Aug 1, 2024
Shareholder Meeting (November 2023)19 slides · Nov 8, 2023