Orion Minerals Limited · ASX:ORN

Orion Minerals — Investor Presentation (August 2025)

20 slides from Orion Minerals's investor presentation, Aug 15, 2025

  1. Slide 1: Accelerating towards production

    Accelerating towards production August 2025 orionminerals.com.au ASX: ORN | JSE: ORN

  2. Slide 2: Important Notices & Disclaimer

    Important Notices & Disclaimer This presentation contains summary information about Orion technical, business, economic, competitive, political and derived from the production target and confirms that all material Minerals Ltd and its subsidiaries (Orion or Company) and their social uncertainties an

  3. Slide 3: Competent Person Statements

    Competent Person Statements The information in this presentation that relates to Orion’s Oosthuizen has sufficient experience that is relevant to the under consideration and to the activities being undertaken Exploration Results is a compilation of previously released type of mining and type of depos

  4. Slide 4: Company snapshot

    Company snapshot Post Proposed Current Share Capital Structure Summary Current Significant Shareholders Issue % Share Issue Shares on issue (30 Jul’25) 1, 2 7,282M 7,390M Tembo Capital (EU/Netherlands) 14.9 Delphi Group (EU/Germany) 11.0 Options on issue (30 Jul’25) 2 175M 235M Clover Alloys (SA) (S

  5. Slide 5: Focus on two highly prospective regions

    Focus on two highly prospective regions 3,582km2 of prime exploration and mining rights Upington Oranjemund Okiep Copper Pofadder Project Prieska Springbok Copperton Nababeep Prieska Copper Zinc Mine 450 km Page 5

  6. Slide 6: Prieska Copper Zinc Mine and Flat Mines (at Okiep)

    Prieska Copper Zinc Mine and Flat Mines (at Okiep) Two fully permitted, brownfield projects PCZM DFS ▪ Total Mineral Resources: 31Mt @ 1.2% Cu and 3.6% Zn resulting in contained Cu of 370kt and contained Zn of 1.12Mt ▪ Total Probable Ore Reserves: 15.6Mt @ 1.1% Cu and 3.1% Zn resulting in contained

  7. Slide 7: Progressing into execution phase

    Progressing into execution phase Accelerating towards production • Project development strategy • Two fully permitted brownfield projects with DFS’s published in March 2025 • Flagship project PCZM to be developed first – integrated project, commencing with Uppers and transitioning into Deeps • Flat

  8. Slide 8: Orion development strategy

    Orion development strategy Macro view of defined orebodies Funding + Project Deliver Governance + Value Engineering Sept 25 Prieska Okiep Nov 25 Optimisation to improve DFS NPV: 13 months Feb 26 financial metrics NPV: A$568m 23kt trial mining mixed May 26 A$75m stockpile Aug 26 NPV/Capex: Phase 1 NP

  9. Slide 9: PCZM favourably positioned on the global cost curve

    PCZM favourably positioned on the global cost curve Optimisation targeting second quartile for Okiep 500 All-in Sustaining Cost Curve - Copper 450 400 350 Optimisation 300 1st Quartile 2nd Quartile 3rd Quartile Okiep 4th Quartile 251,22 250 200 200 AiSC(USc/lb) 150 PCZM (¢/lb) 94,36 100 AISC 50 - 00

  10. Slide 10: Funding workflow to unlock Uppers and then Deeps

    Funding workflow to unlock Uppers and then Deeps Offtake negotiations underway Underway/Complete Near Term Execution Longer Term Execution Equity Capital Raise SPP Equity Capital Raise Offtake - Partner Selection Offtake - DD/Agreements/Close IDC - Funding Options IDC - Complementary Funding Role Tr

  11. Slide 11: Project execution

    Project execution orionminerals.com.au ASX: ORN | JSE: ORN

  12. Slide 12: Project definition

    Project definition Skilled professionals, deliberate processes, measurable outcomes Operational Readiness Project Value Execution Engineering Governance Project Construction Leadership Packages Team Page 12

  13. Slide 13: Skilled professionals

    Skilled professionals Experienced team to drive execution Steering committee Managing Director Project execution team PCZM OCP Project Director General Manager General Manager Project Mining Director Processing Director Governance Advisor Project Operational Value Controls Manager Readiness Manager

  14. Slide 14: Deliberate processes

    Deliberate processes Enabling project execution PCZM DFS Project Implementation Plan Value Engineering • NPV: AUD 568 million Functionality divided by • IRR (post tax): 26% Cost processes. • Peak Capital: AUD 578 million • AISC: USD2.06/lb Cu targets • Capital Intensity: 5% to 10% • USD9,174/t Cu Eq

  15. Slide 15: Outcomes - concentrate by Christmas 2026

    Outcomes - concentrate by Christmas 2026 PCZM integrated execution for phase 1 Uppers and phase 2 Deeps Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 EPCM Series of contracts On-site Contractors Camp incl Civils * Surfac

  16. Slide 16: Appendix

    Appendix orionminerals.com.au ASX: ORN | JSE: ORN

  17. Slide 17: PCZM Project Mineral Resource Estimates

    PCZM Project Mineral Resource Estimates Refer ASX/JSE Releases 28 March 2025, 25 July 2023 Page 17

  18. Slide 18: PCZM – Metal Equivalents

    PCZM – Metal Equivalents Deeps LoM Plan The Deeps LoM plan contains 22.6Mt of material with an underground average mined grade of 1.0% Cu and 3.3% Zn, giving a Cu equivalent (CuEq) grade of 1.6% Cu. The CuEq (%) values presented for the Deeps LoM Plan and Deeps Probable Ore Reserve estimate were det

  19. Slide 19: OCP – Flat Mines Project Mineral Resource Estimates

    OCP – Flat Mines Project Mineral Resource Estimates Refer ASX/JSE Releases 28 March 2025 Page 19

  20. Slide 20: Orion Minerals Limited

    Orion Minerals Limited Level 27, 120 Collins Street Melbourne, Vic, 3000 Australia Phone: +61 (0)3 8080 7170 Email: info@orionminerals.com.au Website: www.orionminerals.com.au orionminerals.com.au ASX: ORN | JSE: ORN

Orion Minerals — Investor Presentation (August 2025) on 6ix