Orion Minerals Limited · ASX:ORN

Orion Minerals — Resources Rising Stars 2025

20 slides from Orion Minerals's conference presentation, December 2025

  1. Slide 1: Resources Rising Stars

    Resources Rising Stars Tony Lennox – Managing Director and Chief Executive Officer December 2025 orionminerals.com.au ASX: ORN | JSE: ORN

  2. Slide 2: Important Notices & Disclaimer

    Important Notices & Disclaimer This presentation contains summary information about Orion by Orion Minerals Ltd, are inherently subject to Orion is not aware of any new information or data that Minerals Ltd and its subsidiaries (Orion or Company) and their significant technical, materially affects t

  3. Slide 3: Competent Person Statements

    Competent Person Statements The information in this presentation that relates to Orion’s information that materially affects the Ore Reserves Exploration Results is a compilation of previously released announced. reports to the ASX by Orion Minerals and is based on information compiled by Mr Paul Ma

  4. Slide 4: Company snapshot

    Company snapshot Post Proposed Current Share Capital Structure Summary Current Significant Shareholders Issue % Share Issue Tembo Capital (EU/Netherlands) 13.4 Shares on issue (25 Nov’25) 1, 2 8,071M 8,138M Delphi Group (EU/Germany) 10.3 Options on issue (25 Nov’25) 235M 235M Ratel Growth (T Borman

  5. Slide 5: Focus on two highly prospective regions

    Focus on two highly prospective regions 3,582km2 of prime exploration and mining rights Upington Oranjemund Okiep Pofadder Copper Project Prieska Springbok Copperton Nababeep Prieska Copper Zinc Mine 450 km Page 5

  6. Slide 6: Prieska Copper Zinc Mine and Flat Mines (at Okiep)

    Prieska Copper Zinc Mine and Flat Mines (at Okiep) Two fully permitted, brownfield projects PCZM DFS  Total Mineral Resources: 31Mt @ 1.2% Cu and 3.6% Zn resulting in contained Cu of 370kt and contained Zn of 1.12Mt  Total Probable Ore Reserves: 15.6Mt @ 1.1% Cu and 3.1% Zn resulting in contained

  7. Slide 7: Progressing into execution phase

    Progressing into execution phase Accelerating towards production Project development strategy • Brownfield projects with DFS’s published in March 2025 • Flagship project PCZM to be developed first – integrated project, commencing with Uppers and transitioning into Deeps • Flat Mines at OCP undergoin

  8. Slide 8: Orion development strategy

    Orion development strategy Macro view of defined orebodies Funding + Project Deliver Governance + Value Engineering Sep 25 Prieska Nov 25 Optimisation Okiep to improve DFS NPV: 13 months Feb 26 financial metrics NPV: A$568m 23kt trial mining mixed May 26 A$75m stockpile Aug 26 NPV/Capex Phase 1 NPV/

  9. Slide 9: PCZM

    PCZM What it looks like 1,250m 31Mt @ 1.2% Cu, 3.6% Zn 2.6km Refer ASX/JSE release 25 July 2023 Page 9

  10. Slide 10: PCZM favourably positioned on the global cost curve

    PCZM favourably positioned on the global cost curve Optimisation targeting second quartile for Okiep 500 All-in Sustaining Cost Curve - Copper 450 400 350 Optimisation 300 1st Quartile 2nd Quartile 3rd Quartile Okiep 4th Quartile 251,22 250 200 200 AiSC(USc/lb) 150 PCZM (¢/lb) 94,36 100 AISC 50 - 00

  11. Slide 11: Funding workflow to unlock Uppers and then Deeps

    Funding workflow to unlock Uppers and then Deeps Glencore non-binding agreement for US$200m-250m Underway/Complete Near Term Execution Longer Term Execution Equity Capital Equity Capital SPP Raise Raise Offtake - Partner Selection Offtake - DD/Agreements/Close IDC - Funding Options IDC - Complementa

  12. Slide 12: Glencore financing and offtake

    Glencore financing and offtake Signed non-binding financing and offtake agreement with Glencore on 17 September • Financing of US$200 million to US$250 million in 2 tranches • Tranche A of US$40 million to be used for the construction and startup of the Uppers at Prieska; • Tranche B of US$160 milli

  13. Slide 13: Moving to project execution

    Moving to project execution Page 13

  14. Slide 14: Project definition

    Project definition Skilled professionals, deliberate processes, measurable outcomes Operational Readiness Project Value Execution Engineering Governance Project Construction Leadership Packages Team Page 14

  15. Slide 15: Deliberate processes

    Deliberate processes Enabling project execution PCZM DFS Project Implementation Plan Value Engineering • NPV: AUD 568 million Functionality divided by • IRR (post tax): 26% Cost processes. • Peak Capital: AUD 578 million • AISC: USD2.06/lb Cu targets • Capital Intensity: 5% to 10% • USD9,174/t Cu Eq

  16. Slide 16: Outcomes - concentrate by Christmas 2026

    Outcomes - concentrate by Christmas 2026 PCZM integrated execution for phase 1 Uppers and phase 2 Deeps Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 EPCM Series of contracts On-site Contractors Camp incl Civils * Surfac

  17. Slide 17: Exploration opportunities at PCZM and OCP

    Exploration opportunities at PCZM and OCP Page 17

  18. Slide 18: PCZM – Near and medium-term exploration

    PCZM – Near and medium-term exploration Medium-term plan for resource definition and target extensions SE NW • 22,000m of resource T1 definition drilling • 72,000m from existing and planned development to T2 target extensions • T1 and T2 are current primary targets T4A • 36-month programme T3 T4B T5

  19. Slide 19: OCP – Near and medium-term exploration

    OCP – Near and medium-term exploration Deposits and prospects under current evaluation Page 19

  20. Slide 20: Contact us

    Contact us Scan the QR code to Orion Minerals Limited download this presentation Level 27, 120 Collins Street Melbourne, Vic, 3000 Australia Phone: +61 (0)3 8080 7170 Email: info@orionminerals.com.au Website: www.orionminerals.com.au orionminerals.com.au ASX: ORN | JSE: ORN

Orion Minerals — Resources Rising Stars 2025 on 6ix