Torrent Power Limited · NSE:TORNTPOWER

Torrent Power — Q2 FY2023-24 Earnings Presentation

24 slides from Torrent Power's earnings presentation, Nov 9, 2023

  1. Slide 1: Exchange filing cover letter

    November 09, 2023 To, To, Corporate Relationship Department Listing Department BSE Limited, National Stock Exchange of India Limited th 14 Floor, P. J. Towers, “Exchange Plaza”, C – 1, Block G Dalal Street, Fort, Bandra- Kurla Complex, Bandra (East), Mumbai-400001 Mumbai-400051 SCRIP CODE: 532779 SC

  2. Slide 2: Torrent Power Limited Investor Presentation Q2 FY 2023-24

    Torrent Power Limited Investor Presentation Q2 FY 2023-24

  3. Slide 3: Disclaimer

    DISCLAIMER This information may contain certain forward-looking statements/details in the current scenario, which is extremely dynamic and increasingly fraught with risks and uncertainties. Actual results, performances, achievements or sequence of events may be materially different from the views ex

  4. Slide 4: Presentation Outline

    PRESENTATION OUTLINE TORRENT GROUP TORRENT POWER LIMITED OVERVIEW OF OPERATIONS Q2 FY24 INVESTMENT RATIONALE FIVE YEAR TREND: KEY FINANCIAL & TECHNICAL STATISTICS

  5. Slide 5: Torrent Group

    TORRENT GROUP TORRENT PHARMACEUTICALS LIMITED • A generics pharmaceutical major with strong global footprint • Ranked 6th in Indian pharma market with leading position amongst top 5 players across key therapeutic areas like Cardiac, CNS, GI & VMN. • Ranked No. 1 among Indian Pharma companies in Braz

  6. Slide 6: Torrent Group

    TORRENT GROUP Turnover $ 4.3 Bn Market Cap $ 12.1 Bn Enterprise Value $ 13.7 Bn Employees 25,200+ Spreading smiles Illuminating Lives Not just healthcare… Lifecare Generating Trust. Distributing Opportunities. Turnover: $ 1.17 Bn Turnover: $ 3.13 Bn Building pan-India state-of-art Enterprise Value:

  7. Slide 7: Torrent Power Limited

    TORRENT POWER LIMITED Spreading smiles Illuminating Lives Thermal Solar Wind Transmission Distribution - 2,730 MW - 263 MW oper- - 920 MW - 355 kms 400 kV - Licensed: state-of-art gas ational - 138capacity MW of operational - 430 MW of & 128 Kms of - Ahmedabad/ Licensed operational 220 - 355 KV, dou

  8. Slide 8: Torrent Power Limited asset locations

    TORRENT POWER LIMITED GUJARAT UTTAR PRADESH AMGEN (362 MW) Sabarmati, Agra Ahmedabad KARNATAKA DGEN (1200 MW) Dahej, Bharuch SUGEN & Kamrej, Surat Wind (120 MW) Gulbarga and UNOSUGEN Raichur, Karnataka (1530 MW) Wind (49.6 MW) Jamnagar Wind (251.6 MW) Kutch 03 Wind (50.9 MW) Rajkot 05 Wind (50.4 MW)

  9. Slide 9: Portfolio of Assets: Thermal Generation

    TORRENT POWER LIMITED PORTFOLIO OF ASSETS : THERMAL GENERATION Particulars Sugen Unosugen Dgen Amgen Capacity 1147.5 382.5 1200 362 (MW) (3 x 382.5) (1 x 382.5) (3 x 400) (1 x 120, 2 x 121) Plant Type Gas-based CCPP Gas-based CCPP Gas-based CCPP Coal Based Location Near Surat, Gujarat Near Surat, Gu

  10. Slide 10: Portfolio of Assets: Renewable Generation

    TORRENT POWER LIMITED PORTFOLIO OF ASSETS : RENEWABLE GENERATION Particulars Solar Wind Capacity (MW) 263 920 Gujarat,Maharashtra,Karnataka, Location Gujarat, Maharashtra & Telangana Rajasthan & Madhya Pradesh COD FY 12 to FY17 FY 12 to FY 24 Avg Tariff (₹/kWh) 7.46 3.81 • 352.50 MW with Company’s L

  11. Slide 11: Portfolio of Assets: Licensed Distribution

    TORRENT POWER LIMITED PORTFOLIO OF ASSETS : LICENSED DISTRIBUTION Ahmedabad/ Particulars Surat Dahej Gandhinagar Licensed Area ~ 356 sq. km. ~ 52 sq. km. ~ 17 sq. km. Peak Demand(FY23) 1,900 MW 742 MW 106 MW As per Electricity Amendment Rules, 2023 the Licenses are deemed to be renewed for further 2

  12. Slide 12: Portfolio of Assets: Licensed Distribution

    TORRENT POWER LIMITED PORTFOLIO OF ASSETS : LICENSED DISTRIBUTION Dadra and Nagar Haveli and Daman Particulars Dholera SIR and Diu Power Distribution Licensed Area ~ 920 sq. km. ~603 sq. km. Peak Demand(FY23) - 1,281 MW As per Electricity Amendment Rules, 2023 the Licenses are deemed to be renewed f

  13. Slide 13: Portfolio of Assets: Franchised Distribution

    TORRENT POWER LIMITED PORTFOLIO OF ASSETS : FRANCHISED DISTRIBUTION Particulars Bhiwandi Agra Shil, Mumbra, Kalwa (SMK) Licensed Area ~ 721 sq. km. ~ 221 sq. km. ~65 sq. Km. Peak Demand 595 MVA 510 MVA 146 MVA (FY23) License validity 25th Jan 2027 31st March 2030 29th Feb 2040 Accolades /  Country'

  14. Slide 14: Overview of Operations – Q2 FY 2023-24

    OVERVIEW OF OPERATIONS – Q2 FY 2023-24 Consolidated Financial Statement Q2 23-24 Q2 22-23 Growth H1 23-24 H1 22-23 Growth FY 22-23 (₹ in Cr.) Unaudited Unaudited % Unaudited Unaudited % Revenue from Operations 6,961 6,703 4% 14,288 13,213 8% 25,694 Power Purchase Cost 4,972 4,457 10,426 9,182 16,949

  15. Slide 15: Overview of Operations – Q2 FY 2023-24

    OVERVIEW OF OPERATIONS – Q2 FY 2023-24 Total Comprehensive Income (TCI) for Q2 FY24 is higher at ₹ 531 crore compared to ₹ 485 crore for Q2 FY23. The major reasons for improvement in the TCI for the quarter on y-o-y basis are:  Increase in contribution from licensed distribution businesses;  Highe

  16. Slide 16: Q2 Thermal PLF / Net Generation

    OVERVIEW OF OPERATIONS – Q2 FY24 Q2 Thermal PLF(%)/ Net Generation(MUs) 96.0% 91.5% 705 MUs 603 MUs 48.9% 40.1% 402 MUs 33.4% 989 25.1% MUs 1469 13.3% MUs 7.0% 3.0% 839 2174 174 0.0% 0.0% 78 3.0% MUs MUs MUs 169 MUs MUs SUGEN UNOSUGEN DGEN GAS PLANTS AMGEN THERMAL 1147.5 MW 382.5 MW 1200 MW 2730 MW

  17. Slide 17: Q2 Renewable PLF / MUs Dispatched

    OVERVIEW OF OPERATIONS– Q2 FY24 Q2 Renewable PLF (%)/ MUs Dispatched 36.7% 27.7% 743 14.9% 14.8% 491 MUs MUs 264 89 MUs 86 MUs MUs WIND 804.5 MW / 919.5 MW* SOLAR 263 MW / 272 MW Q2 22-23 Q2 23-24 *Includes generation from 115 MW SECI V Project commissioned on July 15, 2023.

  18. Slide 18: Q2 USO/Purchase and T&D Loss

    OVERVIEW OF OPERATIONS– Q2 FY24 Q2 USO/Purchase (MUs) 2,678 2,281 2,430 2,487 1,004 1,041 1,010 993 693 760 181 217 193 207 Ahmedabad Surat Dahej DDDNH Bhiwandi Agra SMK Q2 23 Q2 24 T&D Loss (%) T&D Loss(%) 35.32% 6.30% 30.69% 5.57% 3.60% 11.35% 2.42% 2.13% 10.98% 9.86% 11.36% 1.67% 0.57% 0.33% Ahme

  19. Slide 19: Investment Rationale

    INVESTMENT RATIONALE • State of the art gas • Huge growth • Need for a robust • Opportunities for based plants potential in grid to support private sector renewables; returns increase in considering the • Direct import of LNG above COE for renewables capacity endemic at efficient cost selected proje

  20. Slide 20: Investment Rationale

    INVESTMENT RATIONALE Excellent Regulated operational Promising businesses records growth ensuring opportunities stable returns Unmatched Strong project distribution management model skills World class Rational generation Value allocation of assets Creation capital

  21. Slide 21: 5 Year Trend - Financial Statistics

    5 YEAR TREND - FINANCIAL STATISTICS Revenues from Operations (₹ Crore) EBIDTA (₹ Crore)/EBIDTA Margin (%) 25694 5141 3734 3607 3826 13151 13641 14257 3389 12173 26% 27% 30% 27% 20% 2018-19 2019-20 2020-21 2021-22 2022-23 2018-19 2019-20 2020-21 2021-22 2022-23 TCI* (₹ Crore) Net Worth (₹ Crore) 1197

  22. Slide 22: 5 Year Trend - Financial Statistics

    5 YEAR TREND - FINANCIAL STATISTICS Net Debt / EBITDA Net Debt Equity Ratio 2.61 0.82 2.24 0.80 0.80 0.80 2.18 1.98 1.97 0.64 18-19 19-20 20-21 21-22 22-23 18-19 19-20 20-21 21-22 22-23 Return on Capital Employed Return on Networth 14.00% 19.07% 14.22% 10.01% 10.31% 11.05% 12.42% 9.32% 9.54% 8.23% 1

  23. Slide 23: 5 Year Trend - Operational Statistics

    5 YEAR TREND - OPERATIONAL STATISTICS THERMAL PLF (%) T&D loss (%) Licensed Distribution 87.8% 88.2% 6.31% 6.03% 72.9% 5.61% 76.9% 4.98% 62.3% 60.1% 59.9% 57.8% 4.06% 4.17% 41.1% 3.59% 3.43% 3.43% 3.74% 59.9% 3.38% 3.17% 44.3% 44.3% 33.4% 40.7% 38.4% 15.0% 9.8% 30.6% 16.1% 0.0% 6.5% 0.40% 0.35% 0.31

  24. Slide 24: Thank You