Ameresco, Inc. · NYSE:AMRC
Ameresco — Corporate Update (July 2017)
14 slides from Ameresco's corporate update, July 2017

Slide 1: Your Trusted Sustainability Partner. Candlewood Solar | New Milford CT
Your Trusted Sustainability Partner. Candlewood Solar | New Milford CT

Slide 2: Ameresco - A Renewable Energy Leader
Ameresco- A Renewable Energy Leader • Founded in 2000 to build sustainable energy solutions • Headquartered in MA • Completed over $5 billion in sustainable energy projects • 1,000+ employees • Strongly focused on working with 70 offices in 34 states Municipalities in New England and 5 provinces *Am

Slide 3: Ameresco - 200 MW of experience in PV
Ameresco- 200 MW of experience in PV Large Complex 18.6MW Ft. Detrick, MD 2.5MW Mass Department of Transportation Pioneering Multi-phase 3MW Canopy + LED, MSP Airport 17MW Arizona State University Page 3 l © 2016 Ameresco, Inc. All rights reserved.

Slide 4: Ground Mount Solar PV Systems
Ground Mount Solar PV Systems • Generate electricity directly from sunlight and feed it to the grid, typically under a Power Purchase Agreement • 3 to 4 acres of land per MW • Mounted on racks supported by steel posts driven or screwed into the ground (4-6 feet) • Tilted to face south, and typically

Slide 5: Ground Mount Solar PV Systems
Ground Mount Solar PV Systems • Generate zero emissions • Are considered permeable, and the ground around them remains natural grasses. • Generate no noise, and the panels are designed to absorb light, generating little to no glare • Preserve land from more intensive development. Page 5 l © 2016 Ame

Slide 6: Ground Mount Solar PV Systems
Ground Mount Solar PV Systems • Installed by Ameresco to avoid impacts to wetlands and other sensitive resources, including endangered species. • 6-9 Month Construction phase for 20MW • Minimal site traffic during operation,1-2 site visits per year • System removed at the end of 20 year term • Site

Slide 7: Candlewood Solar – Project Overview
Candlewood Solar – Project Overview • 20MW AC Fixed Tilt Solar Photovoltaic (PV) Installation > Installation on ~80 acres of land ~ 65 acres is currently wooded and will be cleared ~ 15 acres of already open field > Maximum height 8-10 feet > No audible noise or moving parts; no lights > No haza

Slide 8: Candlewood Solar – Project Overview Site Plan (cont.)
Candlewood Solar – Project Overview Site Plan (cont.) • Site location is close to Rocky River Substation and the associated transmission node • Site contains sufficient space for a 20 MW AC system to meet RFP requirements, while still maintaining adequate buffers. • Interconnection run to the substa

Slide 9: Candlewood Solar – Project Overview Environmental Benefits
Candlewood Solar – Project Overview Environmental Benefits • Annual energy generation of 34,000 MWh > Enough energy to power over 2,400 homes in one year > Offsetting CO2 emissions: – Equal to the consumption of >25 million pounds of coal OR – Equal to CO2 intake of over 22,000 acres of forest in on

Slide 10: Candlewood Solar – Project Overview Local Investment
Candlewood Solar – Project Overview Local Investment • Total Project Investment > $45-50 Million • Local Investment by the Project > $12-15 Million > System installation creates more than 100 jobs, local labor hired for civil/ site and electrical work > Development, Permitting, Consulting, and Legal

Slide 11: Connecticut Siting Council - Process
Connecticut Siting Council- Process • Petition Filing Process > Preparation of Siting Council Petition for Declaratory Ruling > Submission of Siting Council Petition for Declaratory Ruling > Stakeholder review and comment period > Site visits and public hearings > Determination of petition approval

Slide 12: Submittal Elements for CSC Approval
Submittal Elements for CSC Approval • Critical Environmental Issues Assessment • Phase I Environmental Site Assessment • Wetlands Delineation & Natural Habitat Assessment • Natural Diversity Database State Species Review • Visual Assessment • Air/ Water Quality Studies • Review by State Historic Pre

Slide 13: Rendering – From Candlewood Mountain Road
Rendering – From Candlewood Mountain Road Page 13 l © 2016 Ameresco, Inc. All rights reserved.

Slide 14: Questions
Questions Joel Lindsay, PE Mike Zimmer Director – Solar PV Project Development Senior Project Development Engineer jlindsay@ameresco.com mzimmer@ameresco.com 508-661-2265 508-598-3056 Your Trusted Sustainability Partner.
Source: Internet Archive copy of ameresco.com
More decks from Ameresco, Inc.
Q3 2026 Earnings Presentation14 slides · Nov 9, 2026
Investor Presentation (November 2026)31 slides · November 2026
Q2 2026 Earnings Presentation15 slides · Aug 3, 2026
Investor Presentation (August 2026)34 slides · August 2026
Q1 2026 Earnings Presentation19 slides · May 4, 2026
Q4 2025 Earnings Presentation16 slides · Mar 2, 2026