Hillgrove Resources Limited · ASX:HGO

Hillgrove Resources — South Australian Resources and Energy Investment Conference 2006

26 slides from Hillgrove Resources's conference presentation, May 2, 2006

  1. Slide 1: Moving to Development

    Slide 1: Moving to Development

    Moving to Development South Australian Resouces and Energy Investment Conference 1-2 May 2006

  2. Slide 2: Hillgrove Resources: Focus Growth Commodities

    Slide 2: Hillgrove Resources: Focus Growth Commodities

    HILLGROVE RESOURCES Focus Growth Commodities Natural Gas ƒ Gunnedah Gas Project has >42% of Australian coal bed methane resources. ƒ Gas close to Australia’s largest population World Copper Consumption and GDP centre of Sydney/Newcastle/Wollongong. Per Capita, 1950-2010 3.5 ƒ Australia’s power produ

  3. Slide 3: Why South Australia?

    Slide 3: Why South Australia?

    KANMANTOO Why South Australia? ƒ One of the most prospective terrains in the world. ƒ Ideal for application of latest exploration techniques. ƒ Neglected historically. ƒ Gawler is vastly under explored major mines. ƒ New greenstone domains akin to the Eastern Goldfields of WA. ƒ Supportive State Gov

  4. Slide 4: State Setting

    Slide 4: State Setting

    KANMANTOO State Setting GAWLER CRATON ® Challenger Archaean to early Mesoproterozoic Cambrian to Late Carboniferous LJ =a Neoproterozoic a ® Operating Mines Intermet Tenement (31% Hillgrove owned) | Hillgrove Tenement ( STUART CURNAMONA PROVINCE, SHELF ) o 100 Kilometers HILLGROVE TENEMENT HOLDINGS

  5. Slide 5: Regional Setting

    Slide 5: Regional Setting

    KANMANTOO Regional Setting Tenement Boundary

  6. Slide 6: Kanmantoo Copper Gold Mine 2005

    Slide 6: Kanmantoo Copper Gold Mine 2005

    KANMANTOO Kanmantoo Copper Gold Mine 2005

  7. Slide 7: Potential Open Pit Operation

    Slide 7: Potential Open Pit Operation

    KANMANTOO Potential Open Pit Operation

  8. Slide 8: Resources

    Slide 8: Resources

    KANMANTOO Resources TYPE INDICATED INFERRED TOTAL Tonnes Cu Au Tonnes Cu Au Tonnes Cu Au Cu Au T % g/t T % g/t T % g/t Metal T Oz OXIDE 204,000 1.0 0.3 41,000 1.6 0.2 245,000 1.1 0.3 2,700 2,400 TRANSITIONAL 1,041,000 1.1 0.2 310,000 1.0 0.4 1,351,000 1.1 0.2 14,700 10,600 FRESH > - 9,673,000 1.1 0.

  9. Slide 9: Mine Corridor

    Slide 9: Mine Corridor

    KANMANTOO Mine Corridor IP with Drilling and Ore Blocks

  10. Slide 10: Simplified Interpreted Geology Map with Resource Model

    Slide 10: Simplified Interpreted Geology Map with Resource Model

    KANMANTOO Simplified Interpreted Geology Map with Resource Model Current resource calculated by Resource Evaluations in December 2004 stands at 18.37MT at 1.1% copper and 0.2g/t gold.

  11. Slide 11: Geological Map of Mine Area

    Slide 11: Geological Map of Mine Area

    KANMANTOO Geological Map of Mine Area

  12. Slide 12: Elevated Garnet Copper/Gold zone

    Slide 12: Elevated Garnet Copper/Gold zone

    KANMANTOO Elevated Garnet Copper/Gold zone with elevated Garnet

  13. Slide 13: Garnet

    Slide 13: Garnet

    KANMANTOO Garnet ƒ Garnet content of mineralisation averages 12%. ƒ Prices USD$100-$240 per tonne. ƒ Uses – water filtration, waterjet cutting, abrasive blasting. ƒ Annual global demand ~500,000tpa. ƒ Substitution for silica sand – 1.40mtpa in US alone. ƒ Target production ~50,000tpa. ƒ India produc

  14. Slide 14: Conceptual Pit Outline

    Slide 14: Conceptual Pit Outline

    KANMANTOO Conceptual Pit Outline

  15. Slide 15: Conceptual View of Potential Open Cut Mine

    Slide 15: Conceptual View of Potential Open Cut Mine

    KANMANTOO Conceptual View of Potential Open Cut Mine

  16. Slide 16: Indicative Timeline

    Slide 16: Indicative Timeline

    KANMANTOO Indicative Timeline Area Est. Cost Est. Duration Commencement (weeks) Base Line $ 125,000 57 Underway Environmental Study Pre-feasibility Study $ 1,261,000 42 Underway EIS $ 150,000 29 Sep 2006 Permits $ 21,000 41 Sep 2006 Definitive Feasibility Study $ 2,142,760 30 Nov 2006 Financing $ 12

  17. Slide 17: Prospect Map: Lead-Zinc

    Slide 17: Prospect Map: Lead-Zinc

    KANMANTOO Prospect Map “Lead - Zinc” Scale: 1:300,000

  18. Slide 18: New Magnetics

    Slide 18: New Magnetics

    New Magnetics 16126000 mN 16126000 mN 6124000 mN.... 6122000 mN 6120000 mN 6118000 mN 6116000 MN... 6114000 mN mBRUKUNGA ilometers Potential Target —- Interpretted Fold Axis Current TMI Image with Potential Targets and Interpretted Geology i HGO_06_034a.wor

  19. Slide 19: Communities and Stakeholders

    Slide 19: Communities and Stakeholders

    KANMANTOO Communities and Stakeholders ƒ We act with integrity, transparency and honesty. ƒ We recognise, respect and support the right of Kanmantoo’s local communities to be consulted: – Focus group meetings – Community meetings – Site tours, newsletters and community webpage. ƒ We aim to consult w

  20. Slide 20: Outstanding New Copper-Gold Development Opportunity

    Slide 20: Outstanding New Copper-Gold Development Opportunity

    KANMANTOO Outstanding New Copper-Gold Development Opportunity ƒ Inferred and Indicated Resource of 18.371 MT @ 1.1% cu and 0.2 g/t au (0.3 – 0.4 g/t projected) – 196,700T contained Cu and 104,500 ozs Au. ƒ Measured target of 20 MT for 8 year 2.5 MTPA – 27,550TPA Cu in cons. ƒ Low cost setting – rail

  21. Slide 21: 31% InterMet Resources

    Slide 21: 31% InterMet Resources

    HILLGROVE RESOURCES 31% InterMet Resources ƒ New Adelaide based exploration company focussed on the Gawler Craton. ƒ Exploration led by two ex-PIRSA geologists with vast experience in the area. ƒ 6,000 km² along Southern Margin of Gawler Range Volcanic Province – interpreted new IOCG province. ƒ Lar

  22. Slide 22: InterMet: Lake Gilles Gravity Targets

    Slide 22: InterMet: Lake Gilles Gravity Targets

    INTERMET Lake Gilles Gravity Targets

  23. Slide 23: Key People

    Slide 23: Key People

    HILLGROVE RESOURCES Key People Directors ƒ David Archer, Managing Director & Chairman – Founded Savage Resources Limited and PowerTel Limited ƒ Pearce Bowman, Non-executive Director – WMC copper executive, SECV CEO ƒ John Quirke, Non-executive Director – Former Senator, SA Member of Parliament ƒ Ron

  24. Slide 24: Capital Structure

    Slide 24: Capital Structure

    HILLGROVE RESOURCES Capital Structure Ordinary Shares HGO 181.1 million Options – 20 cents 31/12/06 HGOOA 38.1 million Options – 30 cents 31/01/09 Unlisted 7.5 million Options – other expiry - ESOP Unlisted 7.1 million Options – other expiry - Sempra Unlisted 8.0 million Market Cap (@ 30 cents per s

  25. Slide 25: Investment Summary

    Slide 25: Investment Summary

    HILLGROVE RESOURCES Investment Summary Gunnedah Gas ƒ Largest on shore resource of gas. ƒ Cooper Basin in decline. ƒ 9 well $12.0M production development in 2006. ƒ Target 0.1-0.3 TCF P2 reserves Q4 ’06 for gas sales contracts. ƒ Tightening gas supply / demand balance post 2006. ƒ Gunnedah Gas is th

  26. Slide 26: Disclaimer

    Slide 26: Disclaimer

    DISCLAIMER This presentation may contain forward looking statements that are subject to risk factors associated with copper, gold and gas businesses. It is believed that the expectations reflected in these statements are reasonable but they may be affected by a variety of variables and changes in un