    The Tata Power Company Limited Investors’ Meet - February 2009 1

  2. Slide 2: Disclaimer

    Disclaimer Certain statements made in this presentation may not be based on historical information or facts and may be “forward looking statements”, including those relating to The Tata Power Company Limited’s general business plans and strategy, its future outlook and growth prospects, and future d

  3. Slide 3: Agenda

    Agenda • Part A: Overview of Tata Power • Part B: Power Business – Section 1: Generation – Section 2: Fuel & Logistics – Section 3: T & D – Section 4: Power Trading • Part C: Other Businesses • Part D: Financial Performance • Part E: Sustainability 3

  4. Slide 4: Part A: Overview of Tata Power

    Part A: Overview of Tata Power 4

  5. Slide 5: A Tata Company

    «ip TATA A Tata Company 6% Largest Companies Tata Moto 22% 23% FY 2008 Tata Steel i Rs 251,543 cr Information Technology 3 62.5bn Tata Consultancy Services a *3% VSNL Materials Tata Chemicals 7% 4% 2% Tata Tea Services Tata Teleservices Profits FY 2007 Tata AutoComp Systems 40% Rs 21,578 or $5.4 bn

  6. Slide 6: Tata Power: Introduction

    Tata Power: Introduction • Largest private, integrated utility company in India today with presence across the value chain in fuel, generation, T&D and trading • Founded in 1906, to supply hydro-electric power to Mumbai. Set-up thermal generation in Trombay in 1960s • Expanded outside Mumbai with IP

  7. Slide 7: Pioneer in Power Sector

    Pioneer in Power Sector First 800 MW thermal unit First pump storage unit in the country of 150 MW Capacity First to Introduce SCADA and Fibre Optic ground wire communication Flue Gas De-sulphurisation plant using 220 kV sea water Cable Transmission 220 kV Network transmission Computerized lines in

  8. Slide 8: Existing Presence in Power Sector

    Existing Presence in Power Sector Tala Transmission NDPL Jojobera 428 MW Samana 29 MW Haldia 90 / 120 MW Trombay 1330 MW Supa 17 MW Mumbai Distribution Mumbai Transmission Khandke 51 MW Hydro 447 MW Bramanvel 11 MW Thermal (1839 MW) Belgaum 81 MW Gadag 16 MW Hydro (471 MW) Wind (124 MW) Other Projec

  9. Slide 9: Tata Power Group – Major Companies

    Tata Power Group – Major Companies Tata Power Subsidiaries Joint Ventures Associates Coastal Gujarat Tata BP Solar Ltd 100% Power Ltd 49% 30% KPC Tata Power Trading Tubed Coal 100% 40% Company Ltd` Mine Ltd 30% Arutmin 100% Trust Energy Mandakini Coal Resources Pte Ltd 33% Mine Ltd 74% Maithon Power

  10. Slide 10: Businesses

    • Trombay 14, 25 • Hydro 14, 32 • Jojobera 23 Businesses • Belgaum 14 • Haldia 27 • Wind Farm 33-35,60 • Solar PV 49 • Mundra Division Generation • Maithon • Tata Steel JV (IEL) Other Entities • Tata BP Solar Transmission • Mumbai 42 • Tala Power Business Distribution • Mumbai 42 • Delhi • Tata Powe

  11. Slide 11: Part B: Power Business

    Part B: Power Business – Section 1: Generation – Section 2: Fuel & Logistics – Section 3: T & D – Section 4: Power Trading 11

  12. Slide 12: Generation: Business Models

    Generation: Business Models 12

  13. Slide 13: Impact of New CERC Norms

    oe Impact of New CERC Norms TATA Parameter Before After Return on Equity 14% (post tax) * 15.5/(1-t) (pre-tax) - 17.481% (MAT) - 23.481% (Normal) * 0.5% additional for timely project completion Depreciation * 3.6% * 5.28% for first 12 years (No AAD) * AAD * Balance equally spread over life (~2%) Lon

  14. Slide 14: Tata Power: Existing Operations

    Tata Power: Existing Operations Mumbai Licence Area (1777 MW) Trombay - Thermal Hydro Power Generation Unit 4 150 MW Oil & Gas Khopoli 72 MW Unit 5 500 MW Oil, Coal & Gas Bhivpuri 75 MW Unit 6 500 MW Oil & Gas Bhira 300 MW Unit 7 180 MW Gas Total 447 MW Total 1330 MW Wind 124 MW Haldia 90 MW Jojober

  15. Slide 15: Thermal Projects Under Implementation

    Thermal Projects Under Implementation Maithon1050 MW Mundra 4000 MW Jojobera/Jamshedpur 240 MW Haldia 30 / 120 MW Trombay 250 MW Thermal (5570 MW) 15

  16. Slide 16: Mundra UMPP

    Project Capacity • 4000 MW (5 x 800 MW) Ownership Structure • 100% subsidiary: Coastal Gujarat Power Limited Business Model • Case 2 Customers • Gujarat (1805 MW), Maharashtra (760 MW), Punjab (475 MW), Haryana (380 MW), Rajasthan (380 MW) Funding • Project Cost: Rs 17,000 Crore (D/E: 75:25) • Finan

  17. Slide 17: Mundra UMPP

    Project Milestone • Over 13% work already completed Construction • Structural erection is in progress for two boiler units and civil work is Activities progressing well at site On-site • Over 2500 people already located on site Funding • CGPL completed all pre-disbursement conditions and received it

  18. Slide 18: Mundra - Boiler and TG Building

    Mundra - Boiler and TG Building 18

  19. Slide 19: Mundra - Cooling Water Conduits below TG Rafts

    Mundra - Cooling Water Conduits below TG Rafts 19

  20. Slide 20: Maithon

    Project Capacity • 1050 MW (2 x 525MW) Ownership Structure • Maithon Power Limited 74: 26 JV of Tata Power and Damodar Valley Corporation Business Model • Regulated Customers • DVC (300 MW), NDPL (300 MW), WBSEB (150 MW), PSEB (300 MW) Funding • Project Cost: Rs 4450 Crores • (D/E: 70:30) • Debt syn

  21. Slide 21: 400 KV Switchyard Column Casting

    Project Milestone • Over 21% of work completed Ordering • Ordering for all packages completed Construction • Column erection completed for Boiler Unit-1 Activity • Foundation completed for Boiler Unit-2 Fuel Supply • Coal linkage sanctioned. Active discussions on to sign Fuel Supply Agreements with

  22. Slide 22: Unit 1- Erection of column & roof girder

    Unit 1- Erection of column & roof girder Unit - 2 Foundation work Unit 1- Column casting in progress for TG deck slab. Unit 1- Mill Bunker 22

  23. Slide 23: Captive Power Plants

    JAMSHEDPUR (PH #6) JOJOBERA (Unit #5) Project Capacity • 120 MW • 120 MW Ownership Structure • IEL (74:26 JV of Tata • IEL Power and Tata Steel) Business Model • CPP • CPP Funding • Project Cost: Rs 490 Crores • Project Cost: Rs 620 Crores • D/E 70:30 • D/E 70:30 Completion • March 2009 • December 2

  24. Slide 24: Jamshedpur (PH #6) – Site Photographs

    Jamshedpur (PH #6) – Site Photographs TG Rotor erection IDCT Commissioned 24

  25. Slide 25: Trombay Unit 8

    Project Capacity • 250 MW Ownership Structure • Tata Power Division Business Model • Regulated + Merchant Funding • Project Cost: Rs 1066 Crore • D/E 70:30 Completion • Synchronized in January 2009 • Commissioning by March 2009 Project Description • Fuel: Imported coal Trombay Unit 8 25

  26. Slide 26: Trombay (Unit 8) – Site Photographs

    Trombay (Unit 8) – Site Photographs 26

  27. Slide 27: Haldia

    Project Capacity • 120 MW (2 x 45 MW + 30MW) Ownership Structure • Tata Power Division Business Model • Merchant and Regulated Customers • Hoogly Metcoke, PPA with Tata Power Trading and WBSEDCL Funding • Project Cost Rs 605 Crores • D/E 70:30 Completion • 1st two 45MW units commissioned in August ‘

  28. Slide 28: Haldia – Site Photographs

    Haldia – Site Photographs 2 1 TG Unit # 1 & 2 in operation Boiler # 3 – 2 under erection 28

  29. Slide 29: Projects in Pipeline

    Projects in Pipeline Total 5670 Planning & development activities initiated 29

  30. Slide 30: Captive Coal Blocks

    Captive Coal Blocks Mandakini Coal Block • 7.5 MTPA (jointly allotted with Jindal Photo Film and Monnet Ispat & Energy - each JV Partner having a share of 2.5 MTPA) at Dist. Angul, Orissa • Submission of EIA Report: Jan / Feb ‘09 • Approval of mining plan by MoC: Jan / Feb ‘09 • Start of Production:

  31. Slide 31: Generation Capacity (Tata Power Group)

    Generation Capacity (Tata Power Group) Tata Power - Capacity 14000 12000 10000 5200 8000 Capacity in MW 6000 3075 Added in the Year 1125 7398 Opening Capacity 4000 220 613 4323 2000 2365 2365 2978 3198 0 2008 2009 2010 2011 2012 2013 Year Ended Mar 31 31

  32. Slide 32: Hydro Electric Power

    Hydro Electric Power • Oldest and one of the largest private sector players with capacity of 447 MW • Several awards and recognitions – Bhira Pump Storage Scheme received the CEA Silver Shield • Agreed to take 26% equity stake in 114 MW Dagachhu Hydro Electric Power Project being developed by The Ro

  33. Slide 33: Initiatives In Renewables

    Initiatives In Renewables • 124 MW operational • 72 MW to be commissioned – 52 MW by March ’09, 20 MW by April ‘09 • 300 MW being additionally explored • Developing a 3 MW grid connected solar PV farm in Maharashtra • Evaluating potential for concentrated solar thermal (CST) generation • Signed MoU

  34. Slide 34: Wind Farms

    Installed Capacity • 124 MW Project Under • 73 MW Implementation (35 MW Karnataka, 21 MW Gujarat, 17 MW Maharashtra) Ownership Structure • Tata Power division Business Model • Regulated Funding • Project Cost: Rs 633 Crores Completion • March - April 2009 Project Description • Turnkey projects by En

  35. Slide 35: Wind Projects Under Implementation

    Wind Projects Under Implementation Samana 21 MW Sadawaghapur 17 MW Gadag 35 MW Wind (73 MW) 35

  36. Slide 36: Part B: Power Business

    Part B: Power Business – Section 1: Generation – Section 2: Fuel & Logistics – Section 3: T & D – Section 4: Power Trading 36

  37. Slide 37: Fuel

    Fuel ears y Fuel supplies 0-25 fo r new projects fo r2 37

  38. Slide 38: Indonesian Coal Mines

    Indonesian Coal Mines Deal Highlights Performance • Acquired 30% equity stake in KPC and • Quantity mined in Jan-Sep 2008 ~ Arutmin from PT Bumi Resources, 37MT Indonesia • Average realised price per tonne (FOB) • Acquisition value of USD 1.1 bn – US$70.5 (Jan-Sep 2008) • Off-take contract with KPC

  39. Slide 39: Trust Energy Asia Pte Limited

    Trust Energy Asia Pte Limited • SPV incorporated in Singapore for owning ships to meet shipping requirements and trading in fuels • Present shipping requirements of 8-9 vessels for Mundra • To be met through a combination of long term charters and out right purchases – 3 LT charters signed and 2 Kor

  40. Slide 40: Part B: Power Business

    Part B: Power Business – Section 1: Generation – Section 2: Fuel & Logistics – Section 3: T & D – Section 4: Power Trading 40

  41. Slide 41: Distribution Opportunities

    Distribution Opportunities • Second License – parallel licensing unlikely to happen soon • Privatization – not much progress in replicating Delhi model • Outsourcing – opportunity for marginal players • Franchisee Opportunity – window is open for private participation 41

  42. Slide 42: Mumbai: Transmission and Distribution

    Mumbai: Transmission and Distribution • 23,000 customers with 2500 MUs of sales (mostly to high value bulk consumers) • 17 receiving and distribution stations, 318 consumer substations and 1335 Kms of HT & LT Cable network. Total asset base over Rs 1400 crores • MERC regulated tariff with 16% RoE on

  43. Slide 43: North Delhi Power Limited (NDPL)

    North Delhi Power Limited (NDPL) • 51:49 JV of Tata Power and Delhi Vidyut Praday Nigam (Govt. of Delhi) • Over 1 million consumers with 5000 MUs consumption and net asset base of over Rs 1800 Crores • Assured returns upto 16%, plus incentives on loss reduction YTD FY09: Sales – Rs 18.14 billion, PA

  44. Slide 44: Powerlinks Transmission Limited

    Powerlinks Transmission Limited • 51:49 JV of Tata Power and Power Grid Corporation of India • 1200 km 400 kV double-circuit transmission lines • Transmits power from Tala Hydroelectric Project and Eastern/North-Eastern region to New Delhi and adjoining areas. • Total investment of Rs 1560 Crores (D

  45. Slide 45: Part B: Power Business

    Part B: Power Business – Section 1: Generation – Section 2: Fuel & Logistics – Section 3: T & D – Section 4: Power Trading 45

  46. Slide 46: Tata Power Trading Company Limited

    Tata Power Trading Company Limited TPTCL Sales (MU) Role 6750 7000 • Identify and tap surplus power source in 6000 the country • Locate a customer who is ready to pay 5000 4500 in cash the for power at its landed cost 4000 inclusive of transmission losses MUs 3000 3000 • Settle commercial terms on b

  47. Slide 47: Part C: Other Businesses

    kd TATA Part C: Other Businesses

  48. Slide 48: Strategic Electronics Division (SED)

    Strategic Electronics Division (SED) • Revenues of Rs.59 crores (Mar 08) against Rs.51 crores during the previous year. • Current revenue contributors include electronics system for the Rocket Launchers, Fire Control Computers for Arjun Tank and Command and Control systems. • Future revenue to come

  49. Slide 49: Tata BP Solar

    Tata BP Solar • 51:49 JV between BP Solar and Tata Power • Market leader in Solar Photovoltaic technology in India with turnover of Rs 660 Crores • Nearly 75% of sales from exports largely to Europe and USA • India’s first Polycrystalline Solar cell manufacturing plant and 45 MW module manufacturing

  50. Slide 50: Part D: Financial Performance

    Part D: Financial Performance 50

  51. Slide 51: Financials - Year Ended March 31, 2008

    Financials - Year Ended March 31, 2008 Year Ended Rupees in Billions 31-Mar-08 31-Mar-07 Operating Income 59.16 47.15 Operating Expenditure (49.79) (39.92) Operating Profit 9.37 7.23 Interest & Finance charges (1.42) (1.89) Depreciation (2.91) (2.92) Other Income 4.66 3.44 Profit Before Tax 9.70 5.8

  52. Slide 52: Financials – Nine Months ended December 31, 2008

    Financials – Nine Months ended December 31, 2008 Quarter Ended Nine Months Ended Rupees in Billions 31-Dec- 08 31-Dec-07 31-Dec-08 31-Dec-07 Operating Income 17.77 14.19 57.62 42.81 Operating Expenditure (15.17) (11.51) (49.21) (34.98) Operating Profit 2.60 2.69 8.41 7.84 Interest & Finance charges

  53. Slide 53: Financials - Consolidated

    Financials - Consolidated Year Ended March 31, 2008 Year Ended Rupees in Billions 31-Mar-08 31-Mar-07 Operating Income 108.91 64.76 Operating Expenditure (87.70) (53.85) Operating Profit 21.21 10.91 Interest & Finance charges 4.88 2.83 Depreciation 5.59 4.15 Other Income 4.79 2.67 Profit Before Tax

  54. Slide 54: Tata Power – Financials (Standalone)

    Tata Power – Financials (Standalone) Annual Sales (MU) Profit After Tax (In Billion Rs.) EPS (in Rs.) Net Worth (In Billion Rs.) 54

  55. Slide 55: Dividend History

    Dividend History Earnings (Rs.) 40 40 Dividends (Rs.) Payout ratio (%) 30 30 20 % Rs. 20 10 10 0 0 2003 2004 2005 2006 2007 2008 55

  56. Slide 56: Funding by Tata Power - Projects under Implementation

    Funding by Tata Power - Projects under Implementation Own Funds Debt (Rs.5,100 Crores) (Rs.18,000 Crores) • Internal accruals: Rs.2800 Crores • Domestic loans through domestic • Remainder financial institutions, banks and – Disinvestment of various holdings capital markets or assets • Foreign loans

  57. Slide 57: Part E: Sustainability

    kd TATA Part E: Sustainability

  58. Slide 58: Climate Change

    Climate Change • Trombay SO2 emission of 24TPD (1330MW) - one of the most stringent • Forum of 46 global companies: New policy framework on Combating Climate Change (3C) • Carbon Footprint for the Company completed • Sustainability Council formed - 17 CDM Projects Identified • Utilization of waste h

  59. Slide 59: Renewable and Clean Coal Technology

    Renewable and Clean Coal Technology • Solar Concentrated Thermal (SCT) • Geo Thermal energy • Coal Bed Methane (CBM) • Coal beneficiation technologies

  60. Slide 60: Wind Farms

    Wind Farms • Existing installed Renewable plants • CDM host country approval received for the 62 MW of the new wind farms • 73 MW of wind power projects under implementation • 17 MW in Maharashtra, 21 MW in Gujarat, 35 MW in Karnataka.

  61. Slide 61: Demand Side Management

    Demand Side Management • DSM Workshop conducted for all utilities in Maharashtra • Energy conservation awareness campaigns for Customers & School • Launched “I will, Mumbai will” (joint Adv. campaign with other Dist. Lic.) • Tata Power Energy Club formed for curbing energy wastage

  62. Slide 62: Human Resource Management

    Human Resource Management • Long Term Settlement with the Union signed • Succession Planning process implemented • Competency Development exercise in progress • Organization Transformation Initiatives are being implemented