Hydro One Limited · TSX:H

Hydro One — Hydro One Networks — Corporate Update (March 2008)

18 slides from Hydro One's corporate update, Mar 4, 2008

  1. Slide 1: Supply to Essex County Class Environmental Assessment

    Hydro One Networks Supply to Essex County Class Environmental Assessment Yury Tsimberg Manager, Asset Strategies & Standards Brian McCormick, Manager, Environmental Services & Approvals March 4, 2008 1

  2. Slide 2: Purpose of this Meeting

    Purpose of this Meeting • Introduce an upcoming Class Environmental Assessment (EA) project for new electricity transmission infrastructure in Essex County • Seek your input on the proposed facilities and study areas • Become acquainted with you and local issues • Invite you to participate in the Cl

  3. Slide 3: Who is Hydro One?

    Who is Hydro One? • Owner / operator of Ontario’s high voltage transmission network, serving large industrial users & local distribution companies (LDCs) • Distribution network serves 1.3 million customers mainly in rural and small urban communities, incl. smaller LDCs • Province of Ontario is sole

  4. Slide 4: Hydro One's Role in System Development

    Hydro One’s Role in System Development • Implement transmission solutions • Obtain Ministry of Environment and Ontario Energy Board approvals as required for new facilities or facility upgrades • Conduct public and stakeholder consultation in accordance with Environmental Assessment Act requirements

  5. Slide 5: The Need for New Transmission Infrastructure

    The Need for New Transmission Infrastructure • Need for new transmission capacity in the Windsor – Essex region confirmed by Ontario Power Authority in consultation with local distribution companies and Hydro One 5

  6. Slide 6: Supply to Essex County Class Environmental Assessment Project

    Supply to Essex County Class Environmental Assessment Project • First of two projects Hydro One will undertake to address identified needs in Essex County • A new transformer station (TS) and associated transmission line facilities or upgrades are required to relieve overloading of the 115 kV circui

  7. Slide 7: Option 1

    Option 1 Study Area for Alternative 1 Supply to Essex County: COUNTY:RD 22 a Belle River COUNTY:RD 2 Existing Transmission Lines COUNTY RD 34 eo 3 NOTRE DAME ST £ y BELLE RIVER TS & 74 a § j meague 3. | " = 8 8 3 | \—e a a | | BELLE RIVER JCT 2 8 LAUZON TS % DIVISION RO ~ cs COUNTY:RD 42 a & ; *, &

  8. Slide 8: Option 2

    Option 2 Supply to Essex County: Study Area for Alternative 2 Ward Juuso? a FOUNTW'RD 22 Belle River recumsen Ro—~_3 " e\ % NOTRE DAME ST & 2 COUNTYRD 2: ve BELLE RIVER TS = a me 5. : en LAUZON TS DIVISION RO. _ BELLERIVERSCT fw 5 é a e 5 8 oe 2 4 WOODSLEEJCT == cABANARD A o 3 a § 1 CUsty, 3 Z ; ——3

  9. Slide 9: Project Approval Requirements

    Project Approval Requirements • Ontario Environmental Assessment Act – The facilities are subject to provincial Environmental Assessment Act approval in accordance with the Class Environmental Assessment for Minor Transmission Facilities • Ontario Energy Board Act – “Leave to Construct” approval is

  10. Slide 10: Target Project Timelines

    Target Project Timelines • Initiate Class EA March/April 2008 and Public Consultation • Identify Preferred Spring 2008 Transmission Option • Identify preferred TS site Spring/Summer 2008 and transmission line route • Anticipated Class EA and Fall 2008 OEB approvals • Start of construction Spring 200

  11. Slide 11: Class EA Process

    Class EA Process • In 1978, a Class EA for minor transmission facilities was developed and approved by the Ontario Ministry of the Environment (MOE) and implemented by the former Ontario Hydro. The Class EA was updated in 1992. • The Class EA process is an effective way of ensuring that minor transm

  12. Slide 12: Class EA Process (continued)

    Class EA Process (continued) • If no concerns are expressed during the public review period, the project is considered acceptable. Hydro One then files a final ESR with the MOE and approval is granted. • If concerns are expressed during the review period, Hydro One will attempt to resolve them in or

  13. Slide 13: Environmental Planning Process

    Environmental Planning Process • The potential effects of the project will be identified during project planning and design as part of the Class EA process, including potential effects on the: – Natural Environment – Cultural Environment – Agricultural Environment – Socio-economic Environment • Key

  14. Slide 14: Development of Criteria

    Development of Criteria • Consider potential effects of the project on the components of the environment • Develop evaluation criteria and indicators where applicable 14

  15. Slide 15: Examples of Evaluation Criteria

    Examples of Evaluation Criteria • Natural environment – Environmentally significant areas (significant habitat, species at risk); forest resources (wooded areas) • Cultural environment – Built heritage (built and landscape features) • Agricultural environment – Soil capability and land use; specialt

  16. Slide 16: Public Consultation Process

    Public Consultation Process • Notification of study commencement on-going communication with municipal officials, potentially- affected property owners and other key stakeholders (e.g. government agencies, MPPs, First Nations and interested groups) throughout the EA and OEB approvals processes • Int

  17. Slide 17: Scheduled Public Consultation Activities

    Scheduled Public Consultation Activities • Project announcement in local newspapers – After Easter weekend • Public Information Centres (PICs) at key stages – First round of PICs in mid-April – Second round when preferred option is determined • Opportunity for public participation in Ontario Energy

  18. Slide 18: How can you help?

    How can you help? • Contribute planning/land use data and other information to assist project team in evaluating the project options • Provide property owners mailing information to assist with public notification • Participate at public information centres in your communities • Contact members of t

Hydro One Networks — Corporate Update (March 2008) on 6ix