Q1 2026
Q1 2026 HIGHLIGHTS
All amounts are in U.S. dollars unless otherwise noted.
References to "C$" are to Canadian dollars.
Strengthened capital structure and liquidity
Closed C$165.0 million equity financing
Successfully issued $350.0 million of senior secured bonds
Fully repaid $220.0 million of project debt
*Specials are defined as stones above 10.8 carats.
UGP advancement
Updated feasibility study confirms total capital cost of
$779.2 million, with $472.4 million already invested.
Strong safety record
The UGP achieved 2,249 lost-time injury free days during the quarter
High-value recoveries
100 Specials* recovered in Q1, including five diamonds greater than 100 carats and one exceeding 300 carats.
Financial performance
Q1 2026 revenue of $21.8 million, reflecting a higher proportion of stockpile material.
BOND FINANCING
Issued $350.0 million bond with a fixed coupon of 12.50% per annum, payable quarterly.
Includes a tap option which allows for an additional
$50.0 million to be issued on the same terms, bringing maximum issuable amount to $400.0 million
Option to establish a Revolving Credit Facility (RCF) of up to $50.0 million
Neither the tap option nor the RCF have been exercised or established as at March 31, 2026.
Net proceeds from the bond issuance have been applied to fully repay the Company's previous $220.0 million senior secured project finance facilities.
Remaining proceeds will be used to fund a dedicated debt service retention account covering two years of interest on the Bonds and to support the continued development of the UGP.
Fancy purple-pink internally flawless 20.31 carat cushion cut from Karowe
OPERATIONS UPDATE
Open pit mining activities at Karowe were temporarily suspended during the first quarter due to high and unseasonal rainfall, resulting in elevated water levels within the pit.
Operations resumed in the open pit in March.
Un-interrupted processing operations were maintained by utilizing run-of-mine stockpiled material.
The increased reliance on run-of-mine stockpiles, which are generally lower in grade and diamond quality, contributed to a softer revenue performance in Q1 2026, contributing to a higher proportion of smaller, lower-value stones recovered and sold during the quarter.
FINANCIAL & OPERATIONAL RESULTS
Revenue (millions)$21.8 $30.3
Q1 2026 Q1 2025
Operating expenses (millions)$21.6 $14.0
Q1 2026 Q1 2025
Operating costs ($/ tonne)$24.72 $23.41
Q1 2026 Q1 2025
Ore mined (tonnes)390,539
Ore processed (tonnes)718,804 676,626
Carats sold79,744 72,871
6,231
Q1 2026 Q1 2025
Q1 2026 Q1 2025
Q1 2026 Q1 2025
HIGH-VALUE RECOVERIES
Recovered 100 Specials* in Q1 2026, including five diamonds greater than 100 carats and one exceeding 300 carats.
Specials equated to 4.3% (Q1 2025: 5.6%) of the weight percentage of total recovered carats from ore processed during Q1 2026.
A total of 72,061 carats (Q1 2025: 90,500 carats) recovered in the quarter.
Notable recovery of a 36.92 carat blue Type IIB diamond through the X-ray Transmission machines at Karowe from ore sourced from unprocessed run-of-mine stockpile material, reinforcing Karowe's reputation for rare, high-value stones.
*Specials are defined as stones above 10.8 carats.
36.92 carat blue Type IIB diamond, recovered in March 2026.
SAFETY LEADERSHIP
Continued strong safety record, with the UGP achieving 2,249 lost-time injury free days and a project-to-date TRIFR of 0.54. Rolling 12-month Total Recordable Injury Frequency Rate (TRIFR) of 0.32.
No lost time injuries at Karowe in Q1 2026.
Lucara has been recognized by the Botswana Chamber of Mines, winning three awards for safety performance
Awarded the AfriSAFE Mining Company of the Year for two years in a row
Recognized with the Mining Company of the Year - Safety, Health, Environment, Risk, and Quality (SHERQ) Excellence Award, awarded by S.H.E. On Standby in Botswana.
KAROWE UGP UPDATE
Updated feasibility study confirms total cost at completion of $779.2 million, including contingency.
As at March 31, 2026, $472.4 million had been incurred, with a further $117.7 million committed but not yet incurred.
From H1 2026 to H1 2028, processing will continue using a combination of open pit ore and run-of-mine stockpiles.
Significant de-risking following the completion of
shaft sinking activities in 2025.
UGP capital expenditures of $19.0 million in Q1 2026, primarily related to shaft equipping, lateral development, and surface infrastructure.
UGP PROGRESS
Advancement of lateral development, with a total of 1,245 metres completed from the ventilation shaft, ahead of the planned handover stage to the lateral development contractor.
Water intersections encountered were effectively managed through targeted grouting.
Shaft equipping was completed to surface at the production shaft, including installation of guides and buntons, followed by decommissioning of sinking infrastructure and commencement of headgear internal steel changeover works.
Lateral development contract awarded in Q4 2025 and onboarding of key personnel and mobilization activities commenced in Q1 2026.
Surface infrastructure works continued, including civil construction and procurement of long-lead ventilation fan components.
UGP PROGRESS
Evaporation pond Production shaft steel work for main conveyors
UGP PROGRESS
310-Level drift towards the ore body 310-Level ramp to 285-Level
UGP PROGRESS
285-Level site loading conveyor structure 285-Level ventilation shaft doors
LOOKING AHEAD
Strengthened capital structure and liquidity with closing of equity financing and successful bond issuance in Q1 2026.
Maintaining full year outlook, with revenue guidance remaining unchanged at $100.0 million to $130.0 million, supported by the return to open pit mining, with all other guidance parameters also reaffirmed.
Ongoing and consistent recovery of large, high-value diamonds from Karowe, including many of the world's largest.
Despite geopolitical uncertainty and evolving global tariff dynamics, demand for large, rare, high-quality diamonds remains comparatively resilient due to their scarcity, provenance, collectability, and appeal as hard luxury assets.
The Lesedi La Rona, recovered at Karowe, and cut and polished by Graff
2026 ANNUAL GUIDANCE
2026 Diamond Sales, Production, and Outlook 2026 full yearDiamond revenue (millions) $100 to $130
Diamond sales (thousands of carats) 340 to 360
Diamonds recovered (thousands of carats) 340 to 360
Ore tonnes mined (millions) Up to 0.6
Waste tonnes mined (millions) Up to 0.2
Ore tonnes processed (millions) 2.6 to 2.9
Total operating cast costs (per tonnes processed) $27.50 to $31.00 UGP capital expenditure Up to $110 million
Sustaining capital expenditure Up to $11.5 million Average exchange rate - Botswana Pula per USD 14.0
Contact
Suite 2800, Four Bentall Centre 1055 Dunsmuir Street
PO Box 49225
Vancouver, BC V7X 1L2
Tel: +1 604 674 0272
Email: [email protected]
LucaraDiamond.com | LUC.TSX | LUC.FNGM | LUC.BSE
1
| Attention: This is an excerpt of the original content. To continue reading it, access the original document here. |
