  1. Slide 1: Elk Valley Resources Sell-side analyst visit

    Slide 1: Elk Valley Resources Sell-side analyst visit

    Elk Valley Resources Sell-side analyst visit 26/27 June 2025

  2. Slide 2: Important notice

    Slide 2: Important notice

    Important notice Information preparation This document does not constitute or form part of any offer or invitation to sell or issue, or In preparing this document, Glencore has made certain estimates and assumptions that any solicitation of any offer to purchase or subscribe for any securities. This

  3. Slide 3: Agenda

    Slide 3: Agenda

    Agenda 1 EVR overview 2 Logistics and shipping infrastructure 3 Integration update 4 Health & Safety 5 Water quality 6 Planning and permitting – engagement with First Nations 7 Value Realisation 8 EVR: Forging a global mining leader 3

  4. Slide 4: EVR Overview

    Slide 4: EVR Overview

    EVR A GLENCORE COMPANY EVR Overview

  5. Slide 5: EVR Overview

    Slide 5: EVR Overview

    EVR Overview EVR is a leading producer of high- quality steelmaking coal from long-life assets in one of the best mining districts in the world Low cost/high margin • 1st quartile margin position • $108.3/t 2025E cash cost Long life assets with volume growth optionality • 30+ years: Fording River, G

  6. Slide 6: Fording River Operations

    Slide 6: Fording River Operations

    Fording River Operations Asset overview History/ • Fording River is a large-scale, long-life Life of Mine asset, incorporated in 1971 • Total Reserves (million tonnes): 350 • Total Resources (million tonnes): 2,850 • Planned mine life: c.40 years Production • Estimated saleable production capacity:

  7. Slide 7: Greenhills Operations

    Slide 7: Greenhills Operations

    Greenhills Operations Asset overview History/ • Greenhills is a non-unionized, long-life Life of Mine asset, operating since 1982 • Total Reserves (million tonnes): 180 • Total Resources (million tonnes): 770 • Planned mine life: c.35 years Production • Estimated saleable production capacity: 5.5 –

  8. Slide 8: Line Creek Operations

    Slide 8: Line Creek Operations

    Line Creek Operations Asset overview History/ • Line Creek was incorporated in 1981 Life of Mine • Total Reserves (million tonnes): 45 • Total Resources (million tonnes): 1,230 • Planned mine life: c.13 years Production • Estimated saleable production capacity: 3.5 – 4.0 Mtpa Projects • Constructing

  9. Slide 9: Elkview Operations

    Slide 9: Elkview Operations

    Elkview Operations Asset overview History/ • Elkview is a large-scale, long-life asset. Life of Mine Underground mining began in 1902 and progressed to open pit in 1969. • Total Reserves (million tonnes): 230 • Total Resources (million tonnes): 990 • Planned mine life: c.35 years Production • Estima

  10. Slide 10: Logistics and Shipping Infrastructure

    Slide 10: Logistics and Shipping Infrastructure

    Logistics and Shipping Infrastructure

  11. Slide 11: Logistics and Shipping Infrastructure

    Slide 11: Logistics and Shipping Infrastructure

    Logistics and Shipping Infrastructure Dedicated infrastructure offers reliability and optionality Shipping Infrastructure Rail Infrastructure • Contracts with Canada’s • Access to three terminals with two leading railways competitive access to Pacific markets • CN Rail and CPKC are • Flexibility to

  12. Slide 12: Integration Update

    Slide 12: Integration Update

    EVR A GLENCORE COMPANY Integration Update

  13. Slide 13: Integration update

    Slide 13: Integration update

    Integration update Successfully integrated into Glencore’s global coal business Strong second half 2024 performance – production (highest in three years) in line with original guidance Post acquisition performance consistent with Glencore expectations with a significant improvement in H2 2024 clean

  14. Slide 14: Health & Safety

    Slide 14: Health & Safety

    A GLENCORE COMPANY Health & Safety

  15. Slide 15: Health & Safety

    Slide 15: Health & Safety

    Health & Safety EVR regional Health & Safety performance High-potential incident frequency rate (HPRIFR) Total recordable injury frequency rate (TRIFR) Year-to-date 31 May 2025 Year-to-date 31 May 2025 HPRIFR TRIFR 2025 YTD: 0.63 2025 YTD: 4.74 ↓42% vs 2024 12 ↓46% vs 2024 4.1 4 Incidents YTD LTI 30

  16. Slide 16: Health & Safety

    Slide 16: Health & Safety

    Health & Safety EVR regional Health & Safety performance • EVR is in the process of implementing SafeCoal to help achieve our vision of getting every employee Home Safe, Every Day GCOM(1) • Glencore’s SafeCoal program is a Introduced across EVR in 2025 comprehensive safety program Trained over 1,300

  17. Slide 17: Water Quality

    Slide 17: Water Quality

    EVR A GLENCORE COMPANY Water Quality

  18. Slide 18: Elk Valley Water Quality Plan (EVWQP)

    Slide 18: Elk Valley Water Quality Plan (EVWQP)

    Elk Valley Water Quality Plan (EVWQP) Selenium and nitrate levels are stabilizing and now reducing downstream of treatment Water quality challenges in the Elk Valley are connected to the long history of mining in the region The mining process generates large quantities of leftover rock that contains

  19. Slide 19: Water quality

    Slide 19: Water quality

    Water quality Water treatment facilities: >US$1 billion invested to date West Line Creek Elkview Fording River South Fording River North Active Water Treatment Saturated Rock Fill Active Water Treatment Saturated Rock Fill Capacity of 7.5 million Capacity of 20 million Capacity of 20 million Capacit

  20. Slide 20: Water quality

    Slide 20: Water quality

    Water quality Water treatment construction projects: +50 million litres per day Remaining estimated spend of c.US$500M by year-end 2027 Full compliance projected in(1): • Mid-2027: Selenium • Mid-2028: Nitrate These facilities are removing between 95% and 99% of selenium from treated water. Selenium

  21. Slide 21: Planning and permitting

    Slide 21: Planning and permitting

    A GLENCORE COMPANY Planning and permitting

  22. Slide 22: Planning and permitting

    Slide 22: Planning and permitting

    Planning and permitting Regulatory approvals Experienced in-house team manages the portfolio of required mine development, operational and environmental permit applications Strong relationships with regulatory Pre-Application Screening​ Review Permit Drafting Decision Duration: 9 – 24 Duration: 1 –

  23. Slide 23: Planning and permitting

    Slide 23: Planning and permitting

    Planning and permitting Engagement with Indigenous Peoples: Ktunaxa Four Ktunaxa First Nations • Organized under the Ktunaxa Nation Council (KNC) • Non-treaty Nations • Total population is ~1,300 people • One of the four Ktunaxa First Nations has exerted independence for the purposes of some regulat

  24. Slide 24: Key permits: Fording River Extension (FRX)

    Slide 24: Key permits: Fording River Extension (FRX)

    Planning and permitting Key permits: Fording River Extension (FRX) Seeking approvals for a planned production start in 2030 • Environmental Assessment and permitting required to mine an additional 281 million tonnes, significantly extending Fording River Operations’ mine life • Utilizing existing equ

  25. Slide 25: Key permits: Cougar (Greenhills)

    Slide 25: Key permits: Cougar (Greenhills)

    Planning and permitting Key permits: Cougar 5 (Greenhills) Approvals expected in 2025: permit applications submitted and nearing completion of regulatory review • Permit to develop Cougar Phase 5 pit, extending mine life by c.5 years (18.5 million tonnes) • Utilizing existing equipment and infrastru

  26. Slide 26: Key permits: Cougar 8/9 (Greenhills)

    Slide 26: Key permits: Cougar 8/9 (Greenhills)

    Planning and permitting Key permits: Cougar 8/9 (Greenhills) Planning for regulatory approvals by 2029 • Environmental Assessment amendment and permits required to mine 64 million tonnes in Cougar Phase 8 and 9 pits, extending mine life for Greenhills Operations by more than 15 years • Utilizes exis

  27. Slide 27: Value Realisation

    Slide 27: Value Realisation

    c 2) . t A GLENCORE COMPANY R | .

  28. Slide 28: Value realisation

    Slide 28: Value realisation

    Value realisation Margin uplift on a go forward basis US$9.5/t • Improvement of sales book, including review of contract specifications • Leveraging Glencore’s marketing expertise and shipping reach Marketing and Logistics • Co-loading cape vessels to reduce freight costs • Sustained lower demurrage

  29. Slide 29: Value realisation

    Slide 29: Value realisation

    Value realisation Operational deep dive – targeting additional c.US$185M of annual value uplift Processing Quality management Increase particle size Sampling to meet UCL Reduce magnetite framework: Additional distribution: Coarsen feed to targets (Ash/TM): Maximise consumption: Barometer of margin t

  30. Slide 30: Project governance

    Slide 30: Project governance

    Planning and permitting Project governance Project Governance Going Historical Project Challenges Forward Projects moving through Refined project Inconsistent application of gates with suboptimal Group wide project classifications and stage previous framework definition and not meeting management st

  31. Slide 31: A leading producer in one of the world's best mining districts

    Slide 31: A leading producer in one of the world's best mining districts

    A leading producer in one of the world’s best mining districts

  32. Slide 32: EVR: Forging a global mining leader

    Slide 32: EVR: Forging a global mining leader

    EVR: Forging a global mining leader Leading producer of high-quality steelmaking coal from long-life assets in one of the world’s best mining districts Safety is our top priority Water quality: EVR has made significant progress implementing the Elk Valley Water Quality Plan. Water treatment faciliti