    OM HOLDINGS LIMITED (ARBN 081 028 337) For personal use only NO. OF PAGES LODGED: 19 20 April 2011 Company Announcements Office ASX Limited 4th Floor 20 Bridge Street SYDNEY NSW 2000 Dear Sir/Madam CHIEF EXECUTIVE OFFICERS PRESENTATION Please be advised the Chief Executive Officer will be presenting

  2. Slide 2: Background Profile of OM Holdings Limited

    BACKGROUND PROFILE OF OM HOLDINGS LIMITED OMH listed on the ASX in March 1998 and has its foundations in metals trading – For personal use only incorporating the sourcing and distribution of manganese ore products and subsequently in processing ores into ferro-manganese intermediate products. The OM

  3. Slide 3: Annual General Meeting – CEO Presentation

    For personal use only Annual General Meeting – 20 April 2011 CEO Presentation 1

  4. Slide 4: OMH Investment Highlights

    OMH Investment Highlights For personal use only 1 A globally integrated pure play manganese company listed on the ASX 2 Long life, high grade Mineral Resources with a pipeline of exploration projects 3 Vertically integrated business model across the entire value chain - from mining to marketing 4 Hi

  5. Slide 5: 2010 Highlights

    2010 Highlights For personal use only Improved safety performance, record Bootu Creek ore tonnes mined and product produced Operations OMQ sinter plant commissioned and solid alloy production despite Q4 power restrictions OMS total shipments in excess of1million tonnes, NFE and IFE marketing agencie

  6. Slide 6: FY 2010 – Summary of Key Financials

    FY 2010 – Summary of Key Financials For personal use only A$ million 2010 2009 Total Sales 307.5 280.3 EBITDA 68.3 35.3 NPAT 47.2 26.9 Operating Cash Flow 20.7 23.7 Dividends per Share 2.75 cents 3 cents Cash at Year End 42.1 79.7 4

  7. Slide 7: Strategic Objectives and Actions

    Strategic Objectives and Actions For personal use only Mission Statement: To become the world’s leading integrated manganese producer Strategic Actions: Maximize earnings Extract maximum value from mining, smelting and marketing operations Increase resources Expand our high grade ore resources organ

  8. Slide 8: OMH Operating Assets

    OMH Operating Assets For personal use only BOOTU CREEK MINE QINZHOU SMELTER SINGAPORE MARKETING High grade deposit, ~ 15 Capacity of 60kt of HCFeMn China market specialists – year mine life and 300kt of sinter experience and expertise Exploration potential on Strategic location - proximity Longstand

  9. Slide 9: Strategic Ore Investment in South Africa

    Strategic Ore Investment in South Africa For personal use only OMH investment in Ntsimbintle Mining and the world class Tshipi Manganese Project 26% Jupiter Mines Ltd. OMH Safika Resources Other BEE stakeholders Ntsimbintle 49.9% Tshipi é Ntle 50.1% Tshipi Manganese Mine 7

  10. Slide 10: Strategic Ore Investment in South Africa

    Strategic Ore Investment in South Africa For personal use only In South Africa’s Kalahari basin, the world’s largest high grade manganese ore resource High grade resources of 163 million tonnes at 37.1% Mn, 60+ year mine life at 2.4mtpa production Project CAPEX fully funded by the partners Open pit

  11. Slide 11: Strategic Alloy Investment in Malaysia

    Strategic Alloy Investment in Malaysia For personal use only OMH feasibility study for a Malaysian manganese sinter, alloy smelter and port complex Manganese ore Power Smelting + Sintering + Bootu Creek (Australia) Power is the 2nd major cost in Malaysia’s opportunity to become manganese alloy smelt

  12. Slide 12: Strategic Alloy Investment in Malaysia

    Strategic Alloy Investment in Malaysia For personal use only Rapidly changing market dynamics in favour of Malaysian project Strategic location to supply the Asian steel industry Competitively priced and reliable power supply Zero import duty and export tax on Manganese products Well-developed road

  13. Slide 13: Delivering on the strategy – the timetable

    Delivering on the strategy – the timetable For personal use only 2009 2010 2011 2012 Bootu operating strategy  optimised operating strategy – 42/38/35% grades 250ktpa SPP plant  1Mtpa ore production Organic Sinter Plant Phase 1  300kt sinter capacity +300ktpa sinter capacity feasibility 15 year m

  14. Slide 14: 2011 Outlook

    2011 Outlook For personal use only OMM – 1 million tonnes production target Operations OMQ – 60,000 tonnes of alloy and full capacity sinter production target OMS – equity and third party marketing, trading and distribution Tshipi site establishment, mine, plant, load out and siding construction Gro

  15. Slide 15: Operational Production Performance

    Operational Production Performance For personal use only Manganese Ore Output Volume 1,000 831.4 800 672.6 648.1 600 516.4 1000 kt 400 243.4 200 [-] 0 2005 2006 2007 2008 2009 2010 2011F Manganese Alloy Output Volume 60 45 39 38 37 40 33 26 60 kt 20 0 2005 2006 2007 2008 2009 2010 2011F 13

  16. Slide 16: Appendix

    For personal use only Appendix 14

  17. Slide 17: Bootu Mineral Resources - Dec 2010

    Bootu Mineral Resources - 31 Dec 2010 For personal use only At 15% Mn Cut-Off Measured Indicated Inferred Combined (1) Deposit: Mt % Mn Mt % Mn Mt % Mn Mt % Mn Chugga North 0.8 22.7 3.4 22.4 0.0 22.8 4.2 22.5 Chugga South 0.4 23.7 1.6 22.4 0.0 0.0 2.0 22.7 Gogo 0.3 25.4 1.3 26.0 0.2 26.8 1.7 26.0 Ma

  18. Slide 18: Bootu Ore Reserve Table - Dec 2010

    Bootu Ore Reserve Table - 31 Dec 2010 At 15% Mn Cut-Off Proved Probable Combined (1) For personal use only Deposit: Mt % Mn Mt % Mn Mt % Mn Chugga North 0.6 20.7 1.6 20.6 2.2 20.6 Chugga South 0.3 21.6 0.8 20.7 1.1 20.9 Gogo 0.3 22.6 1.0 23.2 1.3 23.1 Masai 0.0 0.0 4.9 20.7 4.9 20.7 Shekuma 0.9 22.9

  19. Slide 19: Tshipi Resource Table

    Tshipi Resource Table JORC and SAMREC (2007) Compliant For personal use only Deposit Indicated Inferred Total (Indicated and Inferred) Tonnes Tonnes Tonnes (Million) % Mn (Million) % Mn (Million) % Mn Zone M 22.69 37.95 39.64 37.87 62.33 37.90 Zone C 22.95 36.68 40.61 37.01 63.56 36.89 Zone N 12.83