North American Construction Group Ltd. · TSX:NOA

North American Construction — Q4 2014 Earnings Presentation

20 slides from North American Construction's earnings presentation, February 2015

  1. Slide 1: Investor Presentation

    Investor Presentation Fourth Quarter ended December 31, 2014

  2. Slide 2: Company Overview

    Company Overview Mining Mining  Founded in 1953  TSX and NYSE listings: “NOA”  Current share price*: $3.75 (CAD)  52 week high/low: $9.22/$3.20  Market capitalization: $131.6 million  Shares outstanding: 34.3 million**  Average daily share volume:  NYSE: 105,161  TSX: 87,127  Annual divide

  3. Slide 3: Net Debt Reduction

    Net Debt Reduction $500 $462 $450 $390 $400 $350 Term A Facility Net Debt ($ Millions) $300 Term B Facility Credit Facility $250 Series 1 Debentures less Cash Capital leases (including interest) $200 Operating lease commitments * $134 $150 $127 $98 $100 $50 $0 2011 2012 2013 2014 2014* Year Ended De

  4. Slide 4: Enterprise Value, Net Book Value, and Price per Share

    Enterprise Value, Net Book Value, and Price per Share Enterprise Value, Net Book Value, and Price per Share $30 $25 $20 $ per Share $15 $10 $5 $0 2010 2011 2012 2013 2014 2014* Year Ended December 31, EV/Share NBV/Share NOA Share Price (TSX) • Net Book Value exclude s intangible assets which, as a p

  5. Slide 5: Stronger, Better Focused

    Stronger, Better Focused NAEP is now a pure‐play heavy construction and mining (HC&M) contractor  Simplified business can better target productivity and cost efficiencies  Pipeline divestiture in 2012 ($16.3M of proceeds)  Piling divestiture in 2013 ($227.5M of proceeds, up to $92.5M of contingen

  6. Slide 6: HC&M – Five Year Financial History

    HC&M – Five Year Financial History Revenue and EBITDA Margin $800 $700 $717 $600 $636 $595 $500 $ Millions $470 $472 $400 14% $300 11% 9% 9% $200 5% $100 $0 2010 2011 2012 2013 2014 Year Ended December 31, 6

  7. Slide 7: Activities That Benefit Our Shareholders

    Activities That Benefit Our Shareholders Share Purchase Program  In December 2014, announced the intention to purchase 1,800,000 common shares for cancellation, this represented 5% of the issued and outstanding shares.  In December 2013, completed the purchase of 1,800,000 common shares for cancel

  8. Slide 8: Activities That Benefit Our Shareholders

    Activities That Benefit Our Shareholders 5th Amended Credit Facility  Negotiated an interest rate reduction of 1.5%, leading to a significant reduction in the cost of borrowing.  A combination of working capital and equipment will secure $85 million in potential borrowing.  Reduced financial cove

  9. Slide 9: First On, Last Off

    First On, Last Off Project Development Phase (3-4 years) Ongoing Operations Phase (30-40 years)  Initial mine site development, project site  Overburden removal, mine infrastructure development, development, airstrips, piping reclamation, tailing ponds remediation, equipment and labour supply Buil

  10. Slide 10: Significant Heavy Construction & Mining Contractor in the Oil Sands

    Significant Heavy Construction & Mining Contractor in the Oil Sands  Expertise  30+ years in Northern Alberta’s harsh operating environment  Knowledge to come up with best solutions for customers  Broad Service Offering  Unique suite of services across project lifecycle  Operational Flexibilit

  11. Slide 11: Strategic Focus

    Strategic Focus  Pursue operational excellence in safety, productivity, customer satisfaction  Continued strengthening of balance sheet  Debt reduction, fleet rationalization and cash‐flow improvement  Grow revenue from activity on existing mine sites, incremental work on new sites, and alternat

  12. Slide 12: Outlook for Revenue Growth

    Outlook for Revenue Growth  Continued activity on existing mine sites as owners grow production  Recent awards of over $100 million of secured work on two existing mine sites  Continued work at Kearl under the five‐year agreement  Continued support of production efforts at Horizon, Base Mine, Mi

  13. Slide 13: BC Hydro - Site C Opportunity

    BC Hydro - Site C Opportunity  Site C is a third dam and generating station on the Peace River in northeast B.C.  The project received environmental approval from the federal and provincial governments in October, 2014.  The project was approved by the Province of B.C. December, 2014.  Expected

  14. Slide 14: Active with Every Oil Sands Client

    Active with Every Oil Sands Client Key Customer Contracts  Project put on hold until at least 2017  Site prep work to end in Q4 2014 SUNCOR FORT CANADIAN HILLS  Master services agreement was extended to June, 2015 NATURAL EXXON HORIZON KEARL  Winter reclamation work continues while we attempt TO

  15. Slide 15: Potential Production Expansion on Oil Sands Mine Sites

    Potential Production Expansion on Oil Sands Mine Sites Key Customer Production and Expansion SUNCOR FORT  Syncrude current: 350,000 bbl/d HILLS CANADIAN NATURAL HORIZON EXXON KEARL  Syncrude expansion total potential: 500,000 bbl/d TOTAL SHELL/ALBIAN JOSLYN JACKPINE AND MUSKEG RIVER  Fort Hills m

  16. Slide 16: Thank You

    THANK YOU 16

  17. Slide 17: Appendix

    APPENDIX

  18. Slide 18: HC&M – Heavy Equipment Fleet

    HC&M – Heavy Equipment Fleet Owned Equipment Leased Equipment Support Heavy Trucks, Support Heavy Trucks, Equipment, 90 Equipment, 59 56 118 Loading Equipment, Loading 48 Equipment, 24 Heavy Trucks Loading Equipment Support Equipment Heavy Trucks Loading Equipment Support Equipment 18

  19. Slide 19: Large, Well Maintained Equipment Fleet

    Large, Well Maintained Equipment Fleet Category Own Lease Rental Total SHOVELS 2 0 0 2 EXCAVATORS (≥100T) 9 3 0 12 EXCAVATORS (<100T) 37 21 6 64 RIGID FRAME TRUCKS (>200T) 23 16 0 20% 39 RIGID FRAME TRUCKS (100T to 200T) 56 18 0 74 RIGID FRAME TRUCKS (<100T) 6 2 0 8 ARTICULATED TRUCKS 5 20 16 40% 40

  20. Slide 20: Forward-Looking Statements

    Forward-Looking Statements The information provided in this presentation contains forward‐looking statements and information which reflect the current view of North American Energy Partners with respect to future events and financial performance. Actual results could differ materially from those con

North American Construction Group — Q4 2014 Earnings Presentation on 6ix