    TABLE OF CONTENTS 1 Endeavour Overview 2 Results and Outlook 3 Our High Quality Portfolio 4 Being a Trusted Partner 5 Competitive Advantage in West Africa 6 Appendix 2

  3. Slide 3: Disclaimer and Forward-Looking Statements

    DISCLAIMER AND FORWARD-LOOKING STATEMENTS Cash cost per ounce and all-in sustaining cash cost per ounce are non-GAAP performance activities; changes in national and local government legislation, regulation of mining measures with no standard meaning under IFRS. This presentation contains statements

  4. Slide 4: Endeavour Overview

    ENDEAVOUR OVERVIEW 1 4

  5. Slide 5: Endeavour has unmatched competitive advantage in the world's second-largest gold producing region

    ENDEAVOUR HAS UNMATCHED COMPETITIVE ADVANTAGE IN THE WORLD’S SECOND-LARGEST GOLD PRODUCING REGION 1 Largest 7 Gold 1.4-1.5Moz West African producer mines AISC $890-940/oz 2022 Production Guidance 5

  6. Slide 6: Company Profile

    COMPANY PROFILE Highlights Top Shareholders Shareholder register as at 31 December 2021 Ticker LSE | TSX: EDV, OTXCQ: EDVMF Shares outstanding as at 21 February, 2022 248m Rank Institution name % of S/O 1 La Mancha 19.5% Share price as at 21 February 2022 £18.65 / C$32.80 2 BlackRock Investment Mana

  7. Slide 7: Peer Benchmarking

    PEER senior gold producers BENCHMARKING CROSS SECTOR BENCHMARKING Endeavour is attractive relative to other 0% 10% 20% 1Moz 2Moz 3Moz 4Moz 5Moz 6Moz 7Moz Endeavour Newmont B2Gold Barrick Kinross Polyus AngloGold AngloGold Barrick Gold Fields Polymetal Agnico-Eagle FY 2021 Production Polyus Kinross Y

  8. Slide 8: Our Strategy

    OUR STRATEGY Watch CEO video Build a resilient business and be a trusted partner with the ability to reward shareholders MAINTAINING A BEING A REWARDING HIGH-QUALITY PORTFOLIO TRUSTED PARTNER SHAREHOLDERS Industry-leading operational excellence Employment and training Prudent balance sheet managemen

  9. Slide 9: Embedding the UN SDGs into our ESG Strategy

    EMBEDDING THE UN SDGS INTO OUR ESG STRATEGY Strong contributions to our host countries SOCIAL IMPACT › Economic Development › Education › Health › Access to Water & Electricity PROTECTING THE ENVIRONMENT › Climate Change › Water Stewardship › Biodiversity › Plastic Waste RESPONSIBLE MINING › Human R

  10. Slide 10: Focused on Being a Resilient Business

    FOCUSED ON BEING A RESILIENT BUSINESS High quality portfolio which generates sufficient cash flow to re-invest in our business and reward our stakeholders PORTFOLIO OBJECTIVES PORTFOLIO OPTIMIZATION PILLARS <$900/oz All-in sustaining cost 01 Operational Excellence +10 YEARS Production visibility fro

  11. Slide 11: Superior Operating Model

    1 SUPERIOR OPERATING MODEL OPERATIONAL EXCELLENCE Geographic focus provides a strong competitive advantage OPERATING MODEL MANAGEMENT TRACK RECORD › Largest producer in each of our operating countries enhances ability to extract synergies 9 years › Significant synergies from + shared technical funct

  12. Slide 12: Strong Operating Track Record

    1 STRONG OPERATING TRACK RECORD OPERATIONAL EXCELLENCE Beat 2021 production guidance 0.20 GROUP LTM INDUSTRY LTIFR1 LEADING 1.08 Industry Average2 1,536koz GROUP 2021 BEAT FY PRODUCTION TOP END 1,365-1,495koz Guidance $880/oz GROUP 2021 $850/oz $900/oz WITHIN AISC FY GUIDANCE RANGE Guidance (1) Lost

  13. Slide 13: Project Pipeline

    2 PROJECT PIPELINE PROJECT DEVELOPMENT Strong competition for capital on a returns basis across the portfolio Long-term upside Near-term growth Immediate cash flow FROM GREENFIELD EXPLORATION FROM PROJECTS FROM PRODUCTION +110 EXPLORATION PROPERTIES 6 PROJECTS 7 MINES TARGET CRITERIA TARGET CRITERIA

  14. Slide 14: Strong Construction Track Record

    CEO INTRODUCTION 2 STRONG CONSTRUCTION TRACK RECORD PROJECT DEVELOPMENT Five recent builds integrated within our business AGBAOU, CÔTE D’IVOIRE, BOUNGOU, BURKINA FASO WAHGNION, BURKINA FASO BUILT IN 2014 BUILT IN 2018 BUILT IN 2019 TRACK RECORD safely with zero LTIs HOUNDÉ, BURKINA FASO ITY CIL, CÔT

  15. Slide 15: Key Projects

    4 44 2 KEY PROJECTS PROJECT DEVELOPMENT Sabodala-Massawa expansion underway; progressing DFS on greenfield projects BROWNFIELD PROJECT: GREENFIELD PROJECT: GREENFIELD PROJECT: SABODALA-MASSAWA EXPANSION FETEKRO KALANA PHASE 1 INSIGHTS: PFS INSIGHTS: PFS INSIGHTS:  Debottlenecking the plant back-end

  16. Slide 16: Strong Exploration Track Record

    3 STRONG EXPLORATION TRACK RECORD UNLOCKING EXPLORATION VALUE Achieved 5-year discovery target of 10-15Moz Total Indicated discoveries and targets 11.5Moz Indicated resources discovered Exploration spend 11.5Moz 3.0Moz Discovered discovered from 2.2Moz mid-2016 to 2021 2.1Moz 2022 Exploration Budget

  17. Slide 17: Largest Exploration Presence in West Africa

    3 LARGEST EXPLORATION PRESENCE IN WEST AFRICA UNLOCKING EXPLORATION VALUE Endeavour has a strategic foothold in two of West Africa’s most prospective belts THE LARGEST FOOTHOLD ON THE HOUNDÉ BELT KOFI LIPTAKO LIGUIDI SIGUIRI NABANGA BANTOU FULL CONTROL OF 125KM BARRICK JV STRETCH ALONG THE ITY BIRIM

  18. Slide 18: Proven Ranking and Screening Methodology

    PROVEN RANKING AND SCREENING METHODOLOGY Watch 3 video UNLOCKING EXPLORATION VALUE Based on techniques used in the oil and gas sector Exhaustive Screened through multi- All screening based 150 criteria data analysis to targets on geological data targets set targets amenable to 110 and first selectio

  19. Slide 19: 15-20Moz Five-Year Resource Discovery Target

    3 STRONG EXPLORATION TRACK RECORD UNLOCKING EXPLORATION VALUE Targeting discovery of more than 2x production depletion over 2021-2025 period 5-year Resource Discovery target Risked mean Indicated resource discovery target (2021 - 2025) $/oz M&I resource as at 31 December, 2020 Target discovery cost

  20. Slide 20: Focused on Long Life and Low AISC Assets

    4 FOCUSED ON LONG LIFE AND LOW AISC ASSETS ACTIVE PORTFOLIO MANAGEMENT Divested non-core assets and integrated five mines Endeavour’s Portfolio Key achievement across 4 pillars Core Mine1 Non-core Mine1 Divested / Ceased Mine Project2 AISC, $/oz Realized synergies Built Houndé 1,300 Built Ity Met gu

  21. Slide 21: Production Outlook

    PRODUCTION OUTLOOK Ability to grow high-quality production while maintaining AISC <$900/oz PRODUCTION AND ALL-IN SUSTAINING COSTS For discontinued operations For continuing operations1 Guidance Outlook +1.6Moz 1.5Moz +1.5Moz <$900/oz 1.4-1.5Moz 1.4-1.5Moz <$900/oz $880/oz $890-940/oz <$900/oz 2013A

  22. Slide 22: Robust Return on Capital Employed

    ROBUST RETURN ON CAPITAL EMPLOYED Significant improvement following build of our Ity and Houndé mines Return on Capital Employed (ROCE)1 20% +10% 2020 vs 2019 10% 6% 6% +20% ROCE target with strong capital 2017 2018 2019 2020 allocation discipline (1) EBIT (Adjusted EBITDA as in MD&A less depreciati

  23. Slide 23: Balance Sheet Strength

    BALANCE SHEET STRENGTH Strong cash generation supports balance sheet strength and shareholder returns Net Debt Reduction (Net Debt)/ Net Cash Net Debt / Adj. EBITDA (LTM) INVESTMENT PHASE DEBT REDUCTION PHASE SHARHEOLDER RETURNS PHASE Net Cash Position $75m $76m ($77m) ($70m) ($175m) ($162m) ($473m)

  24. Slide 24: Attractive Shareholder Returns

    ATTRACTIVE SHAREHOLDER RETURNS Minimum dividend commitment of +$500m for FY-2020 to 2023 SHAREHOLER RETURNS POLICY Progressive Dividend Policy Supplemental Dividend Minimum Dividend Paid $175m Minimum Progressive Dividend Minimum Dividend Committed › Provides dividend visibility during $150m growth

  25. Slide 25: Attractive Shareholder Returns

    ATTRACTIVE SHAREHOLDER RETURNS Strong commitment to delivering excess shareholder returns Cumulative Shareholder Returns $338m Minimum dividend $338m Supplemental shareholder returns $138m Cumulative shareholder returns $140m ($0.57/sh) $200m $15m $153m $125m $60m ($0.37/sh) supplemental shareholder

  26. Slide 26: Attractive Shareholder Returns

    ATTRACTIVE SHAREHOLDER RETURNS Most aggressive share buyback program amongst peers Indicative yield for shareholder returns1 $138m FY-2021 Share Buyback FY-2021 Dividend 8% 7% in share buybacks 6% for FY-2021 5% 4% 4.4% 3% 2% 1% 0% Indicative yield of Polyus Newmont3 Gold Fields Polymetal Endeavour2

  27. Slide 27: LSE Premium Listing Completed in June 2021

    LSE PREMIUM LISTING COMPLETED IN JUNE 2021 The largest pure gold producer listed on the premium segment of the LSE INSIGHTS Production for London Stock Exchange listed gold producers1 › Liquidity continues to increase in Gold Silver in gold equivalent the UK with 24% of our free float 3.0Moz shares

  28. Slide 28: Ability to Reward Shareholders Across Cycles

    ABILITY TO REWARD SHAREHOLDERS ACROSS CYCLES Watch video Underpinned by a resilient business, disciplined capital allocation and a strong competitive advantage in West Africa RESILIENT BUSINESS + DISCIPLINED CAPITAL ALLOCATION High Quality Being a Prudent Balance Sheet Organic Shareholder Returns Po

  29. Slide 29: Upcoming Catalysts

    UPCOMING CATALYSTS Q1 Sabodala-Massawa Completion of Definitive Feasibility Study for Phase 2 2022 Q2 Lafigué Completion of Definitive Feasibility Study for Lafigué project at Fetekro 2022 Q3 Shareholder Returns Payment of H1-2022 dividend 2022 Q3 Mana Wona Underground first stope production 2022 29

  30. Slide 30: Results and Outlook

    RESULTS AND OUTLOOK 2 30

  31. Slide 31: Strong Achievements in 2021

    STRONG ACHIEVEMENTS IN 2021 STRONG OPERATIONAL HEALTHY ATTRACTIVE ROBUST PERFORMANCE FINANCIAL POSITION SHAREHOLDER RETURNS ORGANIC GROWTH Group LTIFR of 0.20, well below Net cash position of $76m Shareholder returns of $278m Discovered 3Moz of Indicated industry average of 1.08 achieved at year end

  32. Slide 32: 2022 Guidance

    2022 GUIDANCE INSIGHTS Consolidated Production Guidance 2021 PRELIMINARY 2022 FULL-YEAR GUIDANCE › Total production guidance for 2022 of (All amounts in koz, on a 100% basis) RESULTS 1,400 – 1,500koz at an AISC of $890 - Ity 272 255 — 270 $940/oz Karma 88 85 — 100 Houndé 293 260 — 275 › Guidance is

  33. Slide 33: 2022 Guidance (Continued)

    2022 GUIDANCE (Continued) Sustaining and Non-Sustaining Capital Expenditure Guidance INSIGHTS › Sustaining and non-sustaining capital spend is expected to SUSTAINING CAPITAL NON-SUSTAINING CAPITAL decrease by approximately $40 million in 2022 compared to FY-2021 FY-2022 FY-2021 FY-2022 2021 (All amo

  34. Slide 34: Supply Chain and Cost Inflation Controls

    SUPPLY CHAIN AND COST INFLATION CONTROLS Renegotiating long-term contracts as a larger group has helped to mitigate inflationary pressures INSIGHTS KEY CONTRACT RENEWALS › Renegotiated contracts after acquisitions of Semafo and Teranga to leverage increased group tender volumes with first key contra

  35. Slide 35: Our High Quality Portfolio

    Watch video OUR HIGH QUALITY PORTFOLIO 3 35

  36. Slide 36: Diversified Portfolio of Seven Mines

    DIVERSIFIED PORTFOLIO OF SEVEN MINES 2022 Guidance P&P RESERVES as at Dec 31, 2020 M&I RESOURCES as at Dec 31, 2020 NAME COUNTRY MINE PRODUCTION AISC CONTAINED GOLD GRADE CONTAINED GOLD GRADE (koz) (US$/oz) (Moz) (g/t) (Moz) (g/t) Houndé Burkina Faso 260-275 875-925 2.58 1.74 4.58 1.74 Ity Côte d’Iv

  37. Slide 37: Production by Asset

    PRODUCTION BY ASSET Increased diversification across assets Production breakdown +628koz Wahgnion 147Koz Mana 205Koz Production FY-2021 vs. FY-2020 Boungou Sabodala-Massawa 174Koz 345Koz 1,536Koz Karma Production 70Koz Boungou 94Koz FY-20211 Karma 88Koz Agabou $880oz 13Koz Hounde 908Koz Mana 121Koz

  38. Slide 38: Sabodala-Massawa Mine

    COO video presentation Website Latest technical report SABODALA-MASSAWA MINE Senegal 360-375koz $675-725/oz 4.8Moz 6.6Moz As at As at 2022 Target 2022 Target December 31, 2020 December 31, 2020 Production AISC P&P Reserves M&I Resources Overview The Sabodala-Massawa complex has potential to become a

  39. Slide 39: Sabodala-Massawa Mine

    COO video presentation Website Latest technical report SABODALA-MASSAWA MINE Senegal KEY OPPORTUNITIES RESERVES AND RESOURCES AS AT DEC. 31, 2020 On a 100% basis • Phase 1 expansion to debottleneck the plant back-end Resources shown Tonnage Grade Content inclusive of Reserves (Mt) (Au g/t) (Au koz)

  40. Slide 40: Sabodala-Massawa Mine

    COO video presentation Website Latest technical report SABODALA-MASSAWA MINE Phase 1 plant expansion completed in Q4-2021 Q4-2021 vs Q3-2021 INSIGHTS › Production remained flat despite the increase in processed grade as gold in circuit increased while plant throughput and plant recovery remained con

  41. Slide 41: Sabodala-Massawa Phase 1 Expansion Completed Under Budget

    SABODALA-MASSAWA PHASE 1 EXPANSION PHASE 1 EXPANSION COMPLETED UNDER BUDGET FOR $14M › Phase 1 of the plant expansion facilitates the processing of an increased proportion of high grade, free-milling Massawa ore through the Sabodala processing plant. › Phase 1 of the plant expansion included the ins

  42. Slide 42: DFS for Phase 2 Due for Completion in Q1-2022

    SABODALA-MASSAWA MINE Senegal DFS FOR PHASE 2 IS DUE FOR COMPLETION IN Q1-2022 • Phase 2 of the expansion will add a new refractory  Improved geometallurgical modelling incorporating a wider range of elements into the resource block model, to ore plant to process the high-grade refractory ore impro

  43. Slide 43: Discovery Target (2021-2025)

    DISCOVERY TARGET (2021-2025) SABODALA-MASSAWA MINE 2.3 - 2.7Moz $26/oz Senegal Indicated resources Discovery cost M&I RESOURCES as at Dec 31, 2020 114Mt at 2.01g/t au containing 7.35Moz NEAR-TERM FOCUS Discovery of additional high-grade refractory and non-refractory ore resources. Explore high-grade

  44. Slide 44: Near-Term Exploration Focus

    NEAR-TERM EXPLORATION FOCUS Exploration added 709koz of Indicated resources in 2021 INSIGHTS Massawa Plan Map › During 2021, exploration efforts delineated 591koz of Indicated resources representing a 11% increase over the 31 December 2020 M&I resource estimate excluding 2021 mine depletion. › Indic

  45. Slide 45: Sofia North Extension

    SOFIA NORTH EXTENSION Shallow high grade mineralisation extending for over 800m along strike 45

  46. Slide 46: Samina

    SAMINA Mineralised strike length greater than 1,100 meters and open to the north and south 46 46

  47. Slide 47: Tina

    TINA Northeast striking mineralised occurrence with further drilling planned for 2022 47 47

  48. Slide 48: Bambaraya

    BAMBARAYA High grade mineralisation from surface extending over 800m along strike BBTR001 13.2m@3.64g/t from 0m MRC21-0725 19m @ 1.97g/t Au from 7m Incl. 8m @ 3.07g/t Au from 18m MRC21-0723 4m @ 7.24g/t Au from 10m MRC21-0723 13m @ 2.06g/t Au from 46m 48 48

  49. Slide 49: Ity Mine

    COO video presentation Website Latest technical report 3D mine site tour ITY MINE Côte D’Ivoire 255-270koz $850-900/oz 2.7Moz 3.8Moz As at As at 2022 Target 2022 Target December 31, 2020 December 31, 2020 Production AISC P&P Reserves M&I Resources Overview The Ity mine is one of Endeavour’s cornerst

  50. Slide 50: Ity Mine

    COO video presentation Website Latest technical report 3D mine site tour ITY MINE Côte D’Ivoire KEY OPPORTUNITIES RESERVES AND RESOURCES AS AT DEC. 31, 2020 On a 100% basis • Commencement of mining Le Plaque and continued inclusion of new Resources shown Tonnage Grade Content discoveries inclusive o

  51. Slide 51: Ity Mine

    COO video presentation Website Latest technical report 3D mine site tour ITY MINE Consistent Q4-2021 production vs Q3-2021 Q4-2021 vs Q3-2021 INSIGHTS Production and AISC › Production remained consistent with the prior quarter as Production, koz AISC, US$/oz higher mill throughput was offset by lowe

  52. Slide 52: Ity Mine Production Plan

    COO video presentation Website Latest technical report 3D mine site tour ITY MINE Côte D’Ivoire Ity production plan +294Koz 2022 Guidance mid-point 2017 Optimization Study Incremental production added 300koz Target production of 250koz over +10 years expected to be achieved based on exploration pote

  53. Slide 53: Discovery Target (2021-2025)

    DISCOVERY TARGET (2021-2025) ITY MINE 3.5 – 4.5Moz $17/oz Côte D’Ivoire Indicated resources Discovery cost M&I RESOURCES as at Dec 31, 2020 93Mt at 1.58g/t au containing 4.74Moz NEAR-TERM FOCUS 3.3Moz discovered since 2016 with +10 year mine life. Focus to maintain and extend mine life through high

  54. Slide 54: Near Term Exploration Focus

    NEAR TERM EXPLORATION FOCUS Targets defined along the full length of the Ity belt INSIGHTS › During 2021 exploration efforts delineated 975koz of Indicated resources representing a 26% increase over the 31 December 2020 M&I resource estimate, excluding 2021 mine depletion. Walter-Bakatouo Zia NE Ext

  55. Slide 55: West Flotouo

    WEST FLOTOUO High grade discovery close to the Ity CIL plant West Flotouo Plan Map West Flotouo Cross Section VO21-165 8.4m @ 4.57 g/t Au 5.9m @ 14.55 g/t Au VO21-176 25.8m @ 4.91 g/t Au 4.2m @ 10.85 g/t Au VO21-158 14.8m @ 3.04 g/t Au 5.9m @ 10.65 g/t Au VO21-096 25.2m @ 13.00g/t Au 3.7m @ 11.01g/t

  56. Slide 56: Le Plaque

    LE PLAQUE Updated resources extended mineralisation INSIGHTS Le Plaque Exploration Targets › During the 2021 drilling campaign, an updated mineral resource was defined at Le Plaque, extending mineralisation towards Le Plaque SW and at depth at Delta Extension. › The high grade Le Plaque deposit has

  57. Slide 57: Delta Extension

    DELTA EXTENSION Mineralisation extends below pit shell 57 57

  58. Slide 58: Walter-Bakatouo

    WALTER-BAKATOUO Near mine low strip ratio resources added WA21-052 5m @ 17.02 g/t Au WA21-074 3m @ 4.35 g/t Au 26.9m @ 3.24 g/t Au 6m @ 2.7 g/t Au WA21-033 WA21-025 18.4m @ 2.73 g/t Au 2m @ 39.84 g/t Au 23m @ 4.29 g/t Au 6.4m @ 3.86 g/t Au WA21-022 11m @ 2.54 g/t Au WA21-060 16.9m @ 6.20 g/t Au 19m

  59. Slide 59: Daapleu Deeps

    DAAPLEU DEEPS High-grade mineralisation extends down dip DA15-178 21.3m @ 1.87g/t Au 8.9m @1.37 g/t Au 9.3m @ 1.12 g/t Au DA16-193 18m @ 1.54g/t Au DA16-194 12.1m @ 1.47g/t Au 6.9m @ 1.13 g/t Au 13.9m @ 1.23 g/t Au DA15-174 14.2m @ 1.21g/t Au 10.7m @ 2.87 g/t Au DA16-193 15.6m @ 1.36 g/t Au DA21-615

  60. Slide 60: Houndé Mine

    COO video presentation Website Latest technical report 3D mine site tour HOUNDÉ MINE Burkina Faso 260-275koz $875-925/oz 2.6Moz 4.6Moz As at As at 2022 Target 2022 Target December 31, 2020 December 31, 2020 Production AISC P&P Reserves M&I Resources Overview The Houndé mine is one of Endeavour’s cor

  61. Slide 61: Houndé Mine

    COO video presentation Website Latest technical report 3D mine site tour HOUNDÉ MINE Burkina Faso KEY OPPORTUNITIES RESERVES AND RESOURCES AS AT DEC. 31, 2020 On a 100% basis • Potential to integrate new discoveries including the Mambo and Golden Resources shown Tonnage Grade Content Hill deposits i

  62. Slide 62: Houndé Mine

    COO video presentation Website Latest technical report 3D mine site tour HOUNDÉ MINE Record performance in FY-2021 Q4-2021 vs Q3-2021 INSIGHTS Production and AISC › Production increased due to the higher recovery rates as well as the Production, koz AISC, US$/oz increased mill tonnage despite the lo

  63. Slide 63: Houndé Mine Production Plan

    COO video presentation Website Latest technical report 3D mine site tour HOUNDÉ MINE Burkina Faso Houndé production plan 2022 Guidance mid-point +426Koz Incremental production added 2016 Optimization Study 300Koz Target production of 250koz over +10 years expected to be achieved based on exploration

  64. Slide 64: Discovery Target (2021-2025)

    DISCOVERY TARGET (2021-2025) HOUNDÉ MINE 3.0 – 4.0Moz $19/oz Burkina Faso Indicated resources Discovery cost M&I RESOURCES as at Dec 31, 2020 108Mt at 1.57g/t au containing 5.47Moz NEAR-TERM FOCUS Focused on maintaining +10-year mine life. Focused on near mill targets such as Kari Area, Vindaloo Sou

  65. Slide 65: Near Term Exploration Focus

    NEAR TERM EXPLORATION FOCUS Maiden resources declared at Mambo and Vindaloo South INSIGHTS Houndé plan map highlighting soil geochemical anomalies › During 2021 exploration efforts delineated 889koz of Indicated resources, representing a 20% increase over the 31 December 2020, M&I resource estimate,

  66. Slide 66: Mambo

    MAMBO Delineation of the Mambo discovery INSIGHTS. Mambo geology and drilling intercepts › Mambo is an attractive deposit as it is expected to have a low strip ratio, the resource contains approximately 40% oxide and transitional material › The higher-grade portion (+2g/t) of the Mambo deposit is ex

  67. Slide 67: Mambo

    MAMBO Down dip mineralisation extension remains open 67 67

  68. Slide 68: Golden Hill Exploration

    GOLDEN HILL EXPLORATION Potential to integrate within the Houndé mine plan INSIGHTS › Advanced-stage exploration project on the Houndé Belt within trucking distance (25-30km) of the Houndé mine › Potential for development as a satellite deposit › Expansive exploration licenses covering 468km2 › Dril

  69. Slide 69: Wahgnion Mine

    COO video presentation Website Latest technical report 3D mine site tour WAHGNION MINE Burkina Faso 140-150koz $1,050-1,150/oz 1.4 Moz 2.1 Moz As at As at 2022 Target 2022 Target December 31, 2020 December 31, 2020 Production AISC P&P Reserves M&I Resources Overview The newly developed Wahgnion mine

  70. Slide 70: Wahgnion Mine

    COO video presentation Website Latest technical report 3D mine site tour WAHGNION MINE Burkina Faso KEY OPPORTUNITIES RESERVES AND RESOURCES AS AT DEC. 31, 2020 • Greater mining flexibility following commissioning of On a 100% basis satellite deposits Resources shown Tonnage Grade Content inclusive

  71. Slide 71: Wahgnion Mine

    COO video presentation Website Latest technical report 3D mine site tour WAHGNION MINE Increased throughput and grades with stable recoveries in Q4-2021 Q4-2021 vs Q3-2021 INSIGHTS › Production increased due to increased plant throughput and higher processed grade while the plant recovery rate remai

  72. Slide 72: Discovery Target (2021-2025)

    DISCOVERY TARGET (2021-2025) WAHGNION MINE 1.5 – 2.0Moz $25/oz Burkina Faso Indicated resources Discovery cost M&I RESOURCES as at Dec 31, 2020 44Mt at 1.51g/t Au containing 2.15Moz NEAR-TERM FOCUS Extend mine life to +10 years through discovery of additional satellite deposits within trucking dista

  73. Slide 73: Wahgnion Mine Exploration Potential

    WAHGNION MINE Significant exploration potential exists within the permitted mine license INSIGHTS Nogbele South: Significant Indicated resource potential › An exploration programme of up to $12 million was planned for 2021. The exploration efforts continued to focus on Nogbele North and Nogbele Sout

  74. Slide 74: Mana Mine

    COO video presentation Website Latest technical report 3D mine site tour MANA MINE Burkina Faso 170-190koz $1,000-1,100/oz 1.4 Moz 3.0 Moz As at As at 2022 Target 2022 Target December 31, 2020 December 31, 2020 Production AISC P&P Reserves M&I Resources Overview The Mana mine is located in the north

  75. Slide 75: Mana Mine

    COO video presentation Website Latest technical report 3D mine site tour MANA MINE Burkina Faso KEY OPPORTUNITIES RESERVES AND RESOURCES AS AT DEC. 31, 2020 • Mine life extensions through open pit and underground exploration On a 100% basis Resources shown Tonnage Grade Content • Cost optimization t

  76. Slide 76: Mana Mine

    COO video presentation Website Latest technical report 3D mine site tour MANA MINE Wona underground development being expedited Q4-2021 vs Q3-2021 INSIGHTS Production and AISC › Production increased due to higher processed grade and Production, koz AISC, US$/oz plant recovery rate, which was partial

  77. Slide 77: Discovery Target (2021-2025)

    DISCOVERY TARGET (2021-2025) Bara MANA MINE 1.0 – 1.5Moz $30/oz Burkina Faso Indicated resources Discovery cost M&I RESOURCES as at Dec 31, 2020 45Mt at 2.07g/t Au containing 3.01Moz NEAR-TERM FOCUS Extend mine life to +10 years through exploration of Siou underground, Wona underground as well as ex

  78. Slide 78: Near Term Exploration Focus

    NEAR TERM EXPLORATION FOCUS Focus on discovering new oxide potential Mana exploration map INSIGHTS › An exploration programme of $8 million was planned for 2021 › In H2-2021 exploration was focussed on the Maoula open pit oxide target, and on evaluating underground targets at Siou, Wona and Nyafe. ›

  79. Slide 79: Maoula

    MAOULA Open pit oxide target MARC21-524 MARC21-513 5m @ 3.01 g/t \ 163m 3m @ 2.39 g/t \ 37m A MARC21-572 MARC21-559 3m @ 2.11 g/t \ 35m 3m @ 2.02 g/t \ 142m MARC21-169 MADD21-521 5m @ 3.24 g/t \ 29m 14m @ 2.65 g/t \ 69m MARC21-342 11m @ 6.27 g/t \ 104m MARC21-507 11m @ 3.72 g/t \ 14m MARC21-308 5m @

  80. Slide 80: Maoula

    MAOULA Mineralisation open between east and west structures NW MARC21-214 SE Base line MARC21-208 4.0m @ 3.33 g/t \ 14m 5.0m @ 1.99 g/t \ 25m 4.0m @ 1.35 g/t \ 21m 6.0m @ 1.53 g/t \ 69m MARC21-207 8.0m @ 2.09 g/t \ 26m Laterite MARC21-209 300m RL 5.0m @ 3.63 g/t \ 118m MARC21-210 7.0m @ 3.29 g/t \ 1

  81. Slide 81: Boungou Mine

    COO video presentation Website Latest technical report 3D mine site tour BOUNGOU MINE Burkina Faso 130-140koz $900-1,000/oz 1.0 Moz 1.5 Moz As at As at 2022 Target 2022 Target December 31, 2020 December 31, 2020 Production AISC P&P Reserves M&I Resources Overview The Boungou mine is a low cost, high

  82. Slide 82: Boungou Mine

    COO video presentation Website Latest technical report 3D mine site tour BOUNGOU MINE Burkina Faso KEY OPPORTUNITIES RESERVES AND RESOURCES AS AT DEC. 31, 2020 • Discovery of new deposits to maintain higher grade profile On a 100% basis Resources shown Tonnage Grade Content • Brownfields drilling to

  83. Slide 83: Boungou Mine

    COO video presentation Website Latest technical report 3D mine site tour BOUNGOU MINE Continued focus on waste stripping at East pit in Q4-2021 Q4-2021 vs Q3-2021 INSIGHTS Production and AISC › Production decreased due to a lower mined and processed grade Production, koz AISC, US$/oz while throughpu

  84. Slide 84: Discovery Target (2021-2025)

    DISCOVERY TARGET (2021-2025) BOUNGOU MINE 1.0 – 1.5Moz $32/oz Burkina Faso Indicated resources Discovery cost M&I RESOURCES as at Dec 31, 2020 14Mt at 3.32g/t Au containing 1.54Moz NEAR-TERM FOCUS Extend mine life to +10 years through exploration of near mine targets Boungou North, Natougou SW, Nato

  85. Slide 85: Near Term Exploration Focus

    NEAR TERM EXPLORATION FOCUS High priority targets within 10km of the mine INSIGHTS Boungou Exploration Map › An exploration programme of up to $7 million was planned for 2021. The exploration efforts were focused on delineating near mine targets including Natougou Northeast, Boungou Northwest and Bo

  86. Slide 86: Karma Mine

    COO video presentation Website Latest technical report KARMA MINE Burkina Faso 85-100koz $1,200-1,250/oz 0.2 Moz 1.9 Moz As at As at 2022 Target 2021 Target December 31, 2020 December 31, 2020 Production AISC P&P Reserves M&I Resources Overview The Karma mine is a low-grade heap In 2017, an optimiza

  87. Slide 87: Karma Mine

    COO video presentation Website Latest technical report KARMA MINE Burkina Faso KEY OPPORTUNITIES RESERVES AND RESOURCES AS AT DEC. 31, 2020 • Mine life extensions through brownfield drilling On a 100% basis Resources shown Tonnage Grade Content • Drilling at Kao North and GG1 to assess additional he

  88. Slide 88: Karma Mine

    COO video presentation Website Latest technical report KARMA MINE Production remained flat in Q4-2021 Q4-2021 vs Q3-2021 INSIGHTS Production and AISC › Production remained flat despite the improved average grade Production, koz AISC, US$/oz and recovery rates as the stacking rate slightly decreased

  89. Slide 89: Karma Mine

    COO video presentation Website Latest technical report KARMA MINE Exploration focused on delineating near mine extensions INSIGHTS Karma H1-2021 Drilling plan › During H2-2021 limited exploration work continued as part of the advanced grade control drilling programme, targeting near mine extensions

  90. Slide 90: Fetekro Project

    PFS press release Latest technical report 3D mine site tour FETEKRO PROJECT Côte D’Ivoire QUICKFACTS (ON 100% BASIS) – 2021 PFS RESERVES AND RESOURCES AS AT DEC. 31, 2020 Ownership 80% EDV; 10% Gov. Côte d’Ivoire, 10% SODEMI Mine Type Open Pit On a 100% basis Mill Type 3.0Mtpa Gravity / CIP Plant Re

  91. Slide 91: Fetekro Project

    FETEKRO PROJECT Simplified map of the Fetekro property showing Lafigué Côte D’Ivoire 2021 project economics are robust, with an attractive NPV and IRR being generated across a range of gold prices The PFS is based on the updated 2020 Mineral Resource Estimate, as published on August 18, 2020, which

  92. Slide 92: Fetekro Project Attractive Project Economics

    Fetekro 2020 PEA vs 2021 PFS FETEKRO PROJECT PLANT TYPE, SIZE & CAPEX PFS PEA VARIANCE Côte D’Ivoire Plant type Gravity / CIP Gravity / CIL Mill Type 3.0 1.5 +100% Upfront capital cost, $m 338 268 +26% LIFE OF MINE PRODUCTION Mine life, years 9.5 8.0 +31% Strip ratio, W:O 10.3 7.4 +41% Tonnes proces

  93. Slide 93: Discovery Target (2021-2025)

    DISCOVERY TARGET (2021-2025) FETEKRO PROJECT 1.2 – 1.8Moz $14/oz Côte D’Ivoire Indicated resources Discovery cost M&I RESOURCES as at Dec 31, 2020 45Mt at 2.00g/t Au containing 2.92Moz NEAR-TERM FOCUS 2.92Moz have been discovered since 2018 with the aim to further extend the Lafigué resources. Sever

  94. Slide 94: Fetekro Project

    FETEKRO PROJECT DFS expected to be published in late Q1-2022 INSIGHTS Drilling between Lafigué Center and Lafigué North › Since the last resource update on 18 August 2020, more than 66,000 meters of drilling have been completed on the Lafigué deposit, the results of this drilling activity successful

  95. Slide 95: Fetekro Project

    FETEKRO PROJECT Mineralisation extends over 500m southeast of current pit shell LFRC21-1441 1.9m@ 0.99 g/t Au 95 95

  96. Slide 96: Kalana Project

    PFS press release Website Latest technical report KALANA PROJECT Mali QUICKFACTS (ON 100% BASIS) – 2021 UPDATED PFS RESERVES AND RESOURCES AS AT DEC. 31, 2020 Ownership 80% EDV; 20% Mali government Mine Type Open Pit On a 100% basis Mill Type 3.0Mtpa Gravity / CIL Plant Resources shown Tonnage Grade

  97. Slide 97: Kalana Project Study Comparison

    KALANA PROJECT Kalana 2016 vs. 2021 Study Comparison1 Mali 2021 STUDY 2016 STUDY VARIANCE PLANT SIZE & CAPEX Nominal mill capacity, Mtpa 3.0 1.2 +150% Upfront capital cost, $m 297 196 +51% › Key changes in updated PFS compared to LIFE OF MINE STATS the 2016 Avnel study: Mine life, years 11 18 -39% ‒

  98. Slide 98: Kalana License and Exploration Targets

    Kalana license and exploration targets KALANA PROJECT Mali › Discovery of additional deposits may provide an extension of the Kalana mining operation. In addition, potential high-grade free-digging soft material may provide further operating flexibility › The Kalanako Northwest area is highly prospe

  99. Slide 99: Bantou Project

    INSIGHTS › Acquired through Endeavour’s acquisition of SEMAFO in 2020 and currently consists of eight mineralized zones with diverse mineralization styles and grades within the prolific Houndé BANTOU PROJECT Burkina Faso Greenstone Belt › The inferred resource is comprised of three main areas with t

  100. Slide 100: Nabanga Project

    INSIGHTS Nabanga deposit plan map and schematic cross-section › Located 250 kilometres southeast of Ouagadougou, the Nabanga Gold Project lies within the Nabanga NABANGA PROJECT Burkina Faso exploration permit. › Results of Preliminary Economic Assessment (PEA) released on September 30, 2019. ‒ Pre-

  101. Slide 101: Greenfield Afema

    INSIGHTS › New Discovery: Woulo Woulo Prospect › Continued geological and GREENFIELD AFEMA Côte D’Ivoire structural evaluations to expand oxide mineralization along the Afema shear zone › Strong drill results across widespread mineralization the Woulo Woulo prospect › Average 40-50 metre wide gold m

  102. Slide 102: Greenfield Liguidi

    102 GREENFIELD LIGUIDI Burkina Faso

  103. Slide 103: Bondoukou - Tanda & Iguela

    INSIGHTS › Over 8 targets have been identified on the Tanda and Iguela exploration permits BONDOUKOU - TANDA & IGUELA Côte D’Ivoire › Dakou, Pala and Assafou- Broukro are high priority targets with the larger resource size potential › High gold in soil geochemical anomalies have been identified 103

  104. Slide 104: Greenfield: Siguiri Licenses

    104 GREENFIELD: SIGUIRI LICENSES Guinea

  105. Slide 105: Greenfield Sissedougou / Mankono

    JV WITH BARRICK GOLD › Drill results suggest the presence of an 800-metre Côte D’Ivoire GREENFIELD SISSEDOUGOU / MANKONO mineralized structure at Sissedougou with best drill results of: ‒ 34.6 m @ 2.08g/t Au at 74.6m, including 1.0m @ 31.52g/t Au ‒ 18.8 m @ 2.30g/t Au at 26.1m ‒ 23.0 m @ 2.14g/t Au

  106. Slide 106: Greenfield Nassile / Da-Guity

    INSIGHTS › Highly prospective area of Nassile and Dar-Guiti Niger GREENFIELD NASSILE / DA-GUITY › Exploration Permit obtained in 2017 › Exploration Permit covers a total surface area of 695km² 106

  107. Slide 107: Greenfield Kofi

    INSIGHTS › Kofi on same trend as Barrick’s Loulo- Mali GREENFIELD KOFI Gounkoto in Mali › Exploration license of Kofi not sold in Tabakoto sales process › Aim is to attain additional license around Kofi North/Netekoto to consolidate exploration cluster 107

  108. Slide 108: Being a Trusted Partner

    Watch video BEING A TRUSTED PARTNER Watch CEO video 4 108

  109. Slide 109: Improving Our Transparency & Disclosure

    IMPROVING OUR TRANSPARENCY & DISCLOSURE As our company has grown, so have our ESG initiatives and commitments 2022 • Set water targets 2021 • External assurance on key • Announce key ESG targets 2020 ESG data for 2025 • 1st RGMP externally • 7 RGMPs externally assured • Complete detailed assured aba

  110. Slide 110: Continuous Improvement in Ratings

    CONTINUOUS IMPROVEMENT IN RATINGS Reflecting increased transparency, disclosure and engagement 2019 2022 2019 2021 Relative Performance 2019 2020 2021 Climate Change D- C C 2020 Water N/A C C Forestry 2021    Defined targets required to advance to a B rating 110

  111. Slide 111: Rigorous Reporting with Board Oversight

    RIGOROUS REPORTING WITH BOARD OVERSIGHT THE BOARD Environment, Sustainability Audit Committee Quarterly & Governance Committee Executive Management Committee Executive ESG SteerCo Quarterly Sector Specialists Health, Human Social Finance Legal & Supply Investor IT safety & resources performance comp

  112. Slide 112: Aligning ESG Priorities Through Exec Comp.

    ALIGNING ESG PRIORITIES THROUGH EXEC COMP. Element Performance Metrics for 2021 Weighting ANNUAL BONUS (STIP) Net Free Cash Flow 20% Financial AISC 10% Production 10% Operational Exploration Targets 20% LSE Listing 20% ESG Safety & Malaria 20% LONG TERM INCENTIVE PLAN (LTIP) Shareholder value TSR vs

  113. Slide 113: Strong Corporate Governance

    STRONG CORPORATE GOVERNANCE Aiming for close alignment with UK Corporate Governance Code Size of Board = 10 Nationalities represented on the Board Board experience by sector Accounting 9 5 1 Strategy & Leadership Metals & Mining International Business Finance Operations & Exploration Corporate Gover

  114. Slide 114: Summary of Key Governance Improvements

    SUMMARY OF KEY GOVERNANCE IMPROVEMENTS Steps taken for listing on the Premium Segment of the LSE andd to comply with UK Corporate Governance Code Employee Share Corporate Disclosure Board Executive Pay Scheme  Redomiciled to the UK as a  FPPP basis applied to  Board Reserved  Restructured CEO 

  115. Slide 115: Turning Our Purpose into an Actionable Strategy

    TURNING OUR PURPOSE INTO AN ACTIONABLE STRATEGY OUR PURPOSE PARTNERING WITH SUPPORTED BY OUR HOSTS STRONG ETHICS TO PRODUCE GOLD THAT AND GOVERNANCE PROVIDES LASTING VALUE TO SOCIETY INVESTING IN PROTECTING OUR HOST COUNTRIES OUR ENVIRONMENT We do so while protecting Respect for human rights and pro

  116. Slide 116: Our Sustainability Strategy

    @ENDEAVOUR MINING ets OUR SUSTAINABILITY Va Ree STRATEGY rcaesstretttertttesnnnass . ~ national and regional levels OUR AMBITION PROTECTING FOR OUR ESG MISSION INVESTING IN OUR ENVIRONMENT IMPLEMENTED ACROSS OUR OUR HOST COUNTRIES 6 MINES, HOST COMMUNITIES d AND BEYOND +) i Biodiversity Water Stewar

  117. Slide 117: Embedding the UN SDGs into our ESG Strategy

    EMBEDDING THE UN SDGS INTO OUR ESG STRATEGY Strong contributions to our host countries SOCIAL IMPACT › Economic Development › Education › Health › Access to Water & Electricity PROTECTING THE ENVIRONMENT › Climate Change › Water Stewardship › Biodiversity › Plastic Waste RESPONSIBLE MINING › Human R

  118. Slide 118: Investing in Our Host Communities

    INVESTING IN OUR HOST COMMUNITIES COMMUNITY ENGAGEMENT EDUCATION GOVERNMENT PAYMENTS › Grievance mechanism in place & and › Key priority for Endeavour to support the › Gold royalties paid on sliding scale, reported in our annual Sustainability Report next generation and overall national increasing a

  119. Slide 119: Supporting Economic Development

    CORPORATE SUPPORTING ECONOMIC DEVELOPMENT PRESENTATION PROCUREMENT ENDEAVOUR FOUNDATION IMPACT INVESTING › Supply chain re-orientated towards West › Created in 2021 to be Endeavour’s primary › Established an impact investing fund Africa since 2019 vehicle to implement regional and national ECODEV to

  120. Slide 120: Addressing Climate Change

    ADDRESSING Endeavour’s GHG emissions intensity amongst lowest in the industry CLIMATE CHANGE Emissions intensity (kgCO2eq/oz) 2020 GHG EMISSIONS INTENSITY In 2021 Endeavour committed to:  -30% by 2030 => ~2C  Net Zero by 2050  Carbon reduction included in Exec. Compensation Emissions intensity (k

  121. Slide 121: Protecting the Environment

    CORPORATE PROTECTING THE ENVIRONMENT PRESENTATION WATER TAILINGS BIODIVERSITY › In 2020, we revised our water accounting › Annual disclosure in line with the Investor › Aim to minimise and mitigate our impacts and reporting methodology to align with Mining and Tailings Safety Initiative ICMM Water A

  122. Slide 122: Our People

    CORPORATE OUR PEOPLE PRESENTATION SAFETY HEALTH GENDER DIVERSITY › Strong safety culture with Zero harm goal › COVID-19 Response › In 2020 set 25% increase in gender diversity as part of the Group-wide ‒ No impact on production › Safety KPI part of annual Group bonus annual bonus… ‒ Successful EDV v

  123. Slide 123: Ethical Business

    CORPORATE ETHICAL BUSINESS PRESENTATION HUMAN RIGHTS ANTI-BRIBERY/CORRUPTION RESPONSIBLE SOURCING › Our Human Rights Policy is reviewed › Independent 3rd party 24/7 whistleblower › All gold produced by Endeavour sourced annually, and we publish an annual Modern hotline from our own operations Slaver

  124. Slide 124: Competitive Advantage in West Africa

    Watch video COMPETITIVE ADVANTAGE IN WEST AFRICA 5 124

  125. Slide 125: West Africa Endeavour's Presence

    WEST AFRICA ENDEAVOUR'S PRESENCE No. 1 GOLDEN OPPORTUNITY No. 1 Gold producer in the region and in each of the countries in which we operate IN WEST AFRICA for global gold discoveries over past decade 20% Endeavour is strategically positioned with an unmatched competitive advantage in the region. En

  126. Slide 126: West Africa is the Fastest-Growing Gold Region

    REGION’S PRODUCTION GROWTH WEST AFRICAN PRODUCTION GROWTH WEST AFRICA 12.5Moz 12.5% IS THE FASTEST- GROWING GOLD PRODUCING REGION 10.0Moz 10.0% Percentage of Global Mine Supply 7.5Moz 7.5% West African Mine Supply +90% 5.0Moz 5.0% production increase over last decade 2.5Moz 2.5% 12% 0.0Moz 0.0% of g

  127. Slide 127: Production for the Region

    PRODUCTION FOR THE REGION ANNUAL GOLD PRODUCTION BY REGION In millions of ounces, for 2019 WEST AFRICA IS THE 2ND LARGEST 12Moz 12Moz GLOBAL GOLD 11Moz 10Moz PRODUCING REGION Given the golden opportunity in West Africa, 6 out of the top 10 senior 6Moz gold producers have a presence in 6Moz the regio

  128. Slide 128: Endeavour is the Dominant West African Producer

    PRODUCTION WEST AFRICAN GOLD PRODUCTION (2021E) ENDEAVOUR Endeavour IS THE DOMINANT AngloGold WEST AFRICAN Newmont GOLD PRODUCER Gold Fields Barrick Given its focus on West Africa, Endeavour B2Gold has a strategic industrial benefit from Kinross being geographically focused yet diversified across mu

  129. Slide 129: Endeavour's Operating Model

    ENDEAVOUR’S OPERATING MODEL › Geographic focus provides a strong competitive advantage › Largest producer in each of our operating countries › Hands-on management model with teams close to operations › Senior management team spends significant time in-country › General managers empowered and rely on

  130. Slide 130: Enhanced Security Platform Due to Scale in the Region

    REGION’S PRODUCTION GROWTH ENHANCED SECURITY PLATFORM DUE TO SCALE IN THE REGION › Security unit structured as a business unit, led by ex-French military › Air strips on sites to avoid use of roads and improve operating efficiencies › Significant foreign aid and co- operation amongst West African na

  131. Slide 131: Industry Exploration Spend

    INDUSTRY EXPLORATION SPEND INDUSTRY 2020 EXPLORATION BUDGET In US$ millions 842 WEST AFRICA IS 788 THE 4TH LARGEST EXPLORATION FOCUS ACROSS THE GLOBE Given that exploration spend often 470 458 foreshadows future production growth, West Africa has the potential to continue to be a large producing reg

  132. Slide 132: Discoveries by Area

    INDUSTRY EXPLORATION SPEND DISCOVERIES BY AREA For the period between 2006-2016 79Moz WEST AFRICA RANKS 1ST FOR DISCOVERIES OVER PAST DECADE 50Moz The region is significantly under-explored 42Moz compared to other regions. 33Moz 79 27Moz 27Moz 23Moz 22Moz 20Moz Moz 18Moz 16Moz 16Moz 15Moz 13Moz 13Mo

  133. Slide 133: Endeavour Holds One of the Largest Land Tenement Holdings in West Africa

    UNDER-EXPLORED REGION ENDEAVOUR HOLDS ONE OF THE LARGEST LAND TENEMENT HOLDINGS IN WEST AFRICA 60% of greenstone belt lies in Burkina Faso and Côte d’Ivoire but… …only represents Endeavour has a strategic foothold in ~30% of production two of West Africa’s most prospective belts since it is underexp

  134. Slide 134: Endeavour Controls the Full 125km Stretch Along the Ity Birimian Belt

    ENDEAVOUR CONTROLS THE FULL 125KM STRETCH ALONG THE ITY BIRIMIAN BELT 134

  135. Slide 135: Endeavour Has the Largest Foothold on the Houndé Belt

    ENDEAVOUR HAS THE LARGEST FOOTHOLD ON THE HOUNDÉ BELT 135 135

  136. Slide 136: West Africa Operates as an Economic Union

    WEST AFRICA OPERATES STABLE SECTOR AS AN ECONOMIC UNION MINING CODE SIZE West African Economic and Well balanced profit sharing: Extractive sector Monetary Union (WAEMU) › Corporate tax rate between 25- represents a low % 35% of GDP1: › Free-carried interests between › Senegal: 2% 10-15% › Cote d’Iv

  137. Slide 137: Unmatched Competitive Advantage

    UNMATCHED COMPETITIVE ADVANTAGE Dominant presence in the world’s second-largest producing region STRATEGIC SUPERIOR MANAGEMENT POSITIONING OPERATING MODEL TRACK RECORD Largest producer in each country In country and regional synergies Discovered 8.4Moz of Indicated resources where we operate at <$25

  138. Slide 138: Appendix

    APPENDIX FT / 6) Es y

  139. Slide 139: Appendix 1: Management, Board and Analyst Coverage

    01 APPENDIX 1 Management, Board and Analyst Coverage

  140. Slide 140: Solid Management Track Record

    SOLID MANAGEMENT TRACK RECORD SÉBASTIEN • Sébastien de Montessus is President and CEO of Endeavour Mining. Under his leadership, he has introduced key strategic objectives that have created a sustainable business that generates long term cash flow DE MONTESSUS • Previously, Sébastien served as the C

  141. Slide 141: Board Members

    BOARD MEMBERS Michael Beckett Alison Baker Carmen Letton David Mimran Tertius Zongo Chairman Non-executive Director Non-executive Director Non-executive Director Non-executive Director Non-executive Director James Askew Livia Mahler Naguib Sawiris Sofia Bianchi Sébastien de Montessus Non-executive D

  142. Slide 142: Analyst Coverage

    ANALYST COVERAGE Firm Analyst Phone Email Bank of America Michael Jalonen ✆ +1 416 369 7592 ✉ lawson.winder@bofa.com Barclays Amos Fletcher ✆ +44 20 7773 2225 ✉ amos.fletcher@barclays.com Berenberg Jonathan Guy ✆ +44 20 3753 3379 ✉ jonathan.guy@berenberg.com BMO Raj Ray ✆ +44 20 7246 5430 ✉ raj.ray@

  143. Slide 143: Appendix 2: Financial Appendices

    02 APPENDIX 2 Financial appendices

  144. Slide 144: Mine Statistics (Quarterly)

    MINE STATISTICS On a quarterly basis SABODALA- ITY KARMA HOUNDÉ MANA BOUNGOU WAHGNION MASSAWA (on a 100% basis) Q3-21 Q2-21 Q3-20 Q3-21 Q2-21 Q3-20 Q3-21 Q2-21 Q3-20 Q3-21 Q2-21 Q3-20 Q3-21 Q2-21 Q3-20 Q3-21 Q2-21 Q3-21 Q2-21 Physicals Total tonnes mined – OP1 000t 5,576 5,934 6,322 4,972 6,212 4,39

  145. Slide 145: Mine Statistics (Year to Date)

    MINE STATISTICS On a year to date (nine months) basis SABODALA- ITY KARMA HOUNDÉ MANA BOUNGOU WAHGNION MASSAWA (on a 100% basis) YTD-21 YTD-20 YTD-21 YTD-20 YTD-21 YTD-20 YTD-21 YTD-20 YTD-21 YTD-20 YTD-212 YTD-212 Physicals Total tonnes mined – OP1 000t 18,326 16,923 16,330 14,146 37,620 32,754 20,

  146. Slide 146: Appendix 3: Reserves and Resources, 5-year exploration target and security

    03 APPENDIX 3 Reserves and Resources, 5-year exploration target and security

  147. Slide 147: Reserves and Resources

    RESERVES AND RESOURCES As of December 31, 2020 On a 100% basis On a 100% basis On a 100% basis Resources shown Tonnage Grade Content Resources shown Tonnage Grade Content Resources shown Tonnage Grade Content inclusive of Reserves (Mt) (Au g/t) (Au koz) inclusive of Reserves (Mt) (Au g/t) (Au koz) i

  148. Slide 148: Exploration Methodology and Strategy

    EXPLORATON METHODOLOGY AND STRATEGY Selection, ranking and risk evaluation of exploration targets Endeavour’s large land position (more than 17,000 sq Km) and comprehensive database over a very large number of exploration targets promotes the application of a general portfolio management theory wher

  149. Slide 149: Exploration Methodology and Strategy

    EXPLORATON METHODOLOGY AND STRATEGY Selection, ranking and risk evaluation of exploration targets Step 4: Final selection of targets, with higher PoO and priority, which can be physically be included in the 5 year exploration plan Since Endeavour cannot feasibly explore the 110 targets, defined in S

  150. Slide 150: Appendix 4: Debt Sources, Revenue Protection Program and ROCE

    04 APPENDIX 4 Debt Sources, Revenue Protection Program and ROCE

  151. Slide 151: Debt Structure

    DEBT STRUCTURE Debt Structure $330 Convertible Notes Debt Structure (at quarter-end) As at 31-Dec-21 › 3% coupon on convertible note payable semi-annually › Matures in February 2023 $330m Convertible Senior Notes $370m 330.0 › Ability to settle in cash or shares $500m Senior Notes 500.0 › Conversion

  152. Slide 152: Short Term Revenue Protection Program

    SHORT TERM REVENUE PROTECTION PROGRAM Increased certainty of cash flow to achieve corporate objectives Gold collars INSIGHTS Gold price in US$/oz › Aimed at increasing cash flow certainty 2,100 Growth and shareholder return focus during construction while retaining headroom to continue an attractive

  153. Slide 153: Return on Capital Employed

    Strong focus on demonstrating returns following investment phase ITY ROCE HOUNDE ROCE RETURN ON CAPITAL EMPLOYED1 44% 35% 2020 Return on Capital Employed (ROCE) by asset 27% 28% 6% 14% Karma 6% 2018A 2019A 2020A 2018A 2019A 2020A Houndé Ity 23% BOUNGOU ROCE MANA ROCE KARMA ROCE 20% Capital Employed

  154. Slide 154: Contact Us

    ENDEAVOUR MINING , a CONTACT US T: +44 203 011 2719 investor@endeavourmining.com Follow us: endeavourmining.com CORPORATE OFFICE 5 Young Street London W8 5EH United Kingdom T: +44 203 011 2723 OPERATIONS OFFICE Hotel Palm Club Croisement Boulevard Latrille et rue du Lycée Technique Abidjan 08 BP 872