Image Resources Nl · ASX:IMA

Image Resources Nl — TZMI Virtual Congress 2021

35 slides from Image Resources Nl's conference presentation, Dec 20, 2021

  1. Slide 1: Targeting Growth in a Growing Market

    Targeting Growth in a Growing Market TZMI Virtual Congress 2021 10 Nov - 20 Dec 2021 Patrick Mutz Managing Director Image Resources NL ASX: IMA 1

  2. Slide 2: High Level Summary

    High Level Summary ASX Code IMA Share Price A$0.20 (26 Oct 2021) Market Cap A$202 million Cash on hand A$50 million (30 Sep 2021) Debt A$0 (effective Feb 2021) Dividend (inaugural) A$0.02/share (paid April 2021) Revenue Net Profit After Tax CY2019 A$146m A$20.8m Revenue Net Profit After Tax CY2020 A

  3. Slide 3: Transition to Mining

    Transition to Mining ¾ Image Resources is one of Australia’s newest established, profitable mining companies ¾ Boonanarring Mineral Sands Project located 80km north of Perth ¾ Project construction 2018 (on-time and on-budget) ¾ 1st production Dec 2018 ¾ Product(s): Heavy Mineral Concentrate (HMC) co

  4. Slide 4: Keys to success

    Keys to success ¾ Location – mine located 1 hour north of capital city of Perth in Western Australia ¾ High Grade – One of the highest in-situ grade projects of its kind in Australia Zircon Grade TiO2 Minerals Grade 2.4% >5% • Typical project grades might be 0.3-0.4% zircon and 2.5% titanium dioxide

  5. Slide 5: Keys to success (continued)

    Keys to success (continued) ¾ Simple Business Model • Shallow open cut mining (contracted) • Simple gravity separation • Simple concentrate product sold in bulk shipments ¾ 100% of production committed under life-of-mine off-take agreements at market pricing ¾ Strong market prices ¾ High demand for

  6. Slide 6: Boonanarring Operating Metrics

    Boonanarring Operating Metrics 2020 2020 2021 Item Units Actual Guidance Guidance HMC Production kt 306 300-330 290-320 HMC Sales kt 311 300-330 300-320 Project Operating Costs A$m 90 100-110 90-100 C1 Cash Costs A$/t HMC sold 292 290-320 290-320 AISC Cash Costs A$/t HMC sold 337 340-370 340-370 HMC

  7. Slide 7: Focus on Growth and Sustainability

    Focus on Growth and Sustainability ¾ Image has 12 zircon/titanium projects in its 100%-owed portfolio • All projects are located in Western Australia within an area of 1,200 square kilometres • All have identified Mineral Resources under the JORC Code and two have Ore Reserves • Only the first of th

  8. Slide 8: Select Project Comparisons

    Select Project Comparisons 1 Ore Reserves & Mineral Resources; in accordance with the JORC Code (2012) ------------------- as percent of 'HM (%)' ----------------- Project/Deposit Category Tonnes HM Slimes VHM Ilmenite Leucoxene Rutile Zircon (million) (%) (%) (%) (%) (%) (%) (%) 2 Boonanarring (Ore

  9. Slide 9: Tenement Portfolio Location

    Tenement Portfolio Location ¾ North Perth Basin in Western Australia ¾ 80 km north of Perth CBD ¾ Proven mineral sands address ƒ Including majors Iluka and Tronox ¾ Infrastructure rich ƒ Brand Highway access, ample grid power, gas pipelines, water sources available, abundant telecommunications etc.

  10. Slide 10: Tenement Portfolio Location

    Tenement Portfolio Location ¾ 1,200 km2 tenements portfolio ¾ 100% focus on mineral sands ¾ Strandline (dry open cut mining) projects ¾ Dredge mining projects 10

  11. Slide 11: Projects Pyramid – Strand Deposits

    Projects Pyramid – Strand Deposits Ore Reserves and Mineral Resources (statements in appendix) Accessible by Dry Open-Cut Mining Projects ranked by combined Zircon plus Rutile Boonanarring OreReserves 6.1Mt;7.8%HM; asat31Dec2020 28.1%Zr+Ru Dredgeminingoption beingevaluated Atlas9.5Mt;8.1%HM;18.5%Zr+

  12. Slide 12: Projects Pyramid – Dredge Deposits

    Projects Pyramid – Dredge Deposits Mineral Resources (statements in appendix) Accessible by Dredge Mining Projects ranked by HM Grade 36% Leucoxene; Bidaminna 94%VHM; 102Mt; 2.2%HM; <4% slimes; 9.5% Zr+Ru <3% oversize Titan-Telesto 140Mt; 1.9%HM; 12.8% Zr+Ru Calypso 51Mt; 1.7% HM; 15.9% Zr+Ru 12 Tot

  13. Slide 13: Growth Strategy

    Growth Strategy Growth strategy; 4 components ¾ 1 of 4: Continue to use existing capital equipment to operate profitably with demonstrated mine life extensions ¾ Operations at Boonanarring to continue on existing Ore Reserves while Atlas project being developed ¾ Following depletion of Ore Reserves

  14. Slide 14: Growth Strategy (continued)

    Growth Strategy (continued) Growth strategy; 4 components ¾ 2 of 4: Look to develop a second mining centre to operate in parallel with existing operations ¾ Front-running project is 100%-owned Bidaminna project • 102 million tonnes Mineral Resources at 2.2% HM (see footnote) • 94% VHM, <4% slimes, <

  15. Slide 15: Growth Strategy (continued)

    Growth Strategy (continued) Growth strategy; 4 components ¾ 3 of 4: Investigate opportunities to invest in zircon/titanium projects outside of the current portfolio that are development ready and have substantial mine life • Potential to self-fund investments/acquisitions • Ability to attract low co

  16. Slide 16: Growth Strategy (continued)

    Growth Strategy (continued) Growth strategy; 4 components ¾ 4 of 4: Investigate the potential for a profitable gold production centre on Image’s 100%-owned gold-focused tenements and adjoining current Farmin tenement • Farmin tenement has historic gold mineralisation and is surrounded by one of Imag

  17. Slide 17: Image Resources – Beyond Operations: ESG

    Image Resources – Beyond Operations Environmental, Social and Corporate Governance (ESG) ¾ ESG framework being developed to facilitate growth to sustainable, mid-tier mining company ¾ Areas of specific focus beyond day-to-day mining and processing operations include: • Health, safety and well being

  18. Slide 18: Community Engagement Program

    Community Engagement Program ¾ Image is proud of its active and varied community support and engagement program including significant local employment. ¾ Since start of operations at Boonanarring, over 50% of the site workforce live locally or within regional shires. 18

  19. Slide 19: Solar Farm at Boonanarring

    Solar Farm at Boonanarring 2.3 MWAC solar farm ¾ Construction and operation by Sunrise Energy Group Pty Ltd ¾ Located on Image owned land adjacent to Boonanarring processing plant ¾ Commissioned Sep 2020 and providing on average 25% of electricity requirements for mining and processing operations ¾

  20. Slide 20: Solar Farm at Boonanarring

    Solar Farm at Boonanarring Boonanarring WCP Brand Highway 20

  21. Slide 21: Rehabilitation Snapshot: Before Mining – April 2018

    Rehabilitation Snapshot: Before Mining – April 2018 21

  22. Slide 22: Rehabilitation Snapshot: During Mining – June 2019

    Rehabilitation Snapshot: During Mining – June 2019 22

  23. Slide 23: Rehabilitation Snapshot: Backfilled – December 2019

    Rehabilitation Snapshot: Backfilled – December 2019 23

  24. Slide 24: Rehabilitation Snapshot: 13 hectares re-vegetated – August 2020

    Rehabilitation Snapshot: 13 hectares re-vegetated – August 2020 24

  25. Slide 25: Carbon Sequestration Research

    Carbon Sequestration Research Australian Carbon Farming Initiative ¾ As part of its focus to reduce its carbon footprint, Image is investigating cooperative work with local landowners near its mining operation under the Australian Carbon Farming Initiative ¾ The goal is to support the work of local

  26. Slide 26: Summary Highlights

    Summary Highlights Image Resources is an established, profitable mining company that… ¾ has accumulated a strong cash balance of A$50m following the early repayment of outstanding debt and paying an inaugural A$0.02/share dividend; ¾ has earned a positive reputation of being a successful project dev

  27. Slide 27: For further information

    For further information Image Resources NL info@imageres.com.au Office: +61 8 9485 2410 Level 2, 7 Ventnor Avenue West Perth, WA 6005 PO Box 469, West Perth, WA 6872 www.imageres.com.au 27

  28. Slide 28: Ore Reserves Summary – JORC 2012

    Appended information Ore Reserves Summary – JORC Code 2012 – as at 31 December 2020 28

  29. Slide 29: Mineral Resources – Material Mining Projects

    Appended information MINERAL RESOURCES – MATERIAL MINING PROJECTS Mineral Resources Summary – Material Mining Projects – JORC Code 2012 – as at 31 December 2020 1. Tonnages and grades have been rounded to reflect the relative uncertainty of the estimate, thus column sums may not equal. 2. Mineral Re

  30. Slide 30: Mineral Resources – Non-Material Projects

    Appended information MINERAL RESOURCES – NON-MATERIAL PROJECTS The Mineral Resources for the Company’s non-material mining projects as at 31 March 2021 are shown in the tables below. Inaugural Mineral Resources have been reported for Boonanarring Northwest and Boonanarring North Extension and Minera

  31. Slide 31: Previously Reported Mineral Resources – Strand Deposits

    Appended information Previously Reported Mineral Resources - Strand Deposits; in accordance with JORC Code (2004) @ 2.5% HM Cut-off ———-------—- as percent of "HM (%)' Project/Deposit Category Tonnes HM Slimes HM Tonnes VHM IImenite Leucoxene Rutile Zircon (million) __(%) (%) (million) _(%) (%) (%)

  32. Slide 32: Mineral Resources – Dredge deposits

    Appended information Mineral Resources - Dredge deposits; in accordance with JORC Code (2012) @ 1.0% HM Cut-off —------—----- as percent of HM (%)' -——----——---—- Project/Deposit Category Tonnes HM Slimes HMTonnes VHM ilmenite Leucoxene Rutile Zircon (million) (%) (%) _ (million) (4 (%) (%) (%) (%)

  33. Slide 33: Competent Person Statement and Previously Reported Information

    Appended information COMPETENT PERSON STATEMENT AND PREVIOUSLY REPORTED INFORMATION This report includes information that relates to Ore Reserves and Mineral Resources which were prepared and first disclosed under JORC Code 2012. The information was extracted from the Company’s previous ASX announce

  34. Slide 34: Appended information

    Appended information These reports are available to view on the Company’s website under “ASX Releases”. The Company confirms it is not aware of any new information or data that materially affects the information included in the original market announcements and, in the case of reporting of Ore Reser

  35. Slide 35: Appended information

    Appended information The information in this report that relates to tonnes, grade and mineral assemblage for Regans Ford deposit (not part of the Company's material mining projects) is based on historic information published by Iluka Resources Limited indicating the Mineral Resources were compiled i