Slide 1: Broken Hill Solar Plant Community Information Session
Broken Hill Solar 1 Plant Community Information Session 11 November 2015
Slide 2: Agenda
2 Agenda Welcome November CIS 1 2 Overview of project status – AGL 3 Local spending / employment 4 Project planning / community update 5 Next meeting > AGL Broken Hill Solar Plant > 11 November 2015
Slide 3: Review actions from previous meeting
3 2. Review actions from previous meeting Action item CIS Status Who meeting 1 AGL contact Broken Hill PROBUS group re: solar plant September Closed HO site visit 2015 2 AGL to provide a comparison of generation between September Open AM solar power and wind energy 2015 3 AGL to organise community s
Slide 4: Overview of project status
4 Overview of project status • Adam Mackett (AGL) > Presentation title > Author > Date (Verdana 10pt)
Slide 5: AGL overview of project status: Solar Plant
5 2. AGL overview of project status Solar Plant › The changing face of the Broken Hill Solar Plant » Top: January 2015 (civil work) » Middle: September 2015 (prior to final module) » Bottom: October 2015 (full generation ~53 MW) › Final module (total 677,760) was installed on Monday, 12 October 2105
Slide 6: Connection Works (CPP)
6 2. AGL overview of project status Connection Works (CPP) › 2 x 22kV transmission line was practically complete at the end of February 2015, including crossing of the ARTC rail. › Operating protocol with TransGrid (Network Services Provider) has been finalised and executed. › Feeder No.2 was energi
Slide 7: Project Milestone: final module installation event
7 2. AGL overview of project status Project Milestone – final module installation event stakeholders: › Broken Hill City Council, Christine Adams and other Council representatives › State Government, Minister Anthony Roberts and Minister Mark Speakman, Minister Sussan Ley representative › Australian
Slide 8: Final module install event trending on Facebook
8 2. AGL overview of project status › Broken Hill Solar Plant final module install event, top trending story on Facebook for the day. > Broken Hill Solar Plant > 11 November 2015
Slide 9: Broken Hill Solar Plant full generation
9 2. AGL overview of project status Broken Hill Solar Plant › Full generation (53 MW) was achieved on Thursday 15 October 2015. > Broken Hill Solar Plant > 11 November 2015
Slide 10: Broken Hill Solar Plant full power generation
10 2. AGL overview of project status Broken Hill Solar Plant › Full power generation (53 MW) was achieved on Wednesday, 14 October 2015. > Broken Hill Solar Plant > 11 November 2015
Slide 11: Broken Hill Solar Plant cumulative generation
11 2. AGL overview of project status Broken Hill Solar Plant › Generation @ the point of connection (commenced Tuesday, 15 September 2015) › Cumulative generation at 23:30hrs on Friday, 6 Nov 2015 was 14,053.84** MWh » ** enough energy to supply approximately 2,000 average NSW homes (for the full ye
Slide 12: Generation and price spike
12 2. AGL overview of project status Broken Hill Solar Plant › Generation on Wednesday, 23 September 2015 – price spike in the PM peak. » AEMO Market Price Cap (MPC) is currently $13 800/MWh (as at 1 July 2015) › Generation from today, 11 November 2015 with actual pricing and forecast pricing based
Slide 13: Broken Hill solar and Hallett Hill wind weekly generation
13 2. AGL overview of project status Broken Hill Solar Plant › Generation from the Broken Hill Solar Plant (~53 MW) – 31 Oct – 6 Nov 2015. » Weekly generation = 2,116.93 MWh (NSW pricing) › Generation from the Hallett Hill Wind Farm (~71.4 MW) – 31 Oct – 6 Nov 2015. » Weekly generation = 3,848.34 MW
Slide 14: Nyngan Solar Plant
14 2. AGL overview of project status Nyngan Solar Plant › Generation @ the point of connection (commenced Saturday, 21 March 2015) › Cumulative generation at 23:30hrs on Friday, 6 Nov 2015 was 107,299.43** MWh » ** Gaps in June due to AEMO/EE SCADA – Nyngan was generation factored in cumulative tota
Slide 15: Project Planning: Broken Hill Landscape Plan
15 4. Project Planning Broken Hill Landscape Plan › Condition C3(c) of the project approval captures the requirement to develop proposed landscaping measures for discussion with the interested community to consider landscaping objectives and standards based on visual impacts and local environmental
Slide 16: Project planning: Broken Hill Landscape Plan
16 4. Project planning Broken Hill Landscape Plan > Broken Hill Solar Plant > 11 November 2015
Slide 17: Landscape Plan: Viewpoint 4 before and after
17 4. Project Planning Broken Hill Landscape Plan › Viewpoint 4 looking south west (before and after) > Broken Hill Solar Plant > 11 November 2015
Slide 18: Project spending
18 Project spending Adam Mackett (AGL) > Presentation title > Author > Date (Verdana 10pt)
Slide 19: Project spending
19 4. Project spending › Broken Hill Solar Plant construction generated direct spending for Broken Hill area - $14.8 million > AGL Broken Hill Solar Plant > 11 November 2015
Slide 20: Project Planning
20 Project Planning • Helena Orel (AGL) • Adam Mackett (AGL) > Presentation title > Author > Date (Verdana 10pt)
Slide 21: Community events
21 5. Community events › Community site tour – proposed morning of Saturday 28 November 2015 › Details will be emailed out to the group › Solar Plant Community Open Day – family day for the whole community › Planned for late February / early March (date to be confirmed) Broken Hill Solar Plant group
Slide 22: AGL Energy deals still ongoing
22 5. AGL Energy deals still ongoing AGL energy deals for Broken Hill businesses and residents › AGL Energy retail team has prepared energy deals specific for the Broken Hill community: › Businesses – 24% of electricity and solar, available now, $100 off first bill when signing up business and resid
Slide 23: Construction Community Fund
23 Construction Community Fund • Helena Orel (AGL) > Presentation title > Author > Date (Verdana 10pt)
Slide 24: Construction Community Fund
24 6. Construction Community Fund › 17 applications received › Assessment of the applications will be done this week with the review panel group › All applicants notified shortly afterwards of the outcome of their application > AGL Broken Hill Solar Plant > 11 November 2015
Slide 25: Next meeting
25 Next meeting > Presentation title > Author > Date (Verdana 10pt)
Slide 26: Next meeting
26 7. Next meeting › Any questions? › Future community meetings > AGL Broken Hill Solar Plant > 11 November 2015