  1. Slide 1: Amulsar Gold Project $325 Million Project Financing Package and Public Equity Issuance

    Lydian International Limited Amulsar Gold Project $325 Million Project Financing Package And Public Equity Issuance February 24, 2016 An amended and restated preliminary short form prospectus dated December 14, 2015 containing important information relating to the securities described in this docume

  2. Slide 2: Cautionary Statements

    Cautionary Statements Forward Looking Statements & Other Disclaimers Certain information contained in this presentation is “forward looking”. All statements in this presentation other than statements of historical fact, that address events, results, outcomes or developments that the Company expects

  3. Slide 3: Cautionary Statements (Cont'd)

    Cautionary Statements (Cont’d) Forward Looking Statements & Other Disclaimers This presentation uses terms that comply with reporting standards in Canada and certain estimates are made in accordance with National Instrument 43-101 – Standard of Disclosure for Mineral Projects (“NI 43-101”). NI 43-10

  4. Slide 4: Amulsar Gold Project Construction Ready

    Amulsar Gold Project Construction Ready Lydianinternational.co.uk | TSX:LYD

  5. Slide 5: Amulsar Gold Project - Armenia

    Amulsar Gold Project - Armenia Compelling Asset; Ready to Build • Large-Scale Gold Deposit 1 – Proven + Probable Reserves: 97 Mt @ 0.78gpt 2.4 M gold ounces – Measured + Indicated Resources: 122 Mt @ 0.77gpt 3.0 M gold ounces – Inferred Resources: 106 Mt @ 0.59gpt 2.0 M gold ounces – 25% of inferred

  6. Slide 6: Construction "Window" Open

    Construction “Window” Open Many Benefits Available and Support to Start • Amulsar Development Aligns with National Interests • Reduce ongoing high unemployment • Pay-down on growing national debt • Reverse trend of declining FDI • Local Community Support • Well attended and constructive participatio

  7. Slide 7: General Arrangement

    General Arrangement Cornerstones to Driving Improved Economics and Operability 7

  8. Slide 8: New Lower-Cost Mine Plan

    New Lower-Cost Mine Plan Improved Economics, Constructability, Operability and Sustainability Q4 2015 2014 Technical Report Technical Report • Value engineering critical Operating Information: to reducing overall Mine life – years 10.0 10.4 Average annual ore tonnes mined/processed – Mtpy 9.7 9.8 fi

  9. Slide 9: Amulsar Gold Project

    Amulsar Gold Project Sizable Upside Within & Near Reserves Pits 9

  10. Slide 10: Upside Potential In-Pit Inferred Resources

    Upside Potential 26 Mt In-Pit Inferred Resources – Priority Conversion Target In-pit Inferred Resources 45,000 40,000 35,000 30,000 Tonnes Per Annum 25,000 20,000 15,000 10,000 5,000 - Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Ore Inferred in waste Other waste Annual pro

  11. Slide 11: Strong Financing Partners

    Strong Financing Partners Project financing backed by seasoned mining investors Orion RCF Total (US$M) (%) (US$M) (%) (US$M) Term Facility $ 140.5 88% $ 19.5 12% $ 160.0 Stream $ 37.5 63% $ 22.5 38% $ 60.0 Private Placement $ 24.2 31% $ 53.4 69% $ 77.6 Cost Overrun Facility $ 22.0 88% $ 3.0 12% $ 25

  12. Slide 12: Financing: Achieves 75% of Funds Required

    Financing: Achieves 75% of Funds Required Cost Overrun Provides Added Buffer Beyond Capex Contingency Uses: Sources: Financing Requirement Financing Package 1 Development Capital Costs $ 370 Term Loan Facility $ 160 2 Financing Costs and Working Capital 25 Equity Private Placements 80 395 Stream 60

  13. Slide 13: Merits of the Transaction

    Merits of the Transaction 75% of Total Financing – On Competitive, Flexible Terms • Substantially funds Amulsar to production, leaving open only: • $25 million public offering, allowing existing shareholders to participate • Equipment financing packages • Significantly reduces equity requirement and

  14. Slide 14: Trading Comparables

    Trading Comparables As a financed developer there is potential for Lydian to re-rate Lydian Unfinanced Developers Financed Developers Juniors P/NAV (x) P/NAV (x) P/NAV (x) Producers(2) P/NAV (x) 1.0x 0.8x Based on C$0.295 0.8x 0.9x 0.9x share price 0.7x Average: 0.8x 0.8x 0.7x Average: 0.6x 0.5x 0.5

  15. Slide 15: Next Steps

    Next Steps Catalysts: Focus Toward Construction • Financing • Satisfy conditions of the Financing Transactions, including: – Move to mandates for equipment financing – Complete the public equity offering of not less than $25 million • Value Engineering Driving Amendments • EIA and Mining Right amend

  16. Slide 16: Supplemental Information

    Supplemental Information Lydianinternational.co.uk | TSX:LYD

  17. Slide 17: Supplemental Information: Amulsar Gold Project

    Supplemental Information: Amulsar Gold Project Lydianinternational.co.uk | TSX:LYD

  18. Slide 18: Amulsar Gold Project - Large Scale Oxide Deposit

    Amulsar Gold Project Large Scale Oxide Deposit Tonnes Au Grade Ag Grade Contained Au Contained Ag (M) (g/t) (g/t) (Moz) (Moz) Mineral Resources Measured + Indicated 122.4 0.77 3.5 3.0 13.9 Inferred 106.2 0.59 2.6 2.0 9.0 Mineral Reserves Proven + Probable 96.7 0.78 3.6 2.4 11.3 Notes to Mineral Reso

  19. Slide 19: Pre-Production Capital Costs

    Pre-Production Capital Costs Updated for Met Testing, Additional Design, Vendor Engagement $ Millions Reduction of $56M over 2014 Contracted Direct Costs: Infrastructure and facilities $ 77.4 Technical Report. Key savings in the Earthworks 51.4 areas of: Heap leach pad 18.9 Mine pre-production 14.1

  20. Slide 20: Operating Cost Comparison

    Operating Cost Comparison Reduced power, reagents and consumables Nov-15 Oct-14 Nov-15 Oct-14 $/ore $/ore Increase Increase Description $/oz $/oz tonne tonne (Decrease) (Decrease) Mining $ 5.83 $ 7.58 $ (1.74) $ 267 $ 362 $ (95) Processing 2.69 3.72 $ (1.03) 123 178 $ (55) General and administrative

  21. Slide 21: Key Infrastructure

    Amulsar Gold Project Key Infrastructure Local Communities Resources for supplies, housing, other Dedicated local workforce Transportation Adjacent to existing road & rail routes Sealed highway from Yerevan to site Utilities High tension power lines, substation, Fiber optics, gas line & water at site

  22. Slide 22: Land Acquisition

    Land Acquisition Key De-Risking Activities • Required following relocation of HLF from Site 14 – Phases 1 & 2: HLF valley area – Phase 3: Conveyor corridor – Phase 4: Buffers • Status – Phases 1 & 2 – Started February 2015 – 97.5% of titles transferred – Continuing negotiations and administrative pr

  23. Slide 23: Environmental, Biodiversity & Social

    Environmental, Biodiversity & Social Pre-Construction Requirements • EIA and Mining Right Amendment • Amendment for value engineering in process • Filed December 2015 • Expect to complete Q2 2016 • ESIA Amendment – Performance Standard Requirement • Amendment for value engineering in process • Prepa

  24. Slide 24: Supplemental Information: Financing Details

    Supplemental Information Financing Details Lydianinternational.co.uk | TSX:LYD

  25. Slide 25: Summary of the Transaction

    Summary of the Transaction Multi-tranche financing minimizes equity dilution Amount Summary Description1 ($ million) $160 Term Loan • LIBOR2 + 6.5% maturing September 30, 2021 • Interest and principal holiday until June 30, 2018 $60 Stream • 6.75% of 2.1Moz gold and 100% of 0.7Moz silver stream (bas

  26. Slide 26: Background of the Transaction

    Background of the Transaction Consideration Given to a Range of Options • Do Nothing – Hold for Brighter Days – Risk to Social License: Government/community support (trust) will be damaged if Lydian fails to advance – Risk to Permit: Mining Right requires substantial construction by Nov 2016 – Risk

  27. Slide 27: Background of the Transaction (Continued)

    Background of the Transaction (Continued) Consideration Given to a Range of Options • Build it Smaller – 2012 Feasibility Study • Started at 5 Mtpa, with expansion to 10 Mtpa in Year 4 • Study recommended to conduct a more detailed review of a 10Mtpa production rate from day 1 • Financing not secure

  28. Slide 28: 10% Cost for Leverage Components

    10% Cost for Leverage Components Favourable Pricing for Orion/RCF Elements; Capped Stream/Offtake • Term Loan & Stream Provide $220 Million of Leverage – Stream and Offtake spread costs to later years – allows additional leverage capacity in early years for Term Loan and anticipated equipment financ

  29. Slide 29: Term Loan Facility

    Term Loan Facility Six Year Term Debt Funding • $160 Million Project Debt Financing • $50 million available through September 2016 • $110 million available through September 2017 • 5 million warrants issuable to lenders on closing of public equity offering • No hedging requirements • No reserve acco

  30. Slide 30: Stream Agreement

    Stream Agreement Capped Deliveries Retain Upside on Growth Potential • $60 Million Deposit for: • 6.75% of refined gold, up to 142,000 ounces • 100% of refined silver, up to 695,000 ounces • Deposit Payable • $25 million, subject to closing conditions (initial security) • $35 million, 3 – 9 months p

  31. Slide 31: Offtake & Cost Overrun Facility

    Offtake & Cost Overrun Facility Cushion Beyond $38 Million Contingency in Pre-Construction Capital Costs • Offtake Deliveries • Capped at current reserves of 2.1 million ozs less stream ozs • Prevailing price during quotational period • Reduction of quotational period possible if certain milestones

  32. Slide 32: Clarity on Stream and Offtake Agreements

    Clarity on Stream and Offtake Agreements Market Terms, with Buyback and Reduction Potential • Stream Transaction – Capped on reserves: maximum deliveries of 142,500 gold ozs and 695,000 silver ozs – If shareholder approval not received or public offering not completed within 9 months: • Repurchase i

  33. Slide 33: Equity Private Placements

    Equity Private Placements Participating Alongside Public Equity Offering • $80 Million Subscription • Occurs when public offering is complete • Non-brokered, but subject to 3% equity origination fee to subscribers • Maximum price of C$0.35 – a 38% premium to 5-Day VWAP (at Nov 30) • Public Offering

  34. Slide 34: Supplemental Information: General Information

    Supplemental Information: General Information Lydianinternational.co.uk | TSX:LYD

  35. Slide 35: Corporate Overview

    Corporate Overview Pre-Transaction Symbol TSX: LYD Share Capital Shares Outstanding 184.6 million At 30-Sept-15 Stock Options 7.3 million Fully Diluted Shares 191.9 million Market Cap At C$0.27 1 C$50 million Cash At 30-Sept-15 2 $10.4 million Financing Debt: 30-Sept-15 Nil Off Balance Sheet 3% Roya

  36. Slide 36: Company Summary: Research Coverage & Shareholders

    Company Summary Research Coverage & Shareholders Research • Bank of Montreal, Andrew Breichmanas Coverage • GMP Securities, Oliver Turner • National Bank, Shane Nagle • Scotiabank, Trevor Turnbull 36

  37. Slide 37: Board of Directors

    Board of Directors Development-Oriented; Independent, Diverse Experience Gordon Wylie (Chair) Non-Executive Director Howard Stevenson President, CEO & Director Member since 2009 32 yrs mining experience Member since 2014 25 yrs global mining experience AngloGold-Ashanti Global Alacer Gold President

  38. Slide 38: Management Team

    Management Team Leadership Experience for Development Doug Tobler Chief Financial Officer Dr. Hayk Aloyan MD, Geoteam (Armenia) Since 2014 33 yrs finance, accounting and Since 2006 17 yrs mineral exploration mining experience Armenian metallogenesis and Alacer Gold CFO resource specialist PwC, equit

  39. Slide 39: Republic of Armenia

    Republic of Armenia Overview Population: 3 million Capital: Yerevan, population 1.2 million Government: President: Serzh Sargsyan (elected in 2013, second term) Prime Minister: Hovik Abrahamyan Literacy: Total population: 99.4% (M: 99.7% / F: 99.2%) Exports: 50% of Armenian exports by value are Mine

  40. Slide 40: Armenia and Mining

    Armenia and Mining Priority for Foreign Direct Investment • Amulsar will be the largest gold mine in Armenia • Mining in Armenia: – $320 million invested in exploration and development of the Teghout copper and molybdenum deposit by Vallex Group through 2014 – Producing • Cronimet Mining AG • Dundee

  41. Slide 41: Thank you

    Thank you Lydianinternational.co.uk | TSX:LYD

Lydian International — Investor Presentation (February 2016) on 6ix