LSB Industries, Inc. · NYSE:LXU

LSB Industries — El Dorado Chamber of Commerce, February 8, 2023

20 slides from LSB Industries's conference presentation, Feb 8, 2023

  1. Slide 1: El Dorado Chamber of Commerce

    Slide 1: El Dorado Chamber of Commerce

    El Dorado Chamber of Commerce LSB Industries Jakob Krummenacher February 8, 2023

  2. Slide 2: LSB Industries at a glance

    Slide 2: LSB Industries at a glance

    LSB Industries at a glance Business Overview LSB is the fifth largest ammonia producer in the U.S. § LSB Industries, founded in 1968 and headquartered in Oklahoma City, OK, is a publicly traded company that manufactures and sells chemical products for the agricultural, mining and industrial markets

  3. Slide 3: LSB Industries Growth Initiatives

    Slide 3: LSB Industries Growth Initiatives

    LSB Industries Growth Initiatives • Advancing safety programs • Capacity expansion through already underway and debottlenecking of existing implementing new ones plants • Investing capital to Becoming Pursue • Evaluate new capacity promote safe, reliable expansion operations and expand Best in Class

  4. Slide 4: Hydrogen and ammonia are expected to be the main carbon-free energy sources in the future

    Slide 4: Hydrogen and ammonia are expected to be the main carbon-free energy sources in the future

    Hydrogen and ammonia are expected to be the main carbon-free energy sources in the future ENERGY TRANSITION TO CLEAN ENERGY Today Tomorrow • NG • Renewable Electricity • Renewable • Electricity • RNG Heating • Heating oil Electricity • Hydrogen • RNG • Propane • Ammonia • Renewable Electricity • Ren

  5. Slide 5: Why is low carbon ammonia an essential fuel to decarbonize societies in the future?

    Slide 5: Why is low carbon ammonia an essential fuel to decarbonize societies in the future?

    Why is low carbon ammonia an essential fuel to decarbonize societies in the future? Levelized CO2e Emissions from the Life Cycle of Various Fuels Grams of CO2e per MJ of fuel 140 132 Production Combustion With all process CO2 captured 120 (~60% of total) 112 102 100 100 83 H2 NH3 81 80 80 Energy Den

  6. Slide 6: Producing low carbon ammonia at El Dorado, AR

    Slide 6: Producing low carbon ammonia at El Dorado, AR

    Producing low carbon ammonia at El Dorado, AR Flue Gas CO2 Process Carbon Pipeline Permanent CO2 Capture Sequestration Nat Gas Steam H2 Ammonia Ammonia Water Methane 375kt Blue N2 Synthesis 75kt Grey Reforming Air Nat Gas for heating § Agreement with Lapis Energy to develop the CO2 capture and seque

  7. Slide 7: Project Blue

    Slide 7: Project Blue

    Project Blue El Dorado Chamber of Commerce 8 February 2023 Reg Manhas – CEO, Lapis Energy

  8. Slide 8: Lapis Energy

    Slide 8: Lapis Energy

    Lapis Energy Lapis enables cost-effective decarbonization for energy-intensive industries through carbon capture and sequestration (CCS). As the Lapis value proposition partner of choice, we prioritize health, safety and the environment and foster strong relationships with local stakeholders through

  9. Slide 9: Cresta Fund Management Overview

    Slide 9: Cresta Fund Management Overview

    Cresta Fund Management Overview A strong history of supporting teams that develop customized solutions for energy and industrial customers • Cresta Fund Management (“Cresta”) is a Dallas-based middle-market infrastructure investment firm founded in Project Cost Customer Key Experience Project Descri

  10. Slide 10: Project Blue - Benefits for El Dorado and Arkansas

    Slide 10: Project Blue - Benefits for El Dorado and Arkansas

    Project Blue - Benefits for El Dorado and Arkansas Opportunity for State and El Dorado to demonstrate global leadership in a new & growing industry Enabling local industry to maintain competitiveness in marketing and sales of “blue ammonia” • Capital budget of complete project in excess of $50 milli

  11. Slide 11: Project Blue Update

    Slide 11: Project Blue Update

    Project Blue Update Schedule to start injection in 1H 2025 (subject to timing of EPA Class VI approval) Complete Secure pore Final plume Class VI well submittal Progress Class VI injection Feasibility Finance & tax equity Drilling space model Class VI FEED submittal 1 2 3 4 5 6 7 ~2Q 2022 ~3Q 2022 ~

  12. Slide 12: How is CO2 captured and stored?

    Slide 12: How is CO2 captured and stored?

    How is CO2 captured and stored? Injected into deep reservoirs, permanently containing the CO2 and avoiding atmospheric release surface cased • The reservoirs holding the CO2 are USDW Sparta approximately 3500-6500 ft below the Cane River Seal surface and 3000 ft below the area Wilcox drinking water

  13. Slide 13: Managing the CO2 plume for years post injection

    Slide 13: Managing the CO2 plume for years post injection

    Managing the CO2 plume for 50 years post injection Plume models – base case 5-year injection per zone Smackover Cotton Valley 1, 2 & 3 Hosston • Models include dissolution, but not hysteresis (models after inclusion of injection well core data will probably After 5-year injection reduce further) • 4

  14. Slide 14: EPA class VI approval process

    Slide 14: EPA class VI approval process

    EPA class VI approval process Close involvement of the EPA in all aspects of the CCUS project from inception to closure current focus 14

  15. Slide 15: Proposed monitoring scheme and injection well

    Slide 15: Proposed monitoring scheme and injection well

    Proposed monitoring scheme and injection well Two deep monitoring wells and one shallow monitoring location, one injection well Proposes Injection Well Design • Firm-up final well locations, based on drilling rig access • Supplement subsurface monitoring with indirect monitoring; 4D VSP, 4D sparse a

  16. Slide 16: Pore space rights required for the project

    Slide 16: Pore space rights required for the project

    Pore space rights required for the project As plume models increase in accuracy, they indicate less pore space (surface tracts) are required Pore Space Rights: There is no oil and gas (or other mineral value) beneath the project/plume area Pore space rights reside with the surface rights holder Have

  17. Slide 17: Topsides Plant

    Slide 17: Topsides Plant

    Topsides Plant TOPSIDES COMPRESSOR PLANT COMPRESSOR COMPRESSOR STAGE 1-3 STAGE 4-5 AMMONIA SUBSURFACE PLANT TEG PLANT BLOWER DEHYDRATION COMPRESSOR COMPRESSOR STAGE 1-3 STAGE 4-5 17

  18. Slide 18: CO2 Supply & CO2 to Injection Final Route

    Slide 18: CO2 Supply & CO2 to Injection Final Route

    CO2 Supply & CO2 to Injection Final Route Compressor Plant CO2 Supply CO2 Injection Brid ge o v er t rack s New pipe rack Brid ge o ver Brid roa d ge o Existing pipe rack Br ver pon id d ge ov er ant oar f pl d So 00m ll ~4 We 18

  19. Slide 19: Early and Transparent Stakeholder Engagement

    Slide 19: Early and Transparent Stakeholder Engagement

    Early and Transparent Stakeholder Engagement Lapis and LSB have been actively discussing the project in El Dorado and Little Rock Lapis has been engaging with local stakeholders since June 2022 o We have met with local El Dorado energy industry leaders o Lapis has joined the El Dorado Chamber of Com

  20. Slide 20: Thank You

    Slide 20: Thank You

    Thank You