  1. Slide 1: Canada Water Development Construction Liaison Forum

    Canada Water Development Construction Liaison Forum Plots A1 & A2 (and surrounding area) 13 October 2022

  2. Slide 2: Overview of tonight's presentation

    • Introductions and meeting terms of reference • Canada Water development • Construction management • Updates from contractors • Construction of Plot A1 (Wates) Overview of • Construction of Plot A2 (Mace) tonight’s • Canada Dock (Galldris/British Land) • Surrey Quays Shopping Centre cark park prese

  3. Slide 3: Our presenters

    Our presenters SARAH WARD MICHAEL DELFS Construction Neighbour British Land Liaison Manager KATIE CARDWELL DANIEL BOULTON STUART MCLEISH Contractor, Wates Contractor, Mace Contractor, Galldris Construction of Construction of Canada Dock Plot A1 Plot A2

  4. Slide 4: Wider Canada Water development works

    Wider Canada Water development works

  5. Slide 5: Plots A1 & A2

    Plots A1 & A2 • Plot A1 is a 35-storey building providing 186 new homes (including intermediate affordable homes), as well as office space and shops and restaurants at ground floor level. • Plot A2 is up to six storeys in height, providing new office space, as well as shops and places for eating and

  6. Slide 6: Site layout and vehicle access

    Site layout and vehicle access • The haul road, by the former Rotherhithe Police Station, is shared between Plots A1 and A2 and controlled by Alandale Group. • The entrance to the haul road is on Lower Road. Traffic marshals are located on Lower Road to ensure there is no traffic build up and to ens

  7. Slide 7: Common working practices

    Common working practices Standard construction working hours: Noise, dust and vibration monitoring and reporting • Monday – Friday: 8am - 6pm • In line with industry standards and the Construction Management Plans for each development site, environmental • Saturday: 8am - 2pm (no noisy works before

  8. Slide 8: Plot A1

    Plot A1 se li “ | ili, ane

  9. Slide 9: Plot A1 – Current site activity

    Plot A1 – Current site activity • Bulk dig nearing completion. • Concrete tower construction is currently at level 6 out of 33. • Concrete office block has started works in the basement. • Basement slab is 70% complete. • Ground floor slab works commenced. • The last of the three tower cranes has no

  10. Slide 10: Plot A1 – Indicative timeline

    Plot A1 – Indicative timeline

  11. Slide 11: Plot A2

    liimace Plot A2

  12. Slide 12: Plot A2 – Current site activity

    Plot A2 – Current site activity • Bulk excavation works now complete. • Work continues to complete the basement box, including the swimming pools for the leisure centre and laying the ground floor slab. • The west and central stair cores of the building are progressing vertically to the roof level o

  13. Slide 13: Plot A2 - Steel Phase works

    Plot A2- Steel Phase works • Steel frame works to begin late October, scheduled to complete Q2 2023. • Works include: • Tower cranes will lift large steel components • Steel components will be fixed with bolt guns • Operatives will work from MEWPs • Includes laying precast concrete floor plank • Lim

  14. Slide 14: Plot A2 – Indicative timeline

    Plot A2 – Indicative timeline

  15. Slide 15: Canada Dock

    Canada Dock

  16. Slide 16: Canada Dock – site activity

    Canada Dock – site activity • Further enabling works in the Dock, due to begin 24th October, include: • Installation of hoarding • Removal of existing timber structures to start to secure the site and create access into the Dock • Installation of ramp into the Dock from site compound • UXO Surveys •

  17. Slide 17: — Rorehale tomecal

    — Rorehale tomecal one works ‘ Hoarding wutaliation works Remove of timber « piers i —— VED Survey works

  18. Slide 18: Surrey Quays Shopping Centre car park works

    Surrey Quays Shopping Centre cark park works Ongoing alterations to the car park continue to creating a new site compound to facilitate the upgrade of Surrey Quays Station (Transport for London). • Works include: • Reconfiguration of existing car park area • Realignment of Deal Porters Way • Constru

  19. Slide 19: Surrey Quays Road – enhancement works

    Surrey Quays Road – enhancement works • Works to improve footpath and area surrounding it from Canada Water bus station down to King George's field begin at the end of October. • Activities include: - Pavement cleaning and repairs - Install new planter - Replacing mesh fencing - Painting lamp column

  20. Slide 20: Former Dock Offices – refurbishment

    Former Dock Offices – refurbishment • Internal and external refurbishment work is taking place at the former Dock Offices. • As part of these works, landscaping is being undertaken in the Dock Office courtyard. • Works are due to be complete by the end of 2022.

  21. Slide 21: Q&A Contact us