  1. Slide 1: PNC Infratech Limited Result Update Presentation - Q4 & FY19

    PNC Infratech Limited Result Update Presentation - Q4 & FY19

  2. Slide 2: Safe Harbour

    Safe Harbour This presentation and the accompanying slides (the “Presentation”), which have been prepared by PNC Infratech Limited (the “Company”), have been prepared solely for information purposes and do not constitute any offer, recommendation or invitation to purchase or subscribe for any securi

  3. Slide 3: Key Highlights & Financials

    1 Key Highlights & Financials PNC infratech 3

  4. Slide 4: Key Highlights for Q4 FY19

    Key Highlights for Q4 FY19 Q4 FY19 Rs. 140 crores +25% Q4 FY19 Rs. 151 crores +47% Q4 FY19 +54% Q4 FY18 Rs. 1,076 crores Rs. 112 crores Q4 FY18 Rs. 103 crores Q4 FY18 Rs. 701 crores * - Excludes bonus of Rs. 58.23 crores from Q4 FY18 PNC infratech 4

  5. Slide 5: Key Highlights for FY19

    Key Highlights for FY19 Rs.12,210 97 +71% +66% +29% crores Days Revenue EBITDA PAT Orderbook Net Working Capital Revenue* of Rs. 3,072 EBITDA* of Rs. 432 PAT of Rs. 325 crores Remaining value of Net Working Capital crores in FY19 as crores in FY19 in FY19 compared to contracts under Days of 97 Days

  6. Slide 6: Key Highlights: Early Completion Bonus

    Key Highlights: Early Completion Bonus Agra - Lucknow Raebareli - Jaunpur Aligarh - Moradabad Expressway BOT (Annuity) Project Highway Project ✓ Received Rs. 58.23 crore ✓ Received Rs. 33.73 crore ✓ Received ‘Provisional onus for the early towards the 'Bonus Annuity' Completion Certificate’ (PCC) co

  7. Slide 7: Financial Closure Achieved for all HAM Projects

    Financial Closure Achieved for all HAM Projects Financial Closure Achieved for All 7 Projects of which 6 Project are Under Construction Jul-16 Mar-17 Mar-17 Mar-17 BPC - BPC - BPC – BPC - Rs. 881 Crores Rs. 1,434 Crores Rs. 1,310 Crores Rs. 1,410 Crores 2 laning with paved shoulders 6 laning Chitrad

  8. Slide 8: Order-book Details

    2 Order-book Details PNC infratech 8

  9. Slide 9: Robust Order-book of over Rs. 12,200 crores

    Robust Order-book of over Rs. 12,200 crores Remaining Key EPC Projects Under Awarding Value Construction Authority (Rs. Crores) Nagpur-Mumbai MSRDC 1,999 Expressway Chakeri-Allahabad NHAI 1,866 ◼ Remaining value of contracts under execution of Purvanchal Expressway, Rs. 12,210 crores as on March 31,

  10. Slide 10: Execution Status of Key Project

    Execution Status of Key Project Project Project Type Execution Status Nagina-Kashipur EPC Appointed Date received and project is under-construction Koliwar-Bhojpur EPC Appointed Date received and project is under-construction Bhojpur-Buxar EPC Appointed Date received and project is under-constructio

  11. Slide 11: Portfolio of Development Projects on PPP Mode

    3 PORTFOLIO OF DEVELOPMENT PROJECTS ON PPP MODE PNC infratech 11

  12. Slide 12: Sizeable Project Portfolio: Operational Projects

    Sizeable Project Portfolio: Operational Projects PNC Share of Invested Total Debt as on % State / JV Kms / TPC Invested Grant Project Authority Type Equity Debt 31st Mar. ’19 Stake Stretch Partners Lanes (Rs. Crs) Amount (Rs. Crs) (Rs. Crs) (Rs. Crs) (Rs. Crs) (Rs. Crs) Ghaziabad UP / SREI, 67.9 / 3

  13. Slide 13: Asset Monetization Plan

    Asset Monetization Plan ◼ Execution of Share Purchase Agreement (SPA) for Divestment of Stake in “Ghaziabad Aligarh Road Project” ✓ Signed SPA for sale of 35% stake (includes 19.88% holding with wholly owned subsidiary of PNC Infratech Ltd.) with Cube Highways and Infrastructure Pte. Ltd. on May 04,

  14. Slide 14: Final Arbitration Award in Narela Industrial Estate Project

    Final Arbitration Award in Narela Industiral Estate Project ◼ Realized Rs. 145.63 crore towards the final arbitration award published in its favour of PNC Delhi Industrialinfra Private Limited on 17th May 2019 ✓ PNC Delhi Industrialinfra Private Limited is a wholly owned subsidiary of the Company an

  15. Slide 15: Sizeable Project Portfolio: HAM Projects

    Sizeable Project Portfolio: HAM Projects PNC Share of Invested Total Debt as on % State / JV Kms / TPC Invested Project Authority Type Equity Debt 31st Mar. ’19 Stake Stretch Partners Lanes (Rs. Crs) Amount (Rs. Crs) (Rs. Crs) (Rs. Crs) (Rs. Crs) Raj/ 83.45/ Dausa-Lalsot 100% NHAI Hybrid - 820 59 59

  16. Slide 16: Annexure I – Summary Financials

    4 Annexure I – Summary Financials PNC infratech 16

  17. Slide 17: Standalone Profitability Statement – Q4

    Standalone Profitability Statement – Q4 Rs. Crores Q4 FY19 Q4 FY18 YoY Growth (%) REVENUE* 1,075.71 700.65 54% EBITDA* 151.18 102.68 47% EBITDA margin* 14.1% 14.7% -60 Bonus 0.00 58.23 Other Income 12.26 6.64 Depreciation 28.22 21.68 Interest 19.40 8.54 Profit Before Tax 115.82 137.34 Total Tax Expe

  18. Slide 18: Standalone Profitability Statement – Full Year

    Standalone Profitability Statement – Full Year Rs. Crores FY19 FY18 YoY REVENUE* 3,071.57 1,798.35 71% EBITDA* 432.0 260.60 66% EBITDA margin* 14.1% 14.5% -43 Bonus 25.30 58.23 Other Income 43.04 23.02 Depreciation 92.24 77.20 Interest 64.09 30.72 Profit Before Tax 344.04 233.93 47% Total Tax Expens

  19. Slide 19: Standalone Balance Sheet

    Standalone Balance Sheet ASSETS (Rs. Crores) Mar-19 Mar-18 EQUITY AND LIABILITIES (Rs. Crores) Mar-19 Mar-18 (1) NON-CURRENT ASSETS EQUITY (a) Property, plant & equipment 613.51 404.81 (a) Equity Share capital 51.31 51.31 (b) Capital work-in-progress 6.21 11.14 (b) Other equity 2,063.89 1,755.39 (c)

  20. Slide 20: Net Working Capital Days

    Net Working Capital Days* 136 136 124 129 122 122 109 113 112 92 97 86 68 73 Mar/13 Mar/14 Mar/15 Mar/16 Mar/17 Mar/18 Mar/19 Debtors Net Working Capital * - Standalone PNC infratech 20

  21. Slide 21: Consolidated Profitability Statement – Full Year

    Consolidated Profitability Statement – Full Year Rs. Crores FY19 FY18 YoY REVENUE* 3,749.1 2,353.16 59% EBITDA* 981.5 710.86 38% EBITDA margin* 26.2% 30.2% -403 Bonus 25.30 58.23 Other Income 46.62 24.35 Depreciation 346.46 261.81 Interest 347.98 309.31 Profit Before Tax 358.98 222.33 61% Total Tax

  22. Slide 22: Segmental Revenue Break-up – Full Year

    Segmental Revenue Break-up – Full Year FY18 FY19 606 717 1,747 3,032 EPC* Toll/Annuity EPC* Toll/Annuity * - EPC segment Excludes bonus of Rs. 25.30 crores from Q1 FY19 and Rs. 58.23 crores from Q4 FY18 PNC infratech 22

  23. Slide 23: Consolidated Balance Sheet

    Consolidated Balance Sheet ASSETS (Rs. Crores) Mar-19 Mar-18 EQUITY AND LIABILITIES (Rs. Crores) Mar-19 Mar-18 (1) NON-CURRENT ASSETS EQUITY (a) Property, plant & equipment 616.70 409.23 (a) Equity Share capital 51.31 51.31 (b) Capital work-in-progress 6.21 11.14 (b) Other equity 1,973.08 1,637.40 (

  24. Slide 24: Annexure II – Company Overview

    5 Annexure II – Company Overview PNC infratech 24

  25. Slide 25: Introduction

    Introduction Established track record of timely/early completion of projects Infrastructure construction, Executed 64 major development and infrastructure projects management company; spread across 13 states, of expertise in execution of which 41 are road EPC projects including highways, projects; c

  26. Slide 26: Business Overview

    Business Overview Operating 6 BOT & 1 OMT Design, procurement and project, comprising of both construction of track and Set up power toll & annuity assets; Total 7 track related works on transmission lines of HAM projects comprising - 6 Mughalsarai - Sonnagar approximately 350 HAM project under- sec

  27. Slide 27: Corporate Structure

    Corporate Structure PNC Infra Holdings Limited (“PNCIHL”)  BOT Holdco for road and other infra projects PNC Bareilly Nainital Highways Private Limited (“PNCBNHPL”) 4 laning of the Bareilly-Almora section of SH 37 Ferrovia Transrail Solutions Private Limited (“FTSPL”) MP Highways Private Limited (“M

  28. Slide 28: Integrated Business Model

    Integrated Business Model Equipment Bank In-house Design & Engineering ◼ Ownership of a fleet of modern ◼ Controls the entire process from equipment enables quick mobilization conceptualization to commissioning of besides ensuring continuous a given project which helps in availability of critical eq

  29. Slide 29: Enhanced Execution Capability

    Enhanced Execution Capability Man and Machine added to execute more projects ◼ Strengthening of In-house execution team with induction of engineers with strong technical knowledge ◼ Investments in Machinery over the years to augment and upgrade the execution capabilities Strong Credit Rating Enhance

  30. Slide 30: Enhanced to augment & upgrade the execution

    Enhanced to augment & upgrade the execution Rs. Crores - Capex addition 1,016 291 725 600 125 429 380 171 49 FY15 FY16 FY17 FY18 FY19 Capex over last 4 years will enable us to achieve a Turnover of over Rs. 5,000 crores PNC infratech 30

  31. Slide 31: In-house Equipment Bank

    In-house Equipment Bank Name of Machinery OEM Quantity Heavy Duty Vehicles Ashok Leyland, Tata Motors 1,178 Diesel Generators Cummins/Jackson, Sudhir, Kirloskar, A/L, Greaves, Prakash, Escorts 469 Light Duty Vehicles and Attachments Mahindra, Tata, Farm Trac, John Deere 399 Passenger Vehicles Toyota

  32. Slide 32: Strengthening of In-house execution team

    Strengthening of In-house execution team Current Total Employees: Over 9,000 - Employee addition 9,075 3,300 5,775 4,284 1,491 3,776 3,947 337 171 FY15 FY16 FY17 FY18 FY19 Strengthening of In-house execution team with induction of engineers with strong technical knowledge PNC infratech 32

  33. Slide 33: Strong Credit Rating

    Strong Credit Rating Reaffirmed Reaffirmed Assigned ◼ PNC Infratech Ltd. ◼ PNC Khajuraho Highways Pvt. Ltd. ◼ PNC Bundelkhand Highways Pvt. Ltd. ✓ Long term bank facilities stands at ✓ Long term bank facilities at CARE A-; ✓ Assigned CARE A-; Stable (Single A CARE AA- (Double A Minus) Stable (Single

  34. Slide 34: Experienced Promoters

    Experienced Promoters Mr. Pradeep Kumar Jain Mr. Naveen Kumar Jain Mr. Chakresh Kumar Jain Mr. Yogesh Kumar Jain Chairman & Managing Director Promoter Managing Director & CFO Managing Director ◼ Over 39 years of experience ◼ Over 30 years of experience in ◼ Over 29 years of experience ◼ Over 24 year

  35. Slide 35: Board of Directors

    Board of Directors Mr. Pradeep Kumar Jain Mr. Chakresh Kumar Jain Mr. Yogesh Kumar Jain Mr. Anil Kumar Rao CMD Managing Director & CFO Managing Director Whole-time Director Mr. Krishan Kumar Jalan (IAS) Mr. Gauri Shankar Mr. Chhotu Ram Sharma Additional Independent Director Independent Director Inde

  36. Slide 36: Clientele

    Clientele > psiIpc Jpeida Delhi Stat dystal and Tfastrucure Developmen Upei of) saRTsUAR TAT Aw f =. Uttar Prad@h State Highways-Authority AY

  37. Slide 37: Growth Strategy

    Growth Strategy Diversification: ◼ Leveraging Strong Project Execution track record to diversify into new functional areas of infrastructure Diversification development ◼ Expand presence in development of industrial areas and dedicated freight corridor projects ◼ Diversify into waste management, wat

  38. Slide 38: For further information, please contact

    For further information, please contact: Company : Investor Relations Advisors : PNC Infratech Ltd Strategic Growth Advisors Pvt. Ltd. CIN: L45201DL1999PLC195937 CIN: U74140MH2010PTC204285 Mr. D. K. Maheshwari Mr. Jigar Kavaiya Vice President - Finance Group Account Head +91-9920602034 dkm@pncinfrat