Torex Gold Resources Inc. · TSX:TXG

Torex Gold Resources — Investor Presentation (November 2021)

40 slides from Torex Gold Resources's investor presentation, November 2021

  1. Slide 1: Corporate Presentation

    TSX | TXG CORPORATE PRESENTATION November 2021

  2. Slide 2: Safe Harbor Statement

    SAFE HARBOR STATEMENT THE PRELIMINARY ECONOMIC ASSESSMENT (THE “PEA” OR “2018 PEA”) IS BASED ON THE TECHNICAL REPORT ENTITLED “MORELOS PROPERTY, NI 43-101 TECHNICAL REPORT, ELG MINE COMPLEX LIFE OF MINE PLAN AND MEDIA LUNA PRELIMINARY ECONOMIC ASSESSMENT, GUERRERO STATE, MEXICO” DATED EFFECTIVE MARC

  3. Slide 3: Investment Highlights

    INVESTMENT HIGHLIGHTS Future underpinned by solid fundamentals Attractively Consistent operator valued relative to with industry-leading intermediate peers safety track record Financially strong gold Long-life potential producer with robust via Media Luna margins and a healthy project balance sheet

  4. Slide 4: Strategic Pillars

    STRATEGIC PILLARS Executing on plan expected to significantly enhance shareholder returns OPTIMIZE & ADVANCE & GROW RESERVES & EXTEND ELG DE-RISK MEDIA LUNA RESOURCES Build on culture as key strategic Deliver Media Luna Feasibility Robust multi-year drill program differentiator Study in Q1/22 on a c

  5. Slide 5: On Track to Achieve Guidance Three Years in a Row

    ON TRACK TO ACHIEVE GUIDANCE THREE YEARS IN A ROW1 Tracking towards upper end of guide range on production Production tracking at upper end of guided range Total cash costs (“TCC”)2 expected to be toward middle of guided range for the full year Q4 expected to be highest cost quarter given lower anti

  6. Slide 6: El Limón Guajes (ELG) – A Foundational Asset

    EL LIMÓN GUAJES (“ELG”) – A FOUNDATIONAL ASSET Future supported by strong cash flow and robust margins from ELG3 489,000 ozs of gold produced last 12 months (LTM) AISC2 margin of more than 50% LTM COVID Interruption Total EBITDA2 of $565M LTM Total free cash flow2 of $130M LTM COVID COVID Interrupti

  7. Slide 7: ESG Excellence as a Foundation

    ESG EXCELLENCE AS A FOUNDATION Sustained performance & ongoing improvement on ESG disclosure a key focus Staying COVID-19 Resistant ESG Ratings Strict protocols/screening remain in place MSCI: ‘A’ rating from ‘BBB’ 30% employees/contractors fully vaccinated and 70% Refinitiv: ‘B’ rating from ‘C’ par

  8. Slide 8: ESG Excellence as a Foundation

    ESG EXCELLENCE AS A FOUNDATION Delivering value to shareholders while making a positive difference in society Productive relationships with Strong governance & diversity focus employees Women make up 50% of Executive Team 99% workforce from Mexico; 60% from and 44% of Board of Directors Guerrero Sta

  9. Slide 9: Extending and Optimizing ELG a Key Strategic Priority

    EXTENDING AND OPTIMIZING ELG A KEY STRATEGIC PRIORITY Approval of El Limón pushback extends open pit mining Pushback of El Limón pit approved; extends open pit production to mid-2024 from late-2023 and adds ~150,000 ounces of production Accelerating near-term underground exploration to continue to e

  10. Slide 10: ELG Underground – A Significant Value Driver

    ELG UNDERGROUND – A SIGNIFICANT VALUE DRIVER Source of solid reserve growth over the last few years Mined gold production2 from ELG underground averaged 93 koz at a grade of ~7.5 g/t between 2019 and 2020 Mining rate of ~1,340 tpd YTD (Q3 2021) 84 koz mined YTD (Q3 2021) at a grade of ~7.1 g/t Under

  11. Slide 11: Multi-Year Production Outlook for ELG

    MULTI-YEAR PRODUCTION OUTLOOK FOR ELG On track to deliver a smooth transition between ELG and Media Luna2 ELG Only (excludes Media Luna) Guidance Outlook1,2 2021 2022 2023 2024 Gold Production koz 430 to 470 430 to 470 400 to 450 300 to 350 Gold production in 2022 expected to be in line with the gui

  12. Slide 12: Media Luna on Track for Production in Early 2024

    MEDIA LUNA ON TRACK FOR PRODUCTION IN EARLY 2024 De-risking and advancing Media Luna as per plan1,2 Media Luna has the potential to be Media Luna to leverage existing a multi-decade underground mine1,2 infrastructure at ELG 2018 PEA outlined average annual Advance rates in Guajes Tunnel AuEq sales o

  13. Slide 13: Media Luna Progress Update

    MEDIA LUNA PROGRESS UPDATE1,2 Tunnelling from both sides of Balsas expected to mitigate schedule risk1 Guajes tunnel now advanced 725m (875m of total development including lateral development) August: 55m of advance (70m total development) September: 115m of advance (170m total development) October:

  14. Slide 14: Media Luna Progress Update

    MEDIA LUNA PROGRESS UPDATE1,2 Technical Report on schedule for completion in Q1 2022 Several scope changes have been made to the design Capital expenditures in upcoming Feasibility Study of Media Luna versus design outlined in 2018 PEA: expected to be higher than in 2018 PEA due to: Access and mater

  15. Slide 15: Media Luna Expected to Extend Cash Flow Beyond ELG

    MEDIA LUNA EXPECTED TO EXTEND CASH FLOW BEYOND ELG Significant resource base with only 1/3rd of the magnetic anomaly drilled Media Luna would extend cashflow beyond life of ELG ~10 years based on 2018 PEA which assumed a top-end mining rate of 8,500 tpd2 ~7.5 years based on April 2021 Indicated reso

  16. Slide 16: Only a Portion of Land Package Has Been Drill Tested

    ONLY A PORTION OF LAND PACKAGE HAS BEEN DRILL TESTED 75% of the broader Morelos property remains largely unexplored1 Committed to investing $2.5M on regional exploration in 2021 Significant exploration potential remains across the broader Morelos property Multiple targets have been identified To dat

  17. Slide 17: Robust Cash Flow Funds Sustained Operations

    ROBUST CASH FLOW FUNDS SUSTAINED OPERATIONS Strong financial position to advance Media Luna3 Robust cash flow from ELG supportive of funding Media Luna and value accretive exploration Potential to utilize debt to be considered based on optimal capital structure entering the construction phase Over $

  18. Slide 18: Executing on Plan Expected to Deliver Re-Rating

    EXECUTING ON PLAN EXPECTED TO DELIVER RE-RATING Several key deliverables anticipated in the coming months Optimize & Extend Advance & De-Risk Grow Reserves & ELG Media Luna Resources Deliver consistent production Construction/development ELG Underground drill results and cash flow (ongoing) (ongoing

  19. Slide 19: Appendix

    Torex Gold RESOURCES INC. APPENDIX

  20. Slide 20: Safety and Operational Excellence Intertwined

    SAFETY AND OPERATIONAL EXCELLENCE INTERTWINED Culture focused on safety evident by ongoing performance LEADERSHIP: Getting the right people in the right roles at the right levels to drive business excellence SYSTEMS OF WORK: SYSTEMS OF WORK: Incident reporting & Business Process investigations Frame

  21. Slide 21: We Are Focused on Enhancing Our ESG Disclosure

    WE ARE FOCUSED ON ENHANCING OUR ESG DISCLOSURE Translating our actions associated with our values into real value1 ENVIRONMENT SOCIAL GOVERNANCE Zero Discharge Site (no discharge Exited 2020 with a LTIF of 0.15 per Seasoned Executive Team with into local watersheds) million hours worked 50% female r

  22. Slide 22: 2020 Responsible Gold Mining Report

    2020 RESPONSIBLE GOLD MINING REPORT Key Highlights 99% operations employees from Mexico; $64.3 million paid in salaries and benefits at site Industry leading safety performance Ratified two-year labour agreement with unionized employees (where annual agreements are the norm) 89% procurement spend in

  23. Slide 23: Innovation: A Key Part of the Torex DNA

    INNOVATION: A KEY PART OF THE TOREX DNA Leveraging innovation to drive value and mitigate risk ROPECON FILTERED TAILINGS SART PLANT Innovative 1.3 km automated conveyor “Dry-stack” filtered tailings facility Reduces consumption of our two most system which transports ore to our best-in-class in the

  24. Slide 24: El Limón Expansion Extends Open Pit Life into Mid-2024

    EL LIMÓN EXPANSION EXTENDS OPEN PIT LIFE INTO MID-2024 Pushback to support a smooth transition between ELG and Media Luna1 Board approval of El Limón open pit expansion (pushback) Expect to support a smooth transition between ELG and Media Luna Fit for purpose investment decision Adds ~150,000 ounce

  25. Slide 25: Cost Performance

    COST PERFORMANCE1,2 Cost control key to maintaining margins and offsetting inflationary pressures Open pit and underground mining unit costs higher than 2020 given maintenance costs and increased stockpile rehandling owing to RopeCon repairs Processing costs impacted by higher cyanide and reagent co

  26. Slide 26: Strong Cash Flow Generation

    STRONG CASH FLOW GENERATION1 Balance sheet continues to strengthen with $222M in cash at end of Q3 2021 Generated $88M in operating cash flow ($100M prior to changes in non-cash working capital) and more than $29M in free cash flow during the third quarter 1) All amounts in US dollars unless otherwi

  27. Slide 27: Balance Sheet & Liquidity

    BALANCE SHEET & LIQUIDITY1 Financial health of business continues to strengthen Net cash of $218M at quarter-end2 Available liquidity of more than $370M at end of Q3 Exited Q3 2021 with $222M of cash $150M revolving debt facility fully undrawn Debt free with less than $4M of lease obligations Amende

  28. Slide 28: Cash Flow Seasonality

    CASH FLOW SEASONALITY Cash flow tends to be weakest in H1 given timing of payments Final payments related to royalties, profit sharing (PTU), and taxes are subject to movements in the Mexican peso relative to the US dollar Cash flow from operations prior to changes in non-cash working capital impact

  29. Slide 29: Monorail-Based Mining System

    MONORAIL-BASED MINING SYSTEM Media Luna Feasibility Study to be advanced under a conventional mine design Mitigates risk to the business given Media Luna will be primary source of feed post mid-2024 Insufficient available upside at Media Luna as it relates to financial or schedule considerations Add

  30. Slide 30: Key Operational Metrics – El Limón Guajes (ELG)

    KEY OPERATIONAL METRICS – EL LIMÓN GUAJES (ELG)1,2 1) Q2 2020 results were impacted by a mandated suspension of operations by the Government of Mexico to mitigate the spread of COVID-19 in the country 2) For more information on operational and financial results, please refer to Torex Gold’s latest M

  31. Slide 31: Key Financial Metrics – Consolidated

    KEY FINANCIAL METRICS – CONSOLIDATED1,2,3 1) Q2 2020 results were impacted by a mandated suspension of operations by the Government of Mexico to mitigate the spread of COVID-19 in the country 2) All amounts in US dollars unless otherwise stated 3) For more information on operational and financial re

  32. Slide 32: Corporate Information and Top Shareholders

    CORPORATE INFORMATION AND TOP SHAREHOLDERS Broadly owned by skilled institutional investors Top 10 Shareholders2 Share Price Performance1 2.00 Institution Shares Shares (M) (%) 1.75 Blackrock 11.9 13.9% Price Performance - USD (Indexed to July 1, 2019) VanEck - ETFs 8.4 9.8% 1.50 RBC Asset Managemen

  33. Slide 33: Board of Directors

    BOARD OF DIRECTORS Ongoing Board refresh to maintain strong strategic and governance experience RICK HOWES PEng Chair of the Board ROSIE MOORE MSc (Geology) 40 years global technical, operational and management mining expertise; Exploration geologist whose 35+ year career includes experience in awar

  34. Slide 34: Management Team

    MANAGEMENT TEAM Proven experience navigating technical, commercial and social complexity JODY KUZENKO LLB President and Chief Executive Officer FAYSAL RODRIGUEZ V.P. Mexico Joined Torex in 2018 as COO; assumed CEO position in June 2020. 20+ years of mining experience in corporate & operational roles

  35. Slide 35: Mineral Reserves – El Limón Guajes (ELG)

    MINERAL RESERVES1 – EL LIMÓN GUAJES (ELG) As of December 31, 2020 Tonnes Au Ag Au Ag (Mt) (g/t) (g/t) (koz) (koz) Open Pit - El Limón (including El Limón Sur) Proven 2.48 3.59 4.3 286 344 Probable 5.84 2.90 4.2 545 787 Proven & Probable 8.32 3.11 4.2 831 1,130 Open Pit - Guajes Proven 1.88 3.87 3.4

  36. Slide 36: Mineral Resources – El Limón Guajes (ELG)

    MINERAL RESOURCES1 – El LIMÓN GUAJES (ELG) As of December 31, 2020 Tonnes Au Ag Au Ag (Mt) (g/t) (g/t) (koz) (koz) Open Pit - El Limón (including El Limón Sur) Measured 2.79 3.64 5.2 330 460 Indicated 9.03 2.66 5.7 770 1,650 Measured & Indicated 11.82 2.89 5.6 1,100 2,120 Inferred 1.68 1.73 7.4 90 4

  37. Slide 37: Notes to Mineral Reserves & Resources (ELG)

    NOTES TO MINERAL RESERVES & RESOURCES (ELG) Notes - El Limón Guajes Complex Reserve Statement Notes - El Limón Guajes Complex Resource Statement 1. Mineral reserves are founded on Guajes, El Limón and El Limón Sur measured 1. The effective date of the estimate is December 31, 2020. and indicated min

  38. Slide 38: Mineral Resources – Media Luna

    MINERAL RESOURCES – MEDIA LUNA Notes - Media Luna Resource Statement 1. The effective date of the estimate is April 30, 2021. 10. Mineral Resources are reported as undiluted; grades are contained grades. 2. Mineral Resources are reported above a 2.0 g/t gold equivalent (AuEq) cut-off 11. The estimat

  39. Slide 39: Media Luna – 2018 Preliminary Economic Assessment

    MEDIA LUNA – 2018 PRELIMINARY ECONOMIC ASSESSMENT1,2 1) Metal Prices used $1,200/oz Au, $17.00/oz Ag, $3.00/lb Cu, USD:MXN 1:18 2) A preliminary economic assessment should not be considered a prefeasibility study or feasibility study, as the economics and technical viability of the Media Luna Projec

  40. Slide 40: www.torexgold.com

    TSX | TXG www.torexgold.com Dan Rollins, CFA Vice President, Corporate Development and Investor Relations Email: dan.rollins@torexgold.com | Direct: 1-647-260-1503

Torex Gold Resources — Investor Presentation (November 2021) on 6ix