Slide 1: Motheo Copper Mine Site Tour Presentation
MATSA Mining Complex Scale and Life For personal use only Significant Producing Asset Adds >10Yrs Life Pro Forma Indicative Copper Equivalent Production (ktpa) (1,2,3,4,6) Cornerstone Asset with minimum mine life of ~12 years supported by Mineral Resources MATSA acquisition achieves Sandfire’s Susta
Slide 2: Important Information and Disclaimer
For personal use only Important Information and Disclaimer This presentation has been prepared by Sandfire Resources Ltd (Sandfire or the Company) and contains information about Sandfire Key assumptions current at the date of this presentation. The presentation is in summary form, has not been indep
Slide 3: Building a world-class copper mine
For personal use only Motheo Copper Mine Building a world-class copper mine Development of Sandfire’s Sandfire intends to fund the 5.2Mtpa Motheo Expansion Case DFS development of the Motheo Copper remains on schedule for completion in Motheo Copper Mine in the June 2022 Quarter: Botswana: Mine thro
Slide 4: Supporting our communities
For personal use only Motheo Supporting our communities Our Motheo community framework pillars Community Health Education Women Empowerment Youth Development Improved outcomes for Encourage attendance in Support equality, Promote training and the physical and mental schools, improve learning inclusi
Slide 5: Production Hub
For personal use only Motheo Production Hub New long-life operation • Initial production from T3 Open Pit, subsequently expanding with ore feed from A4 Deposit • Base Case 3.2Mtpa Motheo Processing Plant with rapid expansion to 5.2Mtpa capacity • Infrastructure – built to support 5.2Mtpa processing
Slide 6: Production Facility
Motheo Production Facility • Designed to be rapidly scalable to 5.2Mtpa with only the addition of a Ball Mill For personal use only Reagent Store Clinic Laboratory Administration Workshop Ball Mill Grinding Expansion Raw Water Primary Crushing Tails Pond Thickener Pebble Crushing Feed Conveyor Coars
Slide 7: Development Timeline
For personal use only Motheo Copper Mine | Development Timeline Mining License Approval & Land Titles Accommodation Village EMP Process Plant Engineering & Pre-Construction Works Accommodation Facility 132KV Powerline & Substations Design & Construction Process Plant Construction Mining Contractor M
Slide 8: Mine Construction & Development Capital
$ $ 80,000,000 320,000,000 For personal use only 23.6 Motheo Copper Mine 70,000,000 280,000,000 60,000,000 240,000,000 Mine Construction 50,000,000 200,000,000 & Development Capital 40,000,000 160,000,000 30,000,000 120,000,000 In US$ (Unaudited) 20,000,000 80,000,000 10,000,000 40,000,000 0 - Q3 FY
Slide 9: Key Progress: T3 Open Pit Mining
For personal use only Motheo Copper Mine Key Progress T3 Open Pit Mining • First pre-strip material was mined at the T3 Open Pit Deposit in late March, approximately one week ahead of schedule against the project execution plan Creating Value through Opportunity 9
Slide 10: Mining Equipment Assembly Yard
Motheo Copper Mine Key Progress For personal use only Mining Equipment Assembly Yard • First Hitachi EX1900 Excavator assembly nearing completion • Both Hitachi EX 2600 Excavators already in production • Tenth Cat 785 almost ready to go, nine in production • Two Cat 777 Water trucks assembly nearing
Slide 11: Mine Pit Overview
Motheo Copper Mine Key Progress For personal use only Mine Pit Overview Mine Pit Overview • Drill and Blast pattern in progress • View looking West over the Stage 1 pit area • First EX 2600 Excavator in operation • Vegetation and topsoil stripping of Stage 1 pit almost complete Creating Value throug
Slide 12: Construction Camp and Mine Village
Motheo Copper Mine Key Progress For personal use only Construction Camp and Offices Motheo Mine Village • Fully Operational • 380 rooms from 752 total, now available for use • 700 person capacity • Kitchen/Diner building commissioned during April and now operational Creating Value through Opportunit
Slide 13: Process Plant and Diesel Farm Area
Motheo Copper Mine Key Progress For personal use only Process Plant and Mining Offices Overview Diesel Farm Area • Administration Office and Clinic on schedule for completion • 800,000 litre fuel farm (far right) in progress in early June • Mine area washdown facility foundations in foreground • Min
Slide 14: Primary Crusher and Concentrate Loadout Facility
Motheo Copper Mine Key Progress For personal use only Primary Crusher Retaining Walls Concentrate Loadout Facility Primary Crusher • Lower steel installed • Concentrate shed bunker wall foundations • Rebar installation continues on crusher underway • Precast concrete panels ready for • Retaining wal
Slide 15: Power Distribution and Tailing Storage Facility
Motheo Copper Mine Key Progress For personal use only 11 kV Power Distribution Tailing Storage Facility (Stage 1) • Powerlines well advanced • Clearing and topsoil removal well advanced • Line to be energised early May • Keyway for embankment in progress Creating Value through Opportunity 15
Slide 16: Surface Water Management
Motheo Copper Mine Key Progress For personal use only Surface Water Management Construction • Sediment Pond 1 partially excavated • Diversion trench under construction Creating Value through Opportunity 16
Slide 17: Exploration: Dominant position in an emerging belt
For personal use only Motheo Exploration Dominant position in an emerging belt Near-mine and regional drilling underway Two drill rigs active around Motheo targeting high-grade mineralisation at T3 and the A1 Dome • Five drill rigs testing high-priority regional targets • Nickel sulphide exploration
Slide 18: Motheo Exploration
For personal use only T1/T2 Zone Motheo Exploration Diamond drilling, target Zone 5 type sheared NPF contact Cu Expansion targets deposits A4 West • Vein-hosted mineralisation within the A4 Diamond drilling, target Mineral Resource has delivered some A4 Dome high grade vein hosted Diamond drilling,
Slide 19: Key Takeaways
For personal use only Key Takeaways Thriving Communities New Production Hub Committed to delivering a lasting, Construction of the Motheo Copper Mine positive contribution to the on schedule and on budget communities where we operate 5.2Mtpa Motheo Expansion Case DFS remains on scheduled for complet
Slide 20: Contact Details
For personal use only Contact Details +61 8 6430 3800 +61 8 6430 3849 www.sandfire.com.au Corporate Head Office Level 2, 10 Kings Park Road West Perth WA 6005 Australia PO Box 1495 West Perth WA 6872 Australia