Eversource Energy (d/b/a) · NYSE:ES

Eversource Energy (d/b/a) — Eversource Energy — Technical Presentation (August 2024)

44 slides from Eversource Energy (d/b/a)'s technical presentation, Aug 21, 2024

  1. Slide 1: Distributed Energy Resources Interconnection Seminar: Expedited Process

    Distributed Energy Resources Interconnection Seminar Expedited Process Thank you for joining us. The presentation will begin at 9:00am. Please mute your phones to avoid any feedback. Thank you. August 21, 2024 1 Safety First and Always

  2. Slide 2: Co-Hosts

    Co-Hosts Mass ACA 2 Safety First and Always

  3. Slide 3: Safety

    Safety Regard ALL wires as live. Overhead power lines are Live Wires not insulated and carry enough energy to cause serious injury or even death. Safety is the most important thing to consider in designing, Keep yourself, your co-workers, tools, ladders and Keep Away vehicles at least 10 feet away f

  4. Slide 4: Interconnection Contacts

    Interconnection Contacts Eversource Energy – Western MA DG Simplified Projects •Matthew Secovich, Renata Gamache, & Christina King •Project inquiries need to be submitted via the portal •General questions email: wmdg@eversource.com Expedited Projects •Matthew Secovich: matthew.secovich@eversource.co

  5. Slide 5: Eversource Energy Seminars

    Eversource Energy Seminars February 8 EMA Simplified March 20 WMA Expedited / Standard May 8 EMA Expedited / Standard June 12 WMA Simplified August 21 WMA Expedited / Standard September 18 EMA Simplified November 20 WMA Simplified December 11 EMA Expedited / Standard 5 Safety First and Always

  6. Slide 6: Power Clerk DG Application

    Power Clerk DG Application https://www.eversource.com/content/wma/about/about-us/doing-business-with-us/builders- contractors/interconnections/massachusetts/application-to-interconnect 6 Safety First and Always

  7. Slide 7: Continuation Of Power Clerk DG Application

    Continuation Of Power Clerk DG Application 7 Safety First and Always

  8. Slide 8: Expedited Requirements: One Line and Battery Storage Sheet

    Expedited Requirements One Line Required to be stamped by a MA Electrical PE. Well documented electric service Point of Common Coupling with Interconnecting Device Size of main breaker External disconnect switch Generator breaker & size Generator connection point kW rating matches application (name

  9. Slide 9: Expedited Requirements: Site Plan and Cut Sheet

    Expedited Requirements Site Plan Must show property/lot lines, street names Interconnecting Pole Numbers Must show revenue meter location and location of inverter(s) and/or generators Must show production meter if Net Metered Does not need to be PE Stamped Must be a plan form view i.e. vertical NOT

  10. Slide 10: Expedited Standard Process

    Expedited Standard Process (single phase >15kw and three phase >25kw)-All Technologies INITIATION ENGINEERING IMPACT NO IMPACT DETAILED CONSTRUCTION FINAL PHASE REVIEW STUDY STUDY ENGINEERING PHASE PHASE 250kW and Depending on Impact Study A determination is Scheduled to begin ES construction Test g

  11. Slide 11: Questions?

    Questions? 11 Safety First and Always

  12. Slide 12: WMA Expedited DG Interconnection Studies

    WMA Expedited DG Interconnection Studies August 21, 2024 Spencer Hutchins Associate Engineer 12 Safety First and Always COMPANY CONFIDENTIAL

  13. Slide 13: Overview

    Overview DER applications in WMA continue to increase and bring more saturation to existing stations. Eversource continues to work closely with ISO-NE on DER projects to assess and verify the correct path forward for each project. Eversource substations are now seeing approximately 300MW of DER conn

  14. Slide 14: Process Overview

    Process Overview Developers can self-screen projects for likely anticipated path of study. Final determination can vary from below in some circumstances; important to review all points of the document. If your project is between 1MW & 5MW AND the interconnecting substation generation total is below

  15. Slide 15: Hosting Capacity Maps

    Hosting Capacity Maps Hosting Capacity Maps publicly available – provides insight into level of saturation and queued generation pending. Maps are general guides and subject to change. https://www.eversource.com/content/ema-c/about/about-us/doing-business-with-us/builders- contractors/interconnectio

  16. Slide 16: DER Projects & Market Participation

    DER Projects & Market Participation Reminder: – On August 28th, 2022, FERC approved ISO-NE’s proposal to have all distribution connected projects follow the state interconnection process regardless of if the project is interconnecting on a market facing feeder. – DER projects that receive PPA approv

  17. Slide 17: Overview of Studies

    Overview of T Studies Level 0 Studies – At a minimum, generally consist of a transfer limit analysis to ensure no degradation of ISO-NE Interface Limits. If adverse impacts found, a Level 3 study will be required. – Some Level 0 projects may require more detailed analysis while others may require le

  18. Slide 18: Technical Data Required - Level 3 ASO

    Technical Data Required - Level 3 ASO Conductor types and distance Project inverter modeling information (>=5MW) – Between Project and inverters/GSUs – Datasheet and manual – Project’s tie line to the point of interconnection – Reactive capability curve and/or data tables (POI) necessary to create t

  19. Slide 19: Timing and Communication

    Timing and Communication Within 20 days of application deemed complete: Eversource will conduct the ASO Impact Screen. Within 5 days, developer will be provided a Standard Process Initial Review Report – Identifying Results of the Impact Screen. If potential for adverse impact is found: Eversource w

  20. Slide 20: Summary of Resources Available

    Summary of Resource Available Mass Distributed Generation, Interconnections & Net Metering https://www.eversource.com/content/ema-c/about/about-us/doing-business-with-us/builders-contractors/interconnections/massachusetts ASO Impact Screening Flow Diagram https://www.eversource.com/content/docs/defa

  21. Slide 21: Questions?

    Questions? 21 Safety First and Always

  22. Slide 22: Solar MA Renewable Target Program (SMART)

    Solar MA Renewable Target Program (SMART) Program Information 22 Safety First and Always

  23. Slide 23: Ask Questions and Get Clarification

    Ask Questions and Get Clarification Coming Soon - FAQ page, which will appear at this link: https://www.eversource.com/content/residential/save- money-energy/clean-energy-options/solar-energy/net-metering-defined/renewable-credits-portal CLEAResult (SMART Program Administrator) – MA.SMART@CLEAResult

  24. Slide 24: Questions?

    Questions? 24 Safety First and Always

  25. Slide 25: MA SMART Program Metering Review

    MA SMART Program Metering Review Manager, Meter Services - Chris Kellogg Supervisors, Meter & Service Andrew Netherwood 25 Safety First and Always

  26. Slide 26: MA SMART Program Topics

    MA SMART Program Topics Meter Socket wiring Emergency disconnect position Information on meter socket use IT (instrumented transformer) Rates Services What the contractor provides What Eversource provides Labeling 26 Safety First and Always

  27. Slide 27: Meter Wiring

    Meter Wiring Solar and Production Socket Meter Wiring Only Scenario – Behind the Meter (BTM) Solar Description: typical solar meter wiring configuration for residential and small commercial customers. Solar Prod Meter (Utility PV Generation Meter) < 60KW = Scalar meter (Monthly consumption) > 60KW =

  28. Slide 28: Meter Wiring

    Meter Wiring Solar Meter Wiring Only Scenario – Behind the Meter (BTM) Solar Description: typical solar meter wiring configuration for residential and small commercial customers. Solar Prod Meter (Utility PV Generation Meter) < 60KW = Scalar meter (Monthly consumption) > 60KW = Interval Recording me

  29. Slide 29: Meter Wiring

    Meter Wiring Solar with Battery and Production Socket Meter Wiring Only Scenario – Behind the Meter (BTM) Solar and Battery Description: typical solar and battery meter wiring configuration for residential and small commercial customers. Solar Prod Meter (Utility PV Generation Meter) < 60KW = Scalar

  30. Slide 30: Meter Wiring

    Meter Wiring Solar Production Socket and Battery Meter Wiring Only Scenario – Behind the Meter (BTM) Solar and Battery Description: typical solar meter wiring configuration for residential and small commercial customers. Solar Prod Meter (Utility PV Generation Meter) < 60KW = Scalar meter (Monthly c

  31. Slide 31: Meter Wiring

    Meter Wiring Solar and Battery Meter Wiring Only Scenario – Behind the Meter (BTM) Solar and Battery Description: typical solar and battery meter wiring configuration for residential and small commercial customers. Solar Prod Meter (Utility PV Generation Meter) < 60KW = Scalar meter (Monthly consump

  32. Slide 32: Meter Wiring

    Meter Wiring Scenario – Standalone Meter at Existing Service location Description: typical meter wiring configuration for residential and small commercial customers where the solar is installed at an existing location, but not behind the meter. Solar Prod Meter (Utility PV Generation Meter) < 60KW =

  33. Slide 33: Meter Wiring: WHY??

    Meter Wiring Scenario – Standalone Meter at Existing Service location Description: typical meter wiring configuration for residential and small commercial customers where the solar is installed at an existing location, but not behind the meter. WHY ?? From From Utility Utility Same Service 120/240v

  34. Slide 34: Production Socket Wiring

    Production Socket Wiring Utility PV Generation and the Utility Storage meters must be wired with Utility feed to the top of the Meter socket; Solar panels and Battery storage to the bottom of the meter socket From Utility L1 L2 Source Side N Disconnect Production Socket This 5th jaw is required for

  35. Slide 35: Meter Socket and Disconnect Labeling

    Meter Socket and Disconnect Labeling The Revenue Meter Socket needs to be labeled as Revenue Meter with the address (Number, Street name & Unit number) that has the solar system. The Production Meter Socket needs to be labeled Production meter with the address (Number, Street name & Unit number) tha

  36. Slide 36: Information about metering socket use

    Information about metering socket use Consult the WMA I&R book for approved meter sockets. Link to WMA I&R book: https://www.eversource.com/content/docs/default-source/wma---pdfs/info-requirements- wma.pdf Using a meter socket listed in the I&R book will AVOID DELAYS All Stand-alone scenarios are co

  37. Slide 37: Instrument Transformer (IT) Rated Services

    Instrument Transformer (IT) Rated Services What does the Installation Contractor Provide? Provide all diagrams and Diagrams – 1-line and 3-line diagrams equipment spec sheets to Eversource for review. Approved IT cabinet Approved Meter Socket w/Test Switch Emergency disconnect All service voltages a

  38. Slide 38: IT Rated Services: What type of equipment do I use?

    IT Rated Services: What type of equipment do I use? Consult the WMA I&R book for approved meter sockets AND IT rated transformer enclosures. All IT metering must be Cold Sequenced. Label Label Label. Clearly mark the Emergency Breaker, all IT cabinets and Meter sockets. The more we know when we go o

  39. Slide 39: Questions?

    Questions? 39 Safety First and Always

  40. Slide 40: Western Massachusetts Expedited Interconnection Seminar

    Western Massachusetts Expedited Interconnection Seminar Wednesday August 21, 2024 Tim Callahan Lead Engineer – Protection and Control 40 Safety First and Always

  41. Slide 41: Information and Technical Requirements for Interconnection of DER

    Information and Technical Requirements for the Interconnection of Distribution Energy Resources (DER) 41 Safety First and Always

  42. Slide 42: Effective Grounding

    Effective Grounding If effective grounding is required, the customer’s site must meet the effective grounding requirement of X0/X1 at the PCC between 2 and 3 when disconnected from the Eversource system. Eversource will review a customer’s site effective grounding by modeling the site in ASPEN and e

  43. Slide 43: P&C Common Comments on SLD

    P&C Common Comments on SLD One-line diagrams must have the IEEE1547 protective settings, and the Ride-Thru capability of the inverter included. See Tables I-IV from ISO New England outlining the IEEE1547 standard. The voltage pickup values need to be listed in volts (primary and/or secondary) in add

  44. Slide 44: Any Questions?

    Any Questions? 44 Safety First and Always