National Fuel Gas Company · NYSE:NFG

National Fuel Gas — Investor Day (November 2013)

164 slides from National Fuel Gas's investor day presentation, Nov 19, 2013

  1. Slide 1: Analyst Day Presentation November 19, 2013

    Analyst Day Presentation November 19, 2013 Exhibit 99 National Fuel Gas Company

  2. Slide 2: Safe Harbor For Forward Looking Statements

    National Fuel Gas Company Safe Harbor For Forward Looking Statements This presentation may contain “forward-looking statements” as defined by the Private Securities Litigation Reform Act of 1995, including statements regarding future prospects, plans, performance and capital structure, anticipated c

  3. Slide 3: Analyst Day – Schedule of Speakers

    Presenter Topic National Fuel Gas Company Analyst Day – Schedule of Speakers Ron Tanski President and Chief Executive Officer Corporate Overview Matt Cabell President of Seneca Resources Corporation Exploration & Production Overview John McGinnis Senior VP of Seneca Resources Corporation Appraisal &

  4. Slide 4: ayeiodi05

    ayeiodi05 €10z saquiaaon - heq ys4qeuy

  5. Slide 5: Exceptional Assets, Focused on Execution

    1.549 Tcfe of Proved Reserves 800,000 Net Acres in Pennsylvania 2.8 MMBbl of Crude Oil Production $191 Million of Midstream EBITDA National Fuel Gas Company Exceptional Assets, Focused on Execution

  6. Slide 6: A History of Success & A Future of Opportunity: Recent Success

    35% Production CAGR Since 2010 Nearly $600 Million Invested in New Pipeline Infrastructure De-risked 2,000 Well Locations in the Marcellus National Fuel Gas Company A History of Success & A Future of Opportunity Recent Success

  7. Slide 7: Corporate Overview

    Corporate Overview Integrated Businesses Provide Complimentary Benefits

  8. Slide 8: Consistent Growth in Low Natural Gas Price Environment

    Fiscal Year Natural Gas (1) ($/MMBtu) Corporate Overview Consistent Growth in Low Natural Gas Price Environment $4.68 $4.49 $4.10 $2.83 $3.60 Natural gas prices dropped 23% from 2009 to 2013

  9. Slide 9: DG EG

    DG EG ealy Juawidojaacq ealy Juawidojaacq weyseq usa1s8M ayeiodi05 €10z saquaaon - feq ys4jeuy

  10. Slide 10: Formula to Grow Our Marcellus Development Program

    High-Quality Reservoir Realized Natural Gas Price Operating Efficiencies Corporate Overview Formula to Grow Our Marcellus Development Program ? Increased Capital Deployment

  11. Slide 11: Opportunities to Move Gas Out of the Northeast

    Corporate Overview Opportunities to Move Gas Out of the Northeast The oversupply of natural gas in the Northeast is creating opportunities for the midstream businesses to develop projects to deliver to higher-priced markets such as Eastern Canada and the Southeast

  12. Slide 12: Marcellus Infrastructure Growth Still Has Room to Run

    2010 to 2013 Expansions 2014+ Expansions Corporate Overview Marcellus Infrastructure Growth Still Has Room to Run Capacity Added 1,819 MDth per day Capital Deployed $422 million Capacity Planned 1,724 to 2,224 MDth per day Capital Expenditures Planned ~$1.5 billion Plans are in place to deploy signi

  13. Slide 13: A History of Success & A Future of Opportunity: Future Goals

    10-15% Adjusted EBITDA Growth 15-25% Production Growth $1.5 Billion of Midstream Investment Over 5 Years National Fuel Gas Company A History of Success & A Future of Opportunity Future Goals

  14. Slide 14: Maintaining Our View on Corporate Structure

    Today Future (2015+) Strong Balance Sheet Ability to modestly increase leverage 1.89x Debt/Adjusted EBITDA Balanced Business Mix 58% E&P (1) 42% Midstream/Utility (1) Operational synergies Investment Grade Credit Diversification of businesses provide credit support Leverage is the cheapest cost of c

  15. Slide 15: Exploration & Production Overview

    Exploration & Production Overview

  16. Slide 16: Seneca’s Evolution

    Seneca Resources Seneca’s Evolution

  17. Slide 17: Fiscal 2013 Highlights

    351% WDA Success Total production increased 45% to 120.7 Bcfe Seneca Resources Fiscal 2013 Highlights Replaced 351% of proved reserves Finding & Development Cost: $1.31/Mcfe Marcellus Finding & Development Cost: $0.99/Mcfe Achieved major breakthrough in the Marcellus Shale Western Development Area (

  18. Slide 18: Disciplined Capital Spending

    Seneca Resources Disciplined Capital Spending

  19. Slide 19: Proven Record of Growth

    Fiscal Years 3-Year F&D Cost (1) ($/Mcfe) Seneca Resources Proven Record of Growth 2006-2008 $7.63 2007-2009 $5.35 2008-2010 $2.37 2009-2011 $2.09 2010-2012 $1.87 2011-2013 $1.67 2013 F&D Cost = $1.31 Marcellus F&D: $0.99 Doubled Proved Reserves Since 2010 71% Proved Developed

  20. Slide 20: Best-In-Class Marcellus Shale Reserve Growth

    Seneca Resources Best-In-Class Marcellus Shale Reserve Growth

  21. Slide 21: Delivering Tremendous Production Growth

    Seneca Resources Delivering Tremendous Production Growth

  22. Slide 22: Delivering More than Just Absolute Growth

    Seneca Resources Delivering More than Just Absolute Growth

  23. Slide 23: Significant Position & Integral Part of Seneca’s Future

    Company Net Marcellus Acreage (1) Enterprise Value (2) ($ Billions) Acres per $ Million of EV Marcellus Shale Significant Position & Integral Part of Seneca’s Future NFG 780,000 $7.4 105.4 RRC 835,000 $15.5 53.9 EQT 560,000 $15.5 36.1 SWN 337,000 $14.6 23.0 AR 334,000 $17.2 19.4 COG 200,000 $15.2 13

  24. Slide 24: Marcellus Shale: Factors for Success

    Marcellus Shale Factors for Success Acreage Position – Quantity & Quality Operating Expertise Control costs Maximize production Gathering, Transportation and Marketing Financial Stability Ability to withstand price swings and market dislocations

  25. Slide 25: Prolific Pennsylvania Acreage

    Marcellus Shale Prolific Pennsylvania Acreage

  26. Slide 26: Understanding Seneca’s 780,000 Net Acres

    Northeast Core ~30,000 acres in NE Core Tier I Acres ~200,000 acres Economic less than $4/Mcf Awaiting Evaluation ~250,000 acres Requires Gas Price Above $4/Mcf ~300,000 acres Seneca Acreage Huge Position – Varies in Understanding Understanding Seneca’s 780,000 Net Acres

  27. Slide 27: Fee Ownership & Contiguity are Beneficial

    No Royalty No Lease Expiration Contiguous Acreage Blocks Seneca’s Tier I acreage is approaching Northeast Core economics Seneca Acreage Fee Ownership & Contiguity are Beneficial

  28. Slide 28: Seneca’s Marcellus Acreage Provides a Unique Advantage

    Seneca Acreage Seneca’s Marcellus Acreage Provides a Unique Advantage Seneca Advantage #1 Fee Ownership Position 28% IRR Competitor Advantage #1 Advantage #2 Seneca Advantage Capital Expenditures $9,000 $9,000 $7,000 $7,000 Multiple Pads No No Yes Yes Working Interest 100% 100% 100% 100% Revenue Int

  29. Slide 29: Best-In-Class Operator in Lycoming County (EDA)

    Seneca’s Operations Best-In-Class Operator in Lycoming County (EDA)

  30. Slide 30: Top-Notch Lycoming Economics

    Seneca’s Operations Top-Notch Lycoming Economics

  31. Slide 31: Seneca’s Lycoming Economics are in the Top 3

    Seneca’s Operations Seneca’s Lycoming Economics are in the Top 3

  32. Slide 32: Driving Down Well Costs

    Seneca’s Operations Driving Down Well Costs In 2014, total well costs are expected to be ~35-40% lower than 2012

  33. Slide 33: Seneca’s Overall Marketing Strategy

    Develop gathering infrastructure with NFG Midstream Firm sales at interstate pipeline interconnects Firm transport (FT) to major markets Firm sales tied to FT contracts Financial hedges to lock in benchmark and basis risk Financial hedges to lock in benchmark and basis risk Seneca’s Gathering & Mark

  34. Slide 34: Ability to Withstand Pricing Challenges

    National Fuel’s Financial Stability Ability to Withstand Pricing Challenges

  35. Slide 35: Marcellus Shale: Factors for Success

    Marcellus Shale Factors for Success Acreage Position – Quantity & Quality Operating Expertise Control costs Maximize production Gathering, Transportation and Marketing Financial Stability Ability to withstand price swings and market dislocations

  36. Slide 36: California: Outstanding Cash Flow

    California Outstanding Cash Flow (1)

  37. Slide 37: Looking Back at the Successful Ivanhoe Acquisition

    California Looking Back at the Successful Ivanhoe Acquisition

  38. Slide 38: California: Looking Forward

    California Looking Forward 1. Manage decline of base production 2. Pursue and develop opportunities for growth from current assets Sespe East Coalinga South Midway Sunset 3. Continue to pursue additional acquisition and farm-in opportunities

  39. Slide 39: Seneca Resources Key Metrics

    Operational Strategy Metric Fiscal 2009 Strategic Improvements Fiscal 2013 Focus on growth- oriented Marcellus Shale assets with significant fee acreage Maintain and grow strong cash flow assets in California 12x Production Growth 7x Reserve Growth 5x EBITDA Growth 49% Decrease per Mcfe 25% EBITDA G

  40. Slide 40: What Will Seneca Look Like Moving Forward?

    Consistent Production Growth: 15-25% CAGR Driven by a very large, high-quality Appalachian acreage position Maintain Oil Production Expand When Possible Excellent operator and significant cash flow generation Disciplined Spending Driven by Rates of Return Pace of development adapts to changing marke

  41. Slide 41: Appraisal & Development Overview

    Appraisal & Development Overview

  42. Slide 42: d National Fuer

    d National Fuer Upstream Chautauqua Cattaraugus Tegany Chemung Bradt sulliy Mercer ‘Snyder Allegheny Cambria a Juniata 3 3 Rg g a E d . 8 Zz > ge a d

  43. Slide 43: ‘Dlearfielé

    ‘Dlearfielé

  44. Slide 44: ‘Dlearfielé

    ‘Dlearfielé

  45. Slide 45: WDA Is the Key to Seneca’s Long-Term Growth Outlook

    Full Development Since 2010 ~225 locations remaining 70-90 wells in Lycoming County Near-term driver of growth Full Development Started in 2013 1,700 to 2,000 locations de-risked Long-term driver of growth Marcellus Shale WDA Is the Key to Seneca’s Long-Term Growth Outlook Seneca Lease Seneca Fee 72

  46. Slide 46: Significantly Improved Understanding of the WDA

    James City Church Run Owl’s Nest Mt. Jewett W. Branch Clermont St. Mary’s Kyler’s Corner Boone Mtn Sulger Farm Tionesta Beechwood Red Hill/ Leasgang Punxy Rich Valley Ridgway Key Statistics Vertical Wells: 30 Full Core: 8 Sidewall Core: 2 3D Seismic: 432 sq m Marcellus Shale Significantly Improved U

  47. Slide 47: Northwest PA Generalized Cross-Section

    TOC Marcellus Shale Northwest PA Generalized Cross-Section Transitional Outer Shelf CaCO Sed. Rate Platform Basin Rich Valley Clermont Beechwood Owl’s Nest James City Leasgang Punxy Ridgway High variability, very poor rock quality in areas High organics, great rock quality, less variability Medium r

  48. Slide 48: WDA Log Summary Cross-Section

    Marcellus Shale WDA Log Summary Cross-Section TOC/PHI/BWV 0 Wt% 50 0.2 v/v 0 0.2 v/v 0 Mineralogy Volume % Gas Resource 0 Mcf/ac-ft 1500 0 Bcf/mi 100 = 6.8 - 8.1% Total GIP = ~70/sect = 5.6 - 6.7% Total GIP = ~75/sect TOC/PHI/BWV 0 Wt% 50 0.2 v/v 0 0.2 v/v 0 Mineralogy Volume % Gas Resource 0 Mcf/ac

  49. Slide 49: 2013 & 2014 WDA Delineation Program

    SRC Lease Acreage SRC Fee Acreage EOG Earned JV Acreage Marcellus Shale 2013 & 2014 WDA Delineation Program Owl’s Nest – Delineating 2 High Btu Wells Completed Rich Valley – Full Development 2 Wells Completed 7-Day IP of 7.8 MMcf/d & EUR of 7.4 Bcf Well 7-Day IP: 4.5 MMcf/d Tionesta – Delineating 1

  50. Slide 50: Rich Valley/Clermont is in Full Development Mode

    Rich Valley 2 Well 7-day IP: 4.5 MMcf/d Lateral Length: 4,492’ 200-250 Horizontal Locations Pad N: Spacing Test JV Wells Pad H Pad D Pad E Pad O Clermont RCS: 9H 7-day IP: 10.0 MMcf/d (EUR: 8.6 Bcf) Non-RCS: 10H 7-day IP: 7.4 MMcf/d Rich Valley 7-day IP: 7.8 MMcf/d EUR: 7.4 BCF Lateral Length: 6,372

  51. Slide 51: Clermont Wells Improved from Early Non-Op JV Wells

    Marcellus Shale Clermont Wells Improved from Early Non-Op JV Wells Clermont 5H & 6H (Non-op wells) Avg. lateral length: 3,344’ Small casing: 4.5” Restricted pump rates Wide stage spacing: 350’ No soaking, low Sw’s Clermont 9H & 10H (Seneca wells) Avg. lateral length: >5,500’ Large casing: 5.5” Incre

  52. Slide 52: Moving All Completions to Reduced Cluster Spacing (RCS)

    Marcellus Shale Moving All Completions to Reduced Cluster Spacing (RCS) RCS Design Conventional Design Twice the number of stages/perforations Increases stimulated reservoir volume Increased proppant near the wellbore improves fracture conductivity

  53. Slide 53: Consistently Improved Results in the Owl’s Nest Area

    Marcellus Shale Consistently Improved Results in the Owl’s Nest Area 2013 Appraisal Program Lateral length >4,400’ to 6,200’ RCS completions 150’ spacing Soaked wells 30 – 60 days Target interval Union Springs: 100% in target

  54. Slide 54: Strong Wells Across WDA Acreage

    Well Name Completion Design Treatable Lateral Length Stages Peak 24-Hour Rate (MMcfd) Peak 7-Day Rate (MMcfd) EUR (Bcf) Status Marcellus Shale Strong Wells Across WDA Acreage Rich Valley 27H RCS 6,372’ 8.1 7.8 7.4 Producing Clermont 9H RCS 5,500’ 11.4 10.0 8.6 Producing Clermont 10H Non-RCS 5,565’ 8

  55. Slide 55: Key Areas of Improvement in Recent Delineation Program

    Areas of Improvement 2012-2013 Delineation Program Marcellus Shale Key Areas of Improvement in Recent Delineation Program Target Selection (Landing Depth) Identification of specific target interval is key Target Execution Percent of wellbore in target interval increased from prior years Completion D

  56. Slide 56: Selection of Target Interval is Critical

    Previous programs spent a significant portion ( > 60% ) of the wellbore outside of the current target interval, identified to have improved productivity Marcellus Shale Selection of Target Interval is Critical

  57. Slide 57: Optimized Landing Depth

    Marcellus Shale Optimized Landing Depth EDA Lycoming Type Log ROP (ft/hr) ROP vs Height Above Onondaga Improved Target Zone Drivers Best rock quality in terms of organic content, brittleness, and porosity Highest rate of penetration (ROP)

  58. Slide 58: Continued Improvement Staying within Targeted Interval

    Marcellus Shale Continued Improvement Staying within Targeted Interval Reasons for Improvement 3D seismic acquisition Improved communication between Geology, Drilling and Completion teams Geosteering technology (azimuthal GR)

  59. Slide 59: RCS & Increased Sand Volume Generating Better Results

    Reducing stage length, increasing the number of stages, and increasing proppant volume have been integral in improving well productivity Marcellus Shale RCS & Increased Sand Volume Generating Better Results Improved near wellbore fracture conductivity Increases near wellbore fracturing & stimulated

  60. Slide 60: Longer Laterals Drive Improved Economics

    Lateral lengths have increased even as target selection and execution have improved Marcellus Shale Longer Laterals Drive Improved Economics

  61. Slide 61: 2013 Appraisal Program was a Success

    P10 P50 P90 Mean StDev Marcellus Shale 2013 Appraisal Program was a Success 50-hr Flowback Rate (Mcf/d/1000') FY13 Program 1,427 1,128 1,147 Previous Programs 1,002 Avg Rate. Peak 50 ht/1000’

  62. Slide 62: 200,000 Acres With 6-8 Bcfe EUR Wells

    Marcellus Shale 200,000 Acres With 6-8 Bcfe EUR Wells

  63. Slide 63: 1,700 To 2,000 Economic WDA Locations Below $4/Mcfe

    Prospect County Product Approx. Remaining Locations EUR (Bcfe) BTU IRR (1) @ $4/MMBtu 15% IRR (1) Breakeven Price ($/Mcf) Marcellus Shale 1,700 To 2,000 Economic WDA Locations Below $4/Mcfe Tract 100 Lycoming Dry Gas 11.5 1,030 90% $2.20 Gamble Lycoming Dry Gas 10-11 1,030 77% $2.33 Tract 595 Tioga

  64. Slide 64: Intercompany Gathering Ensures Timely Gas Sales

    Develop gathering infrastructure with NFG Midstream Firm transport (FT) to major markets Firm sales tied to FT contracts Financial hedges to lock in benchmark and basis risk Financial hedges to lock in benchmark and basis risk Firm sales at interstate pipeline interconnects Marcellus Shale Marketing

  65. Slide 65: R Z E g a > z fa] E d National Fuel NATIONAL FUEL

    3 5 R Z E g 3 8 a > z fa] 5 E d National Fuel NATIONAL FUEL GAS SUPPLY CORPORATION EMPIRE PIPELINE GATHERING PIPE INES MAJOR TRANSMISSION PIPELINES ‘SENECA RESOURCES ACREAGE

  66. Slide 66: TGP Production & Firm Sales Aligned Thru 2014

    Marcellus Shale Marketing TGP 300 Production & Firm Sales Aligned Thru 2014

  67. Slide 67: Targeting Future Firm Sales on Transco

    Marcellus Shale Marketing Targeting Future Firm Sales on Transco

  68. Slide 68: d National Fuel

    d National Fuel + ries gq verona Cail xe choi: Snyder . eA 2 4 a Rg g E 3 So , 3 F ses : Somerset futon Frankin es nico — 3 a 2 clan : (saany scion

  69. Slide 69: Mississippian Lime: Commencing Evaluation Program in Fiscal 2014

    Mississippian Lime Commencing Evaluation Program in Fiscal 2014 The initial entry into the Mississippian Lime play furthers the Company’s goal of maintaining a significant contribution from oil-producing properties Unit 30-day IP: 352 BOED (92% Oil/NGLs) Total Net Acres: 13,615 100% working interest

  70. Slide 70: €10z s2quaaon - heq yshjeUy

    €10z s2quaaon - heq yshjeUy

  71. Slide 71: Stable Production Fields; Modest Growth Potential

    East Coalinga Temblor Formation Primary North Lost Hills Tulare & Etchegoin Formation Primary/Steamflood South Lost Hills Monterey Shale Primary North Midway Sunset Tulare & Potter Formation Steamflood South Midway Sunset Antelope Formation Steamflood Sespe Sespe Formation Primary Key Areas of Focus

  72. Slide 72: South Midway Sunset Has Delivered Significant Growth

    California South Midway Sunset Has Delivered Significant Growth Highlights Since Acquisition Increased daily production by 130% Drilled 80 new producers Added 3.3 MMBO of proven reserves Increased steam capacity by 280% Identified opportunities for additional pool development Extended Pool Boundary

  73. Slide 73: South MWSS Growth Opportunities Continue into 2014

    California South MWSS Growth Opportunities Continue into 2014

  74. Slide 74: Early Success in Farm-In with Chevron at East Coalinga

    California Early Success in Farm-In with Chevron at East Coalinga 1-Acre Test 48 BOPD 5-Acre Test 54 BOPD 2-Acre Test 18 BOPD 2000’ Returned to Production 1-acre (~30 locations) 2-acre (~40 locations) 5-acre (~120 locations) Downspacing Potential 2013 Evaluation Wells Seneca Lease Existing Wells Hig

  75. Slide 75: Ramping Up the Coalinga Drill Program in Fiscal 2014

    California Ramping Up the Coalinga Drill Program in Fiscal 2014 2014 Development Program (Tentative) Location Selection Criteria 2014 Locations (30) 2013 Locations (12) • 2013 new well production • Reservoir pressure mapping • Historical production • Past EOR attempts

  76. Slide 76: Ongoing Evaluation of Long-Term Sespe Potential

    TC 524-28 IP: 100 BOEPD 1 Oil 10/13 TC 525-28 IP: 160 BOEPD 1 Oil 10/13 WS 525-33 1 Oil in 11/13 WS 535-33 1 Oil in 11/13 Year Target # of Wells Average IP (BOEPD) st st st st California Ongoing Evaluation of Long-Term Sespe Potential “X” SANDS ISOCHORE (Thickness) Mile 2011 Wells (5) 2012 Wells (6)

  77. Slide 77: Evaluating the Monterey Shale at South Lost Hills

    California Evaluating the Monterey Shale at South Lost Hills

  78. Slide 78: Limited Growth Opportunities, But Strong Economics

    Field Average Well Cost Average EUR (MBO) Estimated IRR @$100/Bbl Fiscal 2014 Locations California Limited Growth Opportunities, But Strong Economics South Midway Sunset $250,000 75% East Coalinga $400,000 50% Sespe – 5 Acre Infill $2,800,000 25% Sespe - Coldwater $2,800,000 35%

  79. Slide 79: Modest Growth Anticipated in 2014 and 2015

    California Modest Growth Anticipated in 2014 and 2015

  80. Slide 80: Marcellus Operational & Environmental Overview

    Marcellus Operational & Environmental Overview

  81. Slide 81: Our Development Approach Drives Major Efficiencies

    Multi-Well Pads Focused Development Areas Faster Spud-to-Sales Timing Economies of Scale Reduces Costs Minimal Infrastructure Constraints & Well Backlog Technical & Operational Expertise Marcellus Shale Our Development Approach Drives Major Efficiencies

  82. Slide 82: EDA Delivering Significant Growth

    Covington – Fully Developed Gross Production: ~60 MMcf per Day 47 Wells Drilled and Producing Marcellus Shale EDA Delivering Significant Growth DCNR Tract 595 Gross Production: ~100 MMcf per Day 34 Wells Drilled (52 Total Locations) 26 Wells Producing DCNR Tract 100 Gross Production: ~220 MMcf per D

  83. Slide 83: EDA – Historical Well Results Are Exceptional

    Development Area Producing Well Count Average IP Rate (MMcf/d) Average 7-Day (MMcf/d) Average 30-Day (MMcf/d) Average EUR per Well (Bcf) Average Lateral Length EUR per 1,000’ of Lateral (Bcfe) Marcellus Shale EDA – Historical Well Results Are Exceptional Covington Tioga County 5.2 4.7 4.1 5.7 4,023’

  84. Slide 84: Faster Spud-to-Sales: Drilling Efficiencies

    Marcellus Shale Faster Spud-to-Sales: Drilling Efficiencies How has this been accomplished? Directional Plan Optimization Minimize drilling path corrections Bit Selection Increases drilling rate and durability Drill Top-hole Sections Deeper with Water More efficient and cost effective Optimize Landi

  85. Slide 85: Faster Spud-to-Sales: Multi-Well Pads Are Key

    Marcellus Shale Faster Spud-to-Sales: Multi-Well Pads Are Key Limiting the movement of rigs between pads allows for more drilling Using LEAN practices has eliminated four days from each rig move Staying in smaller regional areas further limits move time

  86. Slide 86: Drilling Efficiencies Allow for More Wells per Year

    Marcellus Shale Drilling Efficiencies Allow for More Wells per Year In spite of increasing the average lateral length, each rig is drilling more wells per year

  87. Slide 87: Faster Spud-to-Sales: Completing More Stages per Day

    Marcellus Shale Faster Spud-to-Sales: Completing More Stages per Day

  88. Slide 88: Faster Spud-to-Sales: The Overall Picture

    Marcellus Shale Faster Spud-to-Sales: The Overall Picture (1)

  89. Slide 89: Faster Spud-to-Sales: More Lateral Feet Completed Yearly

    Marcellus Shale Faster Spud-to-Sales: More Lateral Feet Completed Yearly

  90. Slide 90: Drilling Cost Reductions: Several Contributing Factors

    Marcellus Shale Drilling Cost Reductions: Several Contributing Factors Improvements From 2012 to 2013 ($525,000 per well) Shorter drilling days to TD: $300,000 Faster rig moves (2012: 8.5 Days 2013: 4.5 Days): $20,000 (6 - well pad) Procurement and supply chain initiatives: $120,000 Directional plan

  91. Slide 91: Completion Cost Reductions: Ongoing Optimization

    Marcellus Shale Completion Cost Reductions: Ongoing Optimization

  92. Slide 92: Completion Cost Reductions: New Efficient Technologies

    Marcellus Shale Completion Cost Reductions: New Efficient Technologies Toe Sub $60,000 savings per well Time Savings Time Savings Time Savings Sleeve $200,000 savings per well Dissolvable Balls $300,000 savings per well $3.4 million saved on a 6-well pad from the utilization of new technologies

  93. Slide 93: Completion Cost Reductions: Water Infrastructure

    Marcellus Shale Completion Cost Reductions: Water Infrastructure System Cost: $8.5 million 8 miles of pipeline 43 million gallons of storage Will serve at least 70 wells Provides 75% of water needs, with the remainder being recycled production fluid Environmental & Cost Benefits Eliminated the need

  94. Slide 94: Minimizing Backlogs: Coordinated Development

    Sales Lag (Months) 0 6 12 18 Marcellus Shale Minimizing Backlogs: Coordinated Development Coordination with NFG Midstream to construct gathering systems Development well backlog typically consists of wells on pads in either the drill or complete phase Regional development programs Focus on multi-wel

  95. Slide 95: Committed to Health, Safety, and the Environment

    “…creating a systematically integrated model of EHS stewardship beyond mere compliance.” Seneca Resources Committed to Health, Safety, and the Environment Seneca Resources Corporation – Value Statement “We ask that each employee share in our philosophy and unwavering commitment to each other’s healt

  96. Slide 96: Midstream Businesses Overview

    Midstream Businesses Overview

  97. Slide 97: National Fuel’s Midstream Businesses

    Midstream Businesses National Fuel’s Midstream Businesses Reporting Segments Subsidiaries

  98. Slide 98: Positioned Well to Serve Appalachian Producers

    National Fuel Gas Supply Corporation Midstream Businesses Positioned Well to Serve Appalachian Producers System Length ~ 2,550 Miles Storage Capacity 73.4 Bcf Contracted Transport 2.58 MMDth/d 2013 Revenue $191.2 Million 2010 – Capital Expenditures $304.6 Million

  99. Slide 99: Positioned Well to Serve Appalachian Producers

    Midstream Businesses Positioned Well to Serve Appalachian Producers

  100. Slide 100: Positioned Well to Serve Appalachian Producers

    Midstream Businesses Positioned Well to Serve Appalachian Producers

  101. Slide 101: Long-Term Strategy Driven by Both Seneca & 3rd Parties

    Midstream Businesses Long-Term Strategy Driven by Both Seneca & 3 rd Parties Develop strong partnerships with customers to help them reach diverse, high-value markets

  102. Slide 102: Positioned to Serve Seneca’s Rapidly Growing Production

    Midstream Businesses Positioned to Serve Seneca’s Rapidly Growing Production

  103. Slide 103: Gathering is the Crucial First Step to Reaching a Market

    Gathering Gathering is the Crucial First Step to Reaching a Market

  104. Slide 104: Existing Systems Supporting Seneca’s Near-Term Growth

    Gathering Existing Systems Supporting Seneca’s Near-Term Growth Covington Gathering System In-service date: November 2009 Capacity: 220,000 Dth per day Interconnect: TGP 300 Capital expenditures (to date): $28.3 million Capital expenditures (future): $7.5 million Trout Run Gathering System In-servic

  105. Slide 105: Developing a 1+ Bcf/d Gathering System in the WDA

    Gathering Developing a 1+ Bcf/d Gathering System in the WDA In-Service: August 2014 Initial Trunkline Capacity: 700 MMcf per day Interconnect TGP 300 Total Cost: $60-$92 Million Major Facilities 24” Pipeline – 6 Miles 8”-20” Pipeline – 25+ Miles Seneca Pads Producing 2 in Fiscal 2014 (15 Wells)

  106. Slide 106: Clermont Gathering System has Large Expandability

    Gathering Clermont Gathering System has Large Expandability In-Service: Ongoing build-out Ultimate Trunkline Capacity: 700 to 1,000 MMcf per day Interconnects TGP 300 and National Fuel Gas Supply Corporation (anticipated) Total Cost: $75 - $125 million Major Facilities Additional Gathering Clermont

  107. Slide 107: A Number of Options to Serve 3rd Party Producers

    Gathering A Number of Options to Serve 3 rd Party Producers

  108. Slide 108: 2014 Spending Driven by Seneca Development

    Gathering 2014 Spending Driven by Seneca Development $100 to $150 Million

  109. Slide 109: More than 1.5 Bcf per day of Gathering Capacity by 2015

    Gathering More than 1.5 Bcf per day of Gathering Capacity by 2015

  110. Slide 110: Capital Deployment Will Deliver Long-Term Growth

    Gathering Capital Deployment Will Deliver Long-Term Growth Revenue Growth (2013 to 2015): ~60% CAGR Capital Investment (2013 to 2015): ~60% CAGR

  111. Slide 111: Project Opportunities to Support WDA Growth

    Develop multiple outlets to high-value markets Pipeline & Storage Project Opportunities to Support WDA Growth

  112. Slide 112: Providing Transportation to Higher-Priced Markets

    Currently Short Supply Short Supply Midstream Businesses Providing Transportation to Higher-Priced Markets

  113. Slide 113: NE Supply Approaching NE Peak Demand

    Midstream Businesses NE Supply Approaching NE Peak Demand Forecasted Actual Peak Demand (24-25 Bcf per day) Median Demand (11.5 Bcf per day) Supply exceeds demand for 70% of the year by 2016

  114. Slide 114: Focusing on Projects to Non-Traditional Demand Markets

    The markets of Eastern Canada, the Mid-Atlantic and Southeast look to be the most desirable markets for shippers to reach over the long-term Midstream Businesses Focusing on Projects to Non-Traditional Demand Markets

  115. Slide 115: Delivering Into the Eastern Canadian Market is Valuable

    Pipeline & Storage Delivering Into the Eastern Canadian Market is Valuable

  116. Slide 116: Northeast PA Spot Markets are Heavily Discounted

    Pipeline & Storage Northeast PA Spot Markets are Heavily Discounted

  117. Slide 117: Major Expansion Designed for Canadian Deliveries

    Northern Access 2015 Pipeline & Storage Major Expansion Designed for Canadian Deliveries Northern Access 2015 Niagara (TCPL) Delivery Point In-Service: November 2015 System: NFG Supply Corp. Capacity: 140,000 Dth per day Interconnect Niagara (TransCanada) Total Cost: $67 Million Major Facilities 23,

  118. Slide 118: Clermont to Chippawa Provides Delivery Options

    Clermont to Chippawa Pipeline & Storage Clermont to Chippawa Provides Delivery Options Delivery Point Clermont to Chippawa Chippawa (TCPL) Hopewell (TGP 200) Corning (Millennium) In-Service: 2016 System: Supply & Empire Capacity 250,000+ Dth per day Interconnects Corning (Millennium) Hopewell (TGP 2

  119. Slide 119: Longer-Term: Reaching Markets Along the Atlantic

    Clermont to Transco Pipeline & Storage Longer-Term: Reaching Markets Along the Atlantic Transco In-Service: 2017 System: NFG Supply Corp. Capacity 300,000 to 500,000 Dth per day Interconnect Transco Leidy Line Total Cost: $100 to $150 Million To Mid-Atlantic & Southeast Clermont to Transco Delivery

  120. Slide 120: Expansions to Move Gas from the WDA are Significant

    Projects to Support WDA Growth Pipeline & Storage Expansions to Move Gas from the WDA are Significant Project Capacity (Dth/day) Northern Access 2015 140,000 Clermont to Chippawa 250,000+ Clermont to Transco 300,000-500,000 Total New Capacity 690,000-890,000+ Project Capital Cost Northern Access 201

  121. Slide 121: Seneca Currently Represents a Small Portion of Capacity

    Pipeline & Storage Seneca Currently Represents a Small Portion of Capacity Total Contracted Transportation Capacity (at 9/30/13): 3.6 MMDth per Day

  122. Slide 122: Recent 3rd Party Expansions Have Been Highly Successful

    Projects to Support 3 rd Parties Pipeline & Storage Recent 3 rd Party Expansions Have Been Highly Successful Project Capacity (Dth/day) Northern Access 2013 320,000 Tioga County Extension 350,000 Line N (2011, 2012 & 2013) 353,000 Total New Capacity 1,023,000 Project Capital Cost Northern Access 201

  123. Slide 123: NFGSC is Now a Net Exporter of Natural Gas to Canada

    Northern Access project was placed in-service November 2011 Pipeline & Storage NFGSC is Now a Net Exporter of Natural Gas to Canada

  124. Slide 124: National Fuel Becoming a Major SW PA Transporter

    Pipeline & Storage National Fuel Becoming a Major SW PA Transporter National Fuel Gas Supply Corp. went from no SW Pennsylvania receipts in 2008 to nearly 40% of all volumes today

  125. Slide 125: Additional Line N Expansions Planned for the Future

    Mercer Expansion Pipeline & Storage Additional Line N Expansions Planned for the Future In-Service: November 2014 System: NFG Supply Corp. Capacity: 105,000 Dth per day Precedent agreements signed for all available capacity Interconnect Mercer (TGP Station 219) Total Cost: $30 Million Expansion: $27

  126. Slide 126: Pairing Line N Expansions with System Modernization

    Westside Expansion & Modernization Mercer (TGP Station 219) Pipeline & Storage Pairing Line N Expansions with System Modernization In-Service: November 2015 System: NFG Supply Corp. Capacity: 175,000 Dth per day Precedent agreements signed for 145,000 Dth per day Interconnect Mercer (TGP Station 219

  127. Slide 127: Developing Unique Solutions for Shippers

    Tuscarora Lateral Pipeline & Storage Developing Unique Solutions for Shippers In-Service: November 2015 System: NFG Supply & Empire Pipeline New No-Notice Services Preserving 172,500 Dth per day (RG&E) Preserving 20,000 Dth per day (NYSEG) Precedent agreement executed with RG&E Capacity Transportati

  128. Slide 128: Significant Expansions Are Driving Growth

    Completed Projects Line N Corridor Line “N” Expansion Line “N” 2012 Expansion Line “N” 2013 Expansion Mercer Expansion West Side Expansion Total Capacity 603 MDth/d Delivering Gas North Tioga County Extension Northern Access Northern Access 2015 Clermont to Chippawa Total Capacity 1,060 MDth/d Leavi

  129. Slide 129: Expansion Project Revenue Growth

    Larger projects under consideration for fiscal 2016 and 2017 will drive significant revenue growth Pipeline & Storage Expansion Project Revenue Growth

  130. Slide 130: New Shale Production Driving Tremendous Growth

    Midstream Businesses New Shale Production Driving Tremendous Growth

  131. Slide 131: Utility

    128 ureansumog €10z saquiaaon - heq yshjeuy

  132. Slide 132: New York & Pennsylvania Service Territories

    Utility New York & Pennsylvania Service Territories New York Total Customers: 520,000 Rate Mechanisms: Revenue Decoupling Weather Normalization Low Income Rates Choice Program/Purchase of Receivables Merchant Function Charge (Uncollectibles Adjustment) 90/10 Sharing (Large Customers ) Natural Gas Ve

  133. Slide 133: Customer Usage

    Utility Customer Usage Residential Usage Industrial Usage

  134. Slide 134: Continued Cost Control Helps Provide Earnings Stability

    Utility Continued Cost Control Helps Provide Earnings Stability

  135. Slide 135: Capital Spending Largely Focused on Maintenance

    Utility Capital Spending Largely Focused on Maintenance The Utility remains focused on spending to maintain the ongoing safety and reliability of its system

  136. Slide 136: Providing Predictability and Stability

    Utility Providing Predictability and Stability

  137. Slide 137: Working Towards a Settlement in New York

    Utility Working Towards a Settlement in New York March 27, 2013 Filed a plan with the NY PSC to adopt an earnings sharing and stabilization mechanism on earnings above a 9.96% ROE April 19, 2013 NY PSC issued an Order to Show Cause (OTSC) commencing a proceeding to establish “temporary rates” June 1

  138. Slide 138: Hedging Strategy

    ayeiodi05 €10z saquiaaon - heq ys4qeuy

  139. Slide 139: How Does Seneca Sell its Production?

    Well Head Interconnection with Interstate Pipeline Network 3rd Party Marketer (or spot market) Firm Transport Demand Center (firm sales or spot market) Spot Market Hedging Overview How Does Seneca Sell its Production? Gathering System Contracted Basis Differential FT Rate The 1,700 to 2,000 economic

  140. Slide 140: Firm Sales Provide a Market for Appalachian Production

    52 Hedging Overview Firm Sales Provide a Market for Appalachian Production Prices shown represent the sales (netback price) at the first non-affiliated interstate pipeline, including the cost of all related downstream transportation.

  141. Slide 141: Seneca Methodically Layers in Index Hedges Over Time

    Hedging Overview Seneca Methodically Layers in Index Hedges Over Time

  142. Slide 142: Current Hedge Book has Seneca Positioned Very Well

    Hedging Overview Current Hedge Book has Seneca Positioned Very Well

  143. Slide 143: Oil & Natural Gas Hedges are Above the Current Strip

    Commodity Risk Management Oil & Natural Gas Hedges are Above the Current Strip (1)

  144. Slide 144: Determining Seneca’s Realized Price on Firm Sales

    Hedging Overview Determining Seneca’s Realized Price on Firm Sales NYMEX & Dominion Monthly Settlement Prices Natural Gas Index Swaps Negotiated at time of Agreement Based on Current Market at Sales/Delivery Point

  145. Slide 145: The Impact of Firm Sales on Realized Price

    57 Determining the Price of a Firm Sales Contract Hedging Overview The Impact of Firm Sales on Realized Price Contract Reference Point NYMEX Dominion December Settlement $4.000 $3.650 Less: Average Sales Basis Differential ($0.284) ($0.265) Average Realized Price (Before Hedging) $3.716 $3.235

  146. Slide 146: Pairing Firm Sales with Hedges Leads to Price Certainty

    58 Determining the Price of a Firm Sales Contract With a $4.25/MMBtu Hedge at the Reference Point Hedging Overview Pairing Firm Sales with Hedges Leads to Price Certainty Contract Reference Point NYMEX Dominion December Settlement $4.000 $3.650 Less: Average Sales Basis Differential ($0.284) ($0.265

  147. Slide 147: Price Certainty only if Firm Sales & Hedge Index Match

    59 Hedging Dominion Firm Sales Contracts With a $4.25/MMBtu Hedge at NYMEX vs. Dominion Hedging Overview Price Certainty only if Firm Sales & Hedge Index Match Contract Reference Point Dominion Dominion December Settlement $3.650 $3.650 Less: Average Sales Basis Differential ($0.265) ($0.265) Averag

  148. Slide 148: FY 2014 Production – Firm Sales & Hedge Composition

    Hedging Overview FY 2014 Production – Firm Sales & Hedge Composition Price Certainty 100% Hedged @ $4.24 /MMcf Price Certainty 92% Hedged @ $4.26/MMcf Seneca has an additional 12.7 Bcf of NYMEX hedges to help mitigate commodity exposure on its WDA sales EDA NYMEX Firm Sales EDA DOM Firm Sales EDA Sp

  149. Slide 149: Financial Wrap-Up

    ayeiodi05 €10z saquiaaon - heq ys4qeuy

  150. Slide 150: Targeting Sustained Growth for the Next Five Years

    National Fuel Gas Company Targeting Sustained Growth for the Next Five Years

  151. Slide 151: Capital Spending Adjusts to Capitalize on Opportunities

    National Fuel Gas Company Capital Spending Adjusts to Capitalize on Opportunities

  152. Slide 152: Forecasting a Modest Outspend in 2014

    National Fuel Gas Company Forecasting a Modest Outspend in 2014 Forecast

  153. Slide 153: Maintaining a Strong Balance Sheet

    Total Debt (1) 43% Debt / Adjusted EBITDA Capitalization National Fuel Gas Company Maintaining a Strong Balance Sheet $3.843 Billion As of September 30, 2013

  154. Slide 154: Strong Liquidity with an Investment Grade Rating

    5.58% Embedded Cost of Long-Term Debt Liquidity ($Millions) National Fuel Gas Company Strong Liquidity with an Investment Grade Rating Cash and Temporary Investments $ 65 Available Short-Term Credit Facilities $1,085 Total Short-term Liquidity $1,150

  155. Slide 155: Focused on Delivering Strong Returns

    2009-2011 2010-2012 2011-2013 National Fuel Gas Company Focused on Delivering Strong Returns NFG Percentile 81% 75% 88%

  156. Slide 156: Dividend Track Record

    Dividend Consistency National Fuel Gas Company Dividend Track Record Current Dividend Yield (1) 2.1% Consecutive Dividend Payments 111 Years Consecutive Dividend Increases 43 Years Current Annualized Dividend Rate $1.50 per Share

  157. Slide 157: A History of Success & A Future of Opportunity

    Adjusted EBITDA Growth Production Growth Midstream Businesses EBITDA Adjusted EBITDA Growth Production Growth Midstream Businesses EBITDA A History of Success A Future of Opportunity National Fuel Gas Company A History of Success & A Future of Opportunity 30% CAGR Since 2009 10-15% CAGR 2014 to 2018

  158. Slide 158: Appendix

    xrpuaddy €10z s2quaaon - heq yshjeuy

  159. Slide 159: Gathering Historical Financials – 2010 & 2011

    Gathering Historical Financials – 2010 & 2011 QTD ended QTD ended QTD ended QTD ended 12/31/2009 3/31/2010 6/30/2010 9/30/2010 FISCAL 2010 Operating Revenue $ $ 1,224 $ 1,237 $ 3,398 $ Operating Expenses: Operation & Maintenance Expense 1,369 Property, Franchise & Other Taxes - Depreciation, Depleti

  160. Slide 160: Gathering Historical Financials – 2012 & 2013

    Gathering Historical Financials – 2012 & 2013 QTD ended QTD ended QTD ended QTD ended 12/31/2011 3/31/2012 6/30/2012 9/30/2012 FISCAL 2012 Operating Revenue 3,565 $ 3,346 $ 4,494 $ 6,069 $ 17,474 $ Operating Expenses: Operation & Maintenance Expense 2,440 Property, Franchise & Other Taxes Depreciati

  161. Slide 161: Comparable GAAP Financial Measure Slides and Reconciliations

    National Fuel Gas Company Comparable GAAP Financial Measure Slides and Reconciliations This presentation contains certain non-GAAP financial measures. For pages that contain non-GAAP financial measures, pages containing the most directly comparable GAAP financial measures and reconciliations are pro

  162. Slide 162: Reconciliation of E&P West Division Adjusted EBITDA to Segment Net Income

    Reconciliation of Exploration & Production West Division Adjusted EBITDA to Exploration & Production Segment Net Income ($ Thousands) FY 2013 Exploration & Production - West Division Adjusted EBITDA 215,042 $ Exploration & Production - All Other Divisions Adjusted EBITDA 277,341 Total Exploration &

  163. Slide 163: Reconciliation of Adjusted EBITDA to Consolidated Net Income

    Reconciliation of Adjusted EBITDA to Consolidated Net Income ($ Thousands) FY 2009 FY 2010 FY 2011 FY 2012 Exploration & Production - West Division Adjusted EBITDA 171,572 $ 187,838 $ 187,603 $ 226,897 $ 215,042 $ Exploration & Production - East Division Adjusted EBITDA 57,179 $ 75,098 $ 175,392 $ 1

  164. Slide 164: Reconciliation of Segment Capital Expenditures to Consolidated

    Reconciliation of Segment Capital Expenditures to Consolidated Capital Expenditures ($ Thousands) FY 2014 FY 2009 FY 2010 FY 2011 FY 2012 FY 2013 Forecast Capital Expenditures from Continuing Operations Exploration & Production Capital Expenditures 188,290 $ 398,174 $ 648,815 $ 693,810 $ 533,129 $ $