Gold Fields Limited · JSE:GFI
Gold Fields — WA Mining Club (July 2018)
20 slides from Gold Fields's conference presentation, Jul 26, 2018
Slide 1: Gold Fields – Delivery & Growth
Gold Fields – Delivery & Growth STUART MATHEWS Executive Vice President: Australasia 26 July 2018
Slide 2: Forward looking statements
Certain statements in this document constitute “forward looking statements” within the meaning of Section 27A of the US Securities Act of 1933 and Section 21E of the US Securities Exchange Act of 1934. In particular, the forward looking statements in this document include among others those relating
Slide 3: Global Footprint
Global Footprint Gold Fields Group 2017 Performance Mines: 7 Projects: 2 Att. production: 2,160koz AIC: US$1,088/oz Net cash flow*: US$441m West Africa region Mines: Tarkwa and Damang Att. production: 639koz AIC: US$1,119/oz Net cash flow*: US$179m inflow Americas region Mine: Cerro Corona (Peru) Au
Slide 4: Australia
Australia Invicible Open Pit Regional Summary St. Ives Mine ● 17 years in Western Australia ● 3rd largest gold miner in Australia (2nd in WA) ● Underground (80%) & Open Pit Mining (20%) ● 43% of Group gold production ● 42% of Net Cash Flow ● Approx. 2200 employees and contractors ● +A$1bn contributi
Slide 5: Gold Fields in Australia – 2017 Performance
Gold Fields in Australia – 2017 Performance •Production: 935koz •AIC: A$1,238/oz Gold Fields Australia (US$948/oz) •Net cash flow: (Divested US$187m (A$243m) Oct’17) •Production: 364koz •AIC: A$1,198/oz St Ives (US$922/oz) •Net cash flow: US$83m (A$108m) •Production: 290koz •AIC: A$1,171/oz Granny S
Slide 6: Historical Gold Production Profile - Australia
Historical Gold Production Profile - Australia Australian Gold Production Ozs St. Ives & Acquisition of 1,000,000 Agnew Granny Smith, Acquisition Lawlers, Darlot Oct’13 800,000 600,000 400,000 200,000 Darlot Granny Smith Agnew St Ives - 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 201
Slide 7: Exploration Expenditure
Exploration Expenditure Sustained & Growing Investment Exploration Expenditure – Australia 120.0 100.0 80.0 60.0 St. Ives Mill Upgrade 40.0 4 Mines Gold downturn Agnew 2 MInes St. Ives 20.0 Agnew Company restructure Granny Smith St. Ives Granny Smith, Lawlers, Darlot Darlot acquisition - 2002 2003 2
Slide 8: Exploration Investment History
Exploration Investment History Australia Context A$76.6M Average A$43M 2013 - 2017 Average 4 Mines A$36M 2005 - 2012 (St. Ives, Agnew, Granny Average Smith, Darlot) 2 Mines 1x Development Project A$28M 2002 - 2004 Multi-mine site at St. Ives Increased mill capacity 2017 – A$94M 2 Mines Increased pro
Slide 9: Vision: To be the global leader in sustainable gold mining
Vision “To be the global leader in sustainable gold mining” 9
Slide 10: Our Values
Our Values We run a business on these values 10
Slide 11: Gold Fields Brand in Australia
Gold Fields Brand in Australia How we operate & what we offer ● Strong safety culture ● Sustainability (safety, environment, community) – No.1 on the Dow Jones Sustainability Index for Extractive Industries ● Strong production profile ● Long life mines ● Demonstrated growth – exploration investment
Slide 12: Gold Fields in Western Australia – Part of the Community
GOLD FIELDS IN WESTERN AUSTRALIA PART OF THE COMMUNITY 12
Slide 13: Gruyere Project
Gruyere Project | Govo (ae
Slide 14: Gruyere Gold Project
Gruyere Gold Project 50:50 Joint Venture – Gold Fields & Gold Road Resources Tailings Storage Facility ● Largest gold development project in Australia July 2018 ● 200 kms NE of Laverton ● A$532M (+10% at top end of project estimate declared). Definitive Estimate under review ● Gold Fields managing p
Slide 15: Gruyere Gold Project – Progress Update End Q2 2018
Gruyere Gold Project Project Progress Update – End Q2 2018 ● On target as per defined Schedule ● Peak Construction from mid- August to November ● Engineering 91% complete ● Process Plant (Engineering, Procurement, Construction) at 33% complete ● Total site Construction at 57% complete ● EPC Contract
Slide 16: Gruyere Accommodations & Aerodrome
Gruyere Gold Project Gruyere Accommodations & Aerodrome • 648 Room camp fully commissioned • Good communications established • Fully landscaped • Full gym facilities • Within 6 km of mine operations and plant • Direct access from aerodrome to camp • Sealed aerodrome fully Certified and in operation
Slide 17: Gruyere Gold Project Overview
Gruyere Gold Project Overview Current Status and Progress Update Primary Crusher Crusher Apron Feeder Coarse Ore Stockpile CIL and Leach Tanks & Thickeners Gruyere Q2 2018 Quarterly Update| Manie McDonald | June 2018 17
Slide 18: Gruyere Gold Project Overview
Gruyere Gold Project Overview Current Status and Progress Update Tailings Screen Structural Steel Crane Pad for Mill Installation Admin Building & ERT Unit Power House Complete Gruyere Q2 2018 Quarterly Update| Manie McDonald | June 2018 18
Slide 19: Gruyere Gold Project Overview
Gruyere Gold Project Overview Process Plant Ponds Current Status and Progress Update . . Gold Recovery Room Earthworks Mine Services Area Lime Storage Silo Assembly Elution Elution Area Area Mine Services Area Powerhouses Workshop Process Plant and Powerhouse Gruyere Q2 2018 Quarterly Update| Manie
Slide 20: Thank you
Thank you QUESTIONS AND ANSWERS