Lomiko Metals Inc.

Lomiko Metals — Technical Presentation (June 2026)

42 slides from Lomiko Metals's technical presentation, June 2026

  1. Slide 1: Introduction to the Exploration Projects and La Loutre Preliminary Feasibility Study

    Introduction to the Exploration Projects and La Loutre Preliminary Feasibility Study Presented by: CEO and President Sustainability Coordinator Knight Piésold Ltd. Knight Piésold Ltd. Kilgour & Associates Ltd. June 2026 TSXV: LMR | Frankfurt: DH8

  2. Slide 2: Disclaimer

    DISCLAIMER This presentation is not a prospectus, offering memorandum or an advertisement and is being provided for information purposes only and does not constitute or form part of, and should not be construed as, an offer or invitation to sell or any solicitation of any offer to purchase or subscr

  3. Slide 3: Land Acknowledgement

    Land Acknowledgement The land/projects where we operate are located within the traditional land of the Kitigan Zibi Anishnaabeg First Nations territory. Our vision is to embrace Indigenous people and Indigenous values within our projects to develop a sustainable approach on our path to critical mine

  4. Slide 4: Agenda

    AGENDA 1. Project Location 2. Field work winter 2025 3. Pre-feasibility study for the La Loutre project 4. Economic projections 5. Project changes based on feedback 6. Environmental Baseline Study 7. 2026 Planned field work 4

  5. Slide 5: Project Location

    Project Location 5

  6. Slide 6: La Loutre and Ruisseau graphite deposit location

    La Loutre and Ruisseau graphite deposit location Ruisseau Maniwaki Ruisseau La Loutre La Loutre Kitigan Zibi Anishinabeg. (2024). 6

  7. Slide 7: Key Information

    Key Information Location & Project Environmental & Community Considerations • Graphite project in southern Québec • Monitoring of water quality, wildlife, and habitats • Advanced exploration stage • Measures to reduce impacts: • Potential source of critical mineral for o Dust and noise control batte

  8. Slide 8: 2025 Winter Fieldwork

    2025 Winter Fieldwork 8

  9. Slide 9: Field work in the winter of 2025

    Field work in the winter of 2025 • Bulk Sample – Graphite ore was mined to demonstrate the entire value chain from the pilot mine to the battery material process, creating materials for the batteries. • The work was carried out solely in the EV zone (northern zone). • Bulk samples – graphite ores we

  10. Slide 10: Noise monitoring

    Noise monitoring These stations were installed one week before work began in order to establish a baseline for noise levels. Geomechanical drilling: • From November 24, 2025, to January 16, 2026 • No work was carried out on weekends or from December 19 to January 5. • The blasting did not result in

  11. Slide 11: Dust monitoring

    Dust monitoring Quebec regulations: The average fine particulate over a 24-hour period cannot exceed 0.03 mg/m². To ensure compliance with this standard, three monitoring stations were installed near the bulk sampling pits in 2025. These stations operated on site from December 1 to 11. Bulk sampling

  12. Slide 12: Water quality results – Winter 2025

    Water quality results – Winter 2025 Sampling completed before (November), during (December), and after (April) the 2025 bulk sampling program • Water quality monitored at 11 stations since 2021 Most lakes were ice-covered during December monitoring • Flowing streams monitored during blasting and ear

  13. Slide 13: CMRDD program – Anode Upgrading– Battery Testing

    CMRDD program – Anode Upgrading– Battery Testing February & June - August- January - November December 2025 April 2026 May 2026 March 2026 August 2026 December 2026 April 2027 2025 January 2026 Crushing/ Mining Flotation Drying Screening Purification Shaping Coating Grinding Source: Lomiko 13

  14. Slide 14: Preliminary Feasibility Study for La Loutre Project

    Preliminary Feasibility Study for La Loutre Project 14

  15. Slide 15: Preliminary feasibility study

    Preliminary feasibility study What are the different engineering studies? What is a pre-feasibility or Preliminary Feasibility study (PFS)? Study Preliminary Economic Pre-feasibility Study (PFS) Feasibility Study (FS) Assessment (PEA) Concept ‘’What it could be’’ ‘’What it should be’’ ‘’What it will

  16. Slide 16: Lomikos' stages of development

    Lomikos’ stages of development 12 24 - 36 18 28 months months months years Phase 2 Phase 3 Phase 4 Phase 5 Construction and Start of graphite Metalurgical study and Detailed environmental impact commissioning of the concentrate at 97%Cg sampling study demonstration plant production Construction of t

  17. Slide 17: Project infrastructure and operations

    Project infrastructure and operations Total surface: 2.2 square kilometers, or 1.3% of the municipality of Lac des Plages. All structures are to be located 60 m from lakes and rivers. Other infrastructure includes: • Open-pit mine - Operation 10 months a year • Plant • Mining waste (rock & Dry taili

  18. Slide 18: Economic Projections

    Economic Projections 18

  19. Slide 19: Project Opportunities

    Project Opportunities • A total of up to 250 jobs will be created. • 160 operations employees would be needed during the entire production (30 years) • 250 construction workers would be needed during the construction phase. Lomiko will train local workers for equipment or factory operator positions.

  20. Slide 20: Pre-feasibility Study Graphite Production

    Pre-feasibility Study Graphite Production Ranked as the 7th largest graphite deposit in the world by Mining.com and Mining Intelligence, the La Loutre project is located in Quebec, Canada. The property lies within the Grenville Geological Province, renowned for its favorable conditions for the forma

  21. Slide 21: Project Economics PFS Level

    Project Economics PFS Level Net present value (NPV@8%) Internal rate of return (IRR) Payback Period • Before tax: CAD $797.5M • Before tax: 30.3% • Before tax: 3.08 years • After tax: CAD $617.4M • After tax: 24.7% • After tax: 3.24 years Initial investment to build the mine and infrastructure: $ 50

  22. Slide 22: Schedule changes

    Schedule changes Summer shutdown: Mining operations will be conducted 10 months per year, with a two-month shutdown planned for July and August. Reasons: • To promote the development of the tourism sector. Estimated lifespan: 28 years plus 2 in construction and an additional 3 in restoration (33 yea

  23. Slide 23: La Loutre Project changes based on feedback

    La Loutre Project changes based on feedback 23

  24. Slide 24: Steps needed for rehabilitation

    Steps needed for rehabilitation Deposit of a financial Restoration work guarantee (associated Mining operations planning with the estimated (including Mine closure Restoration work Environmental (restoration plan) amount of the work) progressive (resource depletion) (including planting) monitoring r

  25. Slide 25: Gradual site restoration

    Gradual site restoration Mining companies must submit a rehabilitation and restoration plan and obtain approval from the relevant ministries. Northern residue storage site All areas affected by mining activities must be revegetated to rehabilitated control erosion and restore a natural appearance to

  26. Slide 26: Waste Disposal Facilities (WDFs)

    Waste Disposal Facilities (WDFs) WDF The mining waste will consist of filtered tailings (i.e., excess Outline water removed using filter presses and air drying) co- disposed with waste rock. Two WDFs were selected in areas with the least impact on aquatic environments (minimum 60 m away from major b

  27. Slide 27: Noise berm

    Noise berm Pit A noise barrier around the pits will be constructed from waste rock to minimize Noise barrier noise from the mining operations. Dimensions: 10 m high by 20-40 m wide. Purpose: • To prevent noise from spreading beyond the construction site. Concevoir les espaces de propagation du bruit

  28. Slide 28: Private road

    Private road Before beginning construction of the final project, it will be essential to build approximately five kilometers of road leading to a highway. We are currently reviewing various route options. After consulting with the communities, we are seeking to identify routes that meet the required

  29. Slide 29: Water from the plant

    Water from the plant The tailings are processed/filtered to remove the moisture. Filtering in done in two stages: • Thickening: Thickening tank • Filtration: using a filter press. Water from the filtration system will be stored in the water tank in the plant and reused in the process for: • Grinding

  30. Slide 30: Contact Water Management

    Contact Water Management Contact water from the WDFs, open pits, noise boundaries, and site infrastructure will be managed to prevent uncontrolled discharge to the environment. Collection ponds are designed to retain sediment and temporarily store runoff during summer/fall storm events. Water from t

  31. Slide 31: Effluent Qualities – Water released from the site

    Effluent Qualities – Water released from the site Effluent water-quality modeling was conducted to verify effluent quality for project planning purposes. Based on the evaluations, it was forecasted that: • Ammonia concentrations are low. • The pH is neutral. • The effluents are non-toxic, as the lev

  32. Slide 32: Geochemical Characterisation

    Geochemical Characterisation Geochemical Testing – Scope and Objectives • Materials tested: o Waste rock o Low grade ore and ore o Tailings • Objectives: assess acid rock drainage (AMD) and metal leaching (ML) potential • Methods: static tests, kinetic (humidity cell) tests, and leach tests • Result

  33. Slide 33: Geochemical Characterisation

    Geochemical Characterisation Waste Rock, LGO and Ore: ARD/ML Behaviour • Both EV and Battery zones contain potentially acid generating (PAG) and non-potentially acid generating (NPAG) samples • Most tested samples generate neutral leachate (pH ~6.5–8.7) in humidity cell tests (HCTs) • One of the 5 w

  34. Slide 34: Geochemical Characterisation

    Geochemical Characterisation Tailings: Geochemical Behaviour and Management • Sulphides (pyrrhotite/pyrite) + carbonates (calcite) → ARD potential partly offset by neutralization • Mineralogical analysis shows neutralizing potential (NP) • ARD onset for tested rock can range from ~23 to 40 years • L

  35. Slide 35: Recommended further studies

    Recommended further studies Predictive water quality additional testing: • Validation of the predicted water quality of the pit based on groundwater sampling. • Conduct humidity cell tests. • Quarterly groundwater monitoring, including a period of 2 weeks to 1 month after installation. Predictive mo

  36. Slide 36: Environmental Baseline Studies

    Environmental Baseline Studies 36

  37. Slide 37: Baseline Studies

    Baseline Studies • 2015 Baseline Studies • 2022 Baseline Studies • Initial Species at screening • Water quality monitoring expanded to 11 stations • Aquatic studies completed • Breeding bird, amphibian, and terrestrial habitat • Fish community and habitat, water surveys completed quality, and benthi

  38. Slide 38: Protected habitat and Special status species

    Protected habitat and Special status species Habitats in the study area Study plan submitted and developed by the Direction de la • Wetlands and fish habitats gestion de la faune de l’Outaouais (DGFa) of the ministère de • White-tailed deer containment area l’Environnement, de la Lutte contre les ch

  39. Slide 39: Summary

    Summary Protecting biodiversity. We are committed to protecting wildlife in the region. Specifically, our work plans will require measures to avoid contact with these animals and minimize our presence in their habitats. Deer habitat. We will take care to preserve the habitat of white-tailed deer. To

  40. Slide 40: 2026 Planned Field work

    2026 Planned Field work 40

  41. Slide 41: Planned survey at La Loutre 2026: Drilling & Test Pits

    Planned survey at La Loutre 2026: Drilling & Test Pits Test pit locations Fall Drill Program Test pit locations Fall Drill Program Test pit locations Site verification for geotechnical work Full project area survey • Infill drill program for Feasibility Study is being developed • KZ Natural resource

  42. Slide 42: Drill Program and Environmental survey Ruisseau 2026

    Drill Program and Environmental survey Ruisseau 2026 Desktop Review • Review of publicly available ecological information: species at risk screening, wetland mapping, fish habitat. Spring Fieldwork: Identify and flag potential ecological features of interest (possible piliated woodpecker nests) Summ

Lomiko Metals — Technical Presentation (June 2026) on 6ix