Nrw Holdings Limited · ASX:NWH

Nrw — FY2021 Earnings Presentation

29 slides from Nrw's earnings presentation, Aug 19, 2021

  1. Slide 1: NRW Holdings FY21 Full Year Results

    Main Roads WA NRW HOLDINGS FY21 FULL YEAR RESULTS 19 AUGUST 2021

  2. Slide 2: Results Overview

    RESULTS OVERVIEW FINANCIAL COVID-19 IMPACT • Revenue up 11.5% to $2.3B in line with guidance. • Major challenge is ongoing management • Earnings (EBITDA) increased to $266.7M up 6.7% compared to FY20; Earnings of our people to ensure their day-to-day (Operating EBIT) of $120.6M were lower than FY20

  3. Slide 3: Environmental, Social & Governance

    ENVIRONMENTAL, SOCIAL & GOVERNANCE

  4. Slide 4: Workforce

    WORKFORCE SAFETY • Continued focus on welfare and safety of workforce including the impact of COVID-19 – the workforce adhered to revised operating procedures as a consequence of COVID-19 and responded well to these challenges. • Total Recordable Injury Frequency Rate (TRIFR) at June 2021 6.25 compa

  5. Slide 5: Sustainability

    SUSTAINABILITY REPORTING AND ONGOING INITIATIVES • NRW is preparing its first Sustainability Report that will be published in September 2021. This report will highlight the alignment of NRW’s corporate values and operations with the United Nations Sustainable Development Goals (SDGs) and be guided b

  6. Slide 6: Workforce: COVID Challenges (Pilbara)

    WORKFORCE: COVID CHALLENGES (PILBARA) TWO KEY ISSUES OVER THE LAST 12 MONTHS Resource availability • Major impact through calendar 2020 during a record period of activity. • Current resource requirements particularly in the Pilbara significantly lower than peak mid 2020 circa 900 (July 2021) v circa

  7. Slide 7: Workforce Major Project Locations

    WORKFORCE MAJOR PROJECT LOCATIONS ROPER BAR Long term contract but relatively new – some challenges but turnover rates improving QLD COAL PROJECTS PILBARA PROJECTS Stable workforce Workforce requirements significantly lower – headcount transitioning to new projects, mining and Strandline NORTHERN DA

  8. Slide 8: Financial Overview

    FINANCIAL OVERVIEW Holdings

  9. Slide 9: Earnings

    EARNINGS • Revenue growth in Mining and MET segments - BGC (Dec 2019), Primero (Feb 2021). • Earnings (EBITDA) increased 6.7% primarily due to the inclusion of mining activities acquired from BGC in FY20. • Operating EBIT impacted by Pilbara based projects due to high staff turnover, labour rate inc

  10. Slide 10: Balance Sheet

    BALANCE SHEET • Boggabri transaction - (shown in pro forma numbers as post year end) comprised sale of $82.6M of mining equipment. • Debt repayments included asset financing repayments of $60.7M, and $21.4M of corporate debt (now fully repaid) mostly relating to business acquisition finance. • New a

  11. Slide 11: Cash Flow

    CASH FLOW • Net cash from operating activities includes circa $66.6M working capital movement due to costs incurred on projects the subject of outstanding claims at year end (see Civil slide). • Other operating cash outflows include repayment of BGC Contracting advances and close out of non performi

  12. Slide 12: Business Structure & Performance

    BUSINESS STRUCTURE & PERFORMANCE

  13. Slide 13: End-to-End Delivery Capability

    END-TO-END DELIVERY CAPABILITY Primero acquisition further enhances delivery 2017 GEOGRAPHIC capabilities across our business. EXPANSION ACQUISITION GOLDING Increased exposure to east coast civil infrastructure, urban and mining markets. INCREASED 2019 CAPABILITIES ACQUISITION RCR MINING TECHNOLOGIE

  14. Slide 14: Business Structure

    BUSINESS STRUCTURE REVENUE FY21 REVENUE FY21 REVENUE FY21 $726.5M $1,177.2M $426.9M 11% 11% 128% CIVIL MINING MINERALS, ENERGY & NRW Civil NRW Mining TECHNOLOGIES Golding Civil Golding Mining Primero Golding Urban Action Drill & Blast RCR Mining Technologies AES Equipment Solutions DIAB Engineering

  15. Slide 15: Civil

    CIVIL

  16. Slide 16: Civil

    CIVIL RESULTS CIVIL PROJECTS • Revenue peaked in calendar year 2020 due to Iron Ore projects including • Resources work won by BGC Contracting acquired in December 2019. o Eliwana stage 1 rail - complete o Most major projects completed early in the second half of FY21 resulting in o Eliwana stage 2

  17. Slide 17: Mining

    MINING

  18. Slide 18: Mining

    MINING RESULTS • Growth in revenue - addition of BGC Contracting’s mining activities which contributed full 12 months compared to seven months in FY20. • Earnings impacted by: o COVID-19 measures on Pilbara iron ore project (now complete); o Staff retention; and o Unseasonal weather events (WA and Q

  19. Slide 19: Karara

    KARARA The Karara mine is the largest mining operation and the first major magnetite mine in the Mid West. • NRW and Karara Mining have commenced work on the PROJECT mobilisation plan to ensure a seamless transition of operations in Client Karara Mining. Magnetite mine site, March 2022. 200kms south

  20. Slide 20: Mining Contracts

    MINING CONTRACTS • Chart below shows Contract status for all current mining activities – with most projects showing full order cover for FY22, (Karara covered by notice of award). • Key contract extensions include Curragh where we have LOI for five year contract extension. • Other projects subject t

  21. Slide 21: Minerals, Energy & Technologies

    MINERALS, ENERGY & TECHNOLOGIES

  22. Slide 22: Minerals, Energy & Technologies (MET)

    MINERALS, ENERGY & TECHNOLOGIES (MET) RESULTS MET PROJECTS • Revenue increased due to addition of Primero from February 2021 and • Cloudbreak Hopper 9 - complete growth in RCR Mining Technologies (RCRMT) and DIAB Engineering. • Queens Primary crusher - ongoing - awarded in FY21 • RCRMT and DIAB Engi

  23. Slide 23: Summary

    SUMMARY Holdings

  24. Slide 24: Outlook

    OUTLOOK • Group Order book at 30 June 2021 was $3.4B, (or at least $4.4B including Curragh LOI) compared to $3.0B at the same time last year. • The near term tender pipeline capable of being awarded in the next 12 months has strengthened to $14.5B compared to $14.1B at the half year and $12B at 30 J

  25. Slide 25: Appendices

    pone am APPENDICES Holdings

  26. Slide 26: Appendix 1: Non-Recurring Transactions

    APPENDIX 1 NON-RECURRING TRANSACTIONS ($M) 20 JUNE 21 30 JUNE 20 Gascoyne recapitalisation 12.4 - Altura Mining (19.1) - Costs related to business acquisitions (4.5) (14.9) EBIT (11.2) (14.9) Gascoyne Recapitalisation • Funds received post Gascoyne recapitalisation included cash and shares (valued a

  27. Slide 27: Appendix 2: Segment Results Under New Structure

    APPENDIX 2 SEGMENT RESULTS UNDER NEW STRUCTURE FY21 FY20 CIVIL ($M) H1 H2 Total H1 H2 Total Revenue 474.7 251.8 726.5 305.0 515.1 820.1 EBITDA 20.2 8.4 28.6 13.3 21.1 34.4 % 4.3% 3.3% 3.9% 4.4% 4.1% 4.2% Operating EBIT 16.3 6.6 22.9 9.8 16.7 26.5 % 3.4% 2.6% 3.1% 3.2% 3.2% 3.2% FY21 FY20 MINING ($M)

  28. Slide 28: Disclaimer

    DISCLAIMER SUMMARY INFORMATION • This Presentation contains summary information about NRW and its associated entities and their activities current only at the date of this Presentation. • This Presentation is for general information purposes only and does not purport to be complete. The content shou

  29. Slide 29: Contact details

    181 Great Eastern Highway BELMONT WA 6102 (08) 9232 4200 www.nrw.com.au

NRW Holdings — FY2021 Earnings Presentation on 6ix