Slide 1: Stratford Coal CCC Meeting Presentation
Stratford Coal CCC Meeting Presentation – Company Report & Overview of Activities February 2021 Michael Plain Environment & Community Superintendent
Slide 2: Table of Contents
Table of Contents 1. Agenda Item 7a (Progress at the Mine) 2. Agenda Item 7b (Environmental Reporting) 3. Agenda Item 7c (Environmental Management Plans and Monitoring) 4. Agenda Item 7d (Community Complaints) 5. Agenda Item 7e (Community Programs) 2
Slide 3: Covid-19 Response
Covid-19 Response The impacts of the Covid-19 pandemic has been risk assessed with significant measures undertaken on-site to protect and safeguard the health of our team members and community from infection and to protect our ability to operate our core business. Measures on site include but are no
Slide 4: 1. Progress at the Mine
1. Progress at the Mine Mining 4th Quarter 2020 Total Waste ROM (T) Product Product (BCM) Coking (T) Thermal (T) Q4 2020 2,095,000 391,936 80,503 141,676 ▪ Mining in Avon North continued during the quarter. Day and evening shift. ▪ Mining in Stratford East Pit during day and evening shift. Stage 2 c
Slide 5: 2. Environmental Reporting & Regulators
2. Environmental Reporting & Regulators Management Area Project Status Reporting • Stratford Mining Complex • The Stratford Mining Complex 2020 Annual Review is currently being prepared. Annual Review 2020 Submission to DPIE is due 31 March 2021. Copies will be made available to the CCC and on the S
Slide 6: 3. Environmental Management Plans & Monitoring
3. Environmental Management Plans & Monitoring a) Air Quality Management b) Blast Management c) Noise Management d) Water Management e) Rehabilitation Management f) Biodiversity Management g) Mine Closure Planning 6
Slide 7: 3a. Air Quality Management
3a. Air Quality Management Management Area Project Status Air quality monitoring • Real-time air quality • The real-time air quality TEOM monitors in Stratford and Craven villages monitoring continue to operate. • General ambient PM10 dust levels have been very low throughout spring/summer due to in
Slide 8: 3a. Air Quality Management - Dust
3a. Air Quality Management Stratford Dust Deposition - Annual Rolling Average Stratford HVAS Monitoring - Particulate Matter (PM10) 12 Months to December 2020 12 Months to December 2020 5.0 80 70 4.0 PM10 (µg/m³) Dust (g/m2/month) 60 3.0 50 40 2.0 30 1.0 20 10 0.0 0 Jan-20 Mar-20 May-20 Jul-20 Sep-2
Slide 9: 3b. Blast Management
3b. Blast Management Management Area Project Status Blasting • Blast Monitoring • Blasting activities continued in Avon North, Roseville West and Stratford East open cuts. • For the annual reporting period 0% of blasts have exceed 115dB(L) (No more • Blast Results than 5% of total blasts allowed to
Slide 10: 3b. Blast Management
3b. Blast Management Ground Clarke (B5) (Mine- Overpressu Vibration Isaac (B1) Ex-Judge (B2) Atkins (B6) Greenwood owned) re Site Monitored Fume Date Time Site 7432 7441 7434 7422 7433 Exceedanc Blasts1 Rating Exceedanc (previously 7377) e1 e1 24hr mm/s dBL mm/s dBL mm/s dBL mm/s dBL mm/s dBL % % We
Slide 11: 3c. Noise Management
3c. Noise Management Management Area Project Status Monitoring • Monthly Noise Survey • Monthly attended noise monitoring was undertaken during Q4 2020. • No non-compliant results were recorded during the surveys. Reports will be made available on the Stratford Coal website. • The next monitoring is
Slide 12: 3d. Water Management
3d. Water Management Management Area Project Status Site Water • Annual water balance • The 2020 annual site water balance is currently being prepared. A summary will be Management review. included in the Annual Review 2020/21 and will be available on the Stratford Coal website. Water management • S
Slide 13: 3d. Water Management
3d. Water Management Stratford Monthly Rainfall pH - Avon River & Avondale Creek 12 Months to December 2020 400 9 Rainfall (mm) 8 200 pH 7 0 6 2021 JAN FEB MAR 2020 APR MAY JUN JUL 5 AUG SEP 01-Jan-20 31-Mar-20 29-Jun-20 27-Sep-20 26-Dec-20 2019 OCT NOV 2018 Month DEC W1 W2 W3 W3A W4 W5 W6 EC - Avon
Slide 14: 3e. Rehabilitation Management
3e. Rehabilitation Management Management Area Project Status Rehabilitated Waste • Avon North waste • Seeding of the northern side of Avon North waste emplacement was completed Emplacements emplacement in April 2020. Due to poor establishment of vegetation, rework and reseed of the Avon North Waste
Slide 15: 3e. Biodiversity Management
3e. Biodiversity Management Management Area Project Status Biodiversity Offset • Revegetation • Planning has been finalised for the revegetation works scheduled in Q1 2021. Area Planning • Planting areas will include offset properties near Craven, Woods Rd and ex- Foreman/Johnson property. Additiona
Slide 16: 3f. Biodiversity Management
3f. Biodiversity Management Management Area Project Status Nest Box Program • Nest Box Installation • 93 Nest boxes are proposed to be installed in the Stratford Biodiversity Area and Biodiversity Enhancement Area in March 2021. These nest boxes are to specifically target the Squirrel glider and oth
Slide 17: 3g Mine Closure Planning
3g Mine Closure Planning Note: *Refer to Stratford Mining Operations Plan & Rehabilitation Management Plan Table 13 Mine Closure Planning Schedule. *Further detail on mine closure planning progress is included in the Annual Review 2020. Management Project Status Area Mine Closure • Stakeholder • Com
Slide 18: 4. Community Complaints - Summary
4. Community Complaints - Summary Stratford Complaint Summary Period: 31/10/2020 - 31/1/2021 Period: 3 Months Total No. of Complaints: 16 Total No. of Complainants: 4 Date/Time of Complainant Method of Complaint Location Complaint Nature of Complaint Investigation/Outcome 12/11/2020 16:48hrs Approx.
Slide 19: 4. Community Complaints - Summary
4. Community Complaints - Summary 3/12/2020 7:16hrs Approx. 2.6km west of Community Hotline Noise Complaint: "Incredibly noisy, sounds like trucks coming through the wall, I'm a shift worker" source • ECC Returned complainants call at 10:10 as requested. •Complainant explained that there had been lo
Slide 20: 4. Community Complaints - Summary
4. Community Complaints - Summary 9/12/2020 9:58hrs Approx. 3.2km west of the Community Hotline Noise Complaint: "2nd call - Also called last night. Very loud machinery noise, and loud horns. Lights are also pointing at operation his house again." • ECC Returned complainants call at 9:20AM. Complain
Slide 21: 4. Community Complaints - Summary
4. Community Complaints - Summary 21/12/2020 21:55hrs Approx. 2.6km west of Community Hotline Noise Complaint: "Loud noise, sounds like a highway coming through the house" source • Complainant did not request a call back. • Weather conditions: Persistent rain/12/2020. Light N wind conditions at the
Slide 22: 4. Community Complaints - Summary
4. Community Complaints - Summary 8/01/2021 12:42hrs Approx. 1.5km from Direct text to MP mobile Blast vibration Complaint via text: "You just shook the house we have two more witnesses enough is enough". location, Bowens Road • SCPL forwarded details of complaint to drill and blast engineer. Stratf
Slide 23: 5. Community Programs
5. Community Programs Management Area Project Status Support Programs Stratford Coal • The application period for the Stratford Coal Community Support Program for 2021 has now Community Support closed. A review of the applications is currently being undertaken and notification to the Program success