Strike Energy Limited · ASX:STX

Strike Energy — Good Oil and Gas Energy Conference 2021

14 slides from Strike Energy's conference presentation, Sep 8, 2021

  1. Slide 1: Perth Basin Gas Update

    Perth Basin Gas Update

  2. Slide 2: Summary information

    yoy strike Summary information This presentation contains summary information regarding Strike Energy and its subsidiaries current as at 8 September 2021. The information in this presentation is of general background only and does not purport to be complete. The contents of this presentation should

  3. Slide 3: Gas value chain: reserves to domestic demand and export

    Dom Storage dem Reserves Production Processing Transmission Domestic Conversion Ex demand to LNG Storage Reserves Production Processing Transmission Conversion Export to LNG Do Storage Storage d Domestic Reserves Reserves Production Processing Production Storage Processing Transmission Transmission

  4. Slide 4: The Permian Gas Fairway: view from South Erregulla

    40 30 20 10 O - : View from South Erregulla | : \ : 2223 = 3 > : 0. Strike The Permian Gas Fairway Lower Kingia Net Pay (m) : Near Fop-Garynginia Shale} + a = = Mea Braga 3 $2 s%°% ee West Bavgalla 5 Wea eeu 2 Wes Brezue 2 (Wen Bragulla 4 a Q Waitsia Hl West Erregulla Beharra ; Ex, : } eu f se <a Ha

  5. Slide 5: Consistent geological outcomes from the Permian Gas Fairway

    ye . Consistent geological outcomes from the strike , Permian Gas Fairway pendirmre-entry 14% phi and.colmletion ain StrOMBBasshows » ‘ 4 : ae of conventional reservoir (2s te peemn EresmaT | development = Spud. in late Nov gaiNest Erregulla 5 y ‘ Large pronounced 2m net pay at 10% Cae J sfeieture =

  6. Slide 6: Strike's acreage at the centre of attention

    0. Strike Strike’s acreage at the centre of attention ] T Strike, Beach/Mitsui and Minres/Norwest = Strike has proven correlation between | Permian Portfolio’s structurally conformable amplitudes and gas ; : Lockyer Deep / prone permeable sandstones. Wait \ ™ North Erregulla . . Mel sia y As = Disco

  7. Slide 7: Major seismic illuminates South Erregulla

    strike Maior seismic illuminates South Erregulla \ U ms at M21 L-001 PSTM ¢ | M21 L-002 PSTM : — somereoue | | t = Pb | | —~ M21 L001 SWEETNESS = Recently acquired Maior 2D seismic data confirms presence of large continuous structure at South Erregulla and increases confidence ahead of drilling = So

  8. Slide 8: Walyering & Jurassic Wet Gas Appraisal

    yoy strike STX 400% in all —_ ™ The Walyering conventional gas discovery was made in the permits Jurassic wet gas play (at 3,400m SS) and flowed ~14 TJ/d Walyering & Jurassic Wet Gas Appraisa Ocean Hill ™ The play has supported other commercial gas projects at Gin-Gin and Red Gully. ™ Post 3D seismi

  9. Slide 9: Exploration, Appraisal and Production Testing

    yoy strike Exploration, Appraisal and Production Testing » All permits for CY21 activities submitted or approved. = Some minor delays have impacted long lead delivery due to COVID affected shipping. = Rig slot secured for WES re-entry. * Optional slot remaining for follow-on appraisal or possible ge

  10. Slide 10: WA Govt supporting downstream projects

    WA Govt supporting downstream projects ot strike through investment and domgas policy Strike interpretation of the WA Government response: 1. Gas suppliers who support and enable downstream development may be considered for exemptions to the domgas policy and allowed to access LNG export capacity 2.

  11. Slide 11: North West Shelf LNG production and sanctioned backfill

    yoy strike North West Shelf LNG production and sanctioned backfill (TJ/d, year) 2,400 1,600 800 20 21 22 23 24 25 Mi Waitsia HY Pluto-NWS HE NWS LNG Prod LNG netback pricing could emerge as the new non-domestically reserved floor price for WA gas Source: Rystad Energy GasMarketCube, Ucube and Strike

  12. Slide 12: What does LNG netback pricing look like for Strike Perth Basin gas?

    yy trik What does LNG netback pricing look like for e Strike Perth Basin gas? Perth Basin LNG Spot netback gas price per GJ usp (AUD & USD, as at 7" Sept 2021) Aub = Atcurrent prices an incremental 20.3 “1.0. Pm ee 9 AS14/GJ margin could 18 127 | be achieved should =_—— LNG spot netback pricing occu

  13. Slide 13: Greater Erregulla Phase

    yoy strike Greater Erregulla Phase 1 West Erregulla Gas Project Resources Confirmed Resources & Reserves Reserves Pending with All EP’s submitted awaiting approvals Foundation Gas Sales! Australian Gas Development Plan Q) Infrastructure Group BOO 87TJ/d Omecauarie up to $28m Pre-Development facility

  14. Slide 14: Slide 14