  1. Slide 1: Constructing the Next European Potash Mine

    For personal use only Constructing the Next European Potash Mine Corporate Presentation December 2021 ASX: HFR

  2. Slide 2: Competent Persons Statement for Muga Ore Reserves, Mineral Resources and Exploration Target

    For personal use only COMPETENT PERSONS STATEMENT FOR MUGA ORE RESERVES, MUGA MINERAL RESOURCES and EXPLORATION TARGET This update was prepared by Mr. Ignacio Salazar Director of Highfield Resources. The information in this update that relates to Ore Reserves is based on information prepared under t

  3. Slide 3: Introduction

    For personal use only INTRODUCTION

  4. Slide 4: An Investment Opportunity in the Next Major European Potash Mine

    An Investment Opportunity in the Next Major European Potash Mine For personal use only Muga Potash Mine Highfield Resources Strong market fundamentals Strong financial position and Global potash prices on the move financial markets support Location is a major strategic advantage Experienced Manageme

  5. Slide 5: Milestones Achieved

    Milestones Achieved For personal use only Detailed design engineering prepared Mining concession received on 1 and ready July 2021 Permitting Engineering 85% of the process plant equipment has Documentation submitted for been contracted construction licences Endeavour Financial appointed, finalising

  6. Slide 6: Updated Feasibility Study Reconfirms Muga's Strong Economics

    Updated Feasibility Study Reconfirms Muga’s Strong Economics For personal use only Updated capex numbers with More advanced engineering NPV8 of €1.89 Billion higher degree of accuracy: reconfirming a 30-year mine 25% IRR phase 1 €398 million life1 phase 2 of €209 nillion At current spot price Debt s

  7. Slide 7: Muga Moving to Construction

    Muga Moving to Construction For personal use only 2021 2022 2023 2024 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Contract with construction partner Finalise procurement of long-lead items Mining Local town hall construction licenses Concession Reconfirm debt credit approval Equity Raise Finalise funding package Appoin

  8. Slide 8: Global Potash Prices on the Move at the Right Time

    Global Potash Prices on the Move at the Right Time For personal use only Strong market fundamentals Upward price forecasts 525 Soybean prices are the 02 10 475 highest in 5 years Billions of tonnes 02 08 425 Billion 06 US$/t 01 04 01 375 02 00 00 325 1983 1980 1986 1989 1992 1995 1998 2001 2004 2007

  9. Slide 9: Overview Muga Project

    For personal use only OVERVIEW MUGA PROJECT

  10. Slide 10: Highfield Resources and the Muga Project

    Highfield Resources and the Muga Project For personal use only Conventional Underground A potash developer listed on the Muga is a two phase project Conventional Flotation and Room and Pillar mining. ASX (HFR) with projects in which will produce a total of 1 Crystallisation processing Declines acces

  11. Slide 11: Shallow Mineralization, Conventional Mining, with Tier-One Infrastructure in Place

    Shallow Mineralization, Conventional Mining, with Tier-One Infrastructure in Place For personal use only 350m Decline access to shallow mineralization; underground Close to the Port of Bilbao (~220km), Room and Pillar mining. No aquifers Spain’s largest port First class infrastructure and National E

  12. Slide 12: Sales and Marketing

    For personal use only SALES AND MARKETING

  13. Slide 13: Significant Logistical Competitive Advantage

    Significant Logistical Competitive Advantage For personal use only Extremely competitive and versatile export options Muga will be one of only two ~1,750km from mines to port ~1,700km from mines to potash mines located in port Southern Europe ~130- 220km from ~6,800 nautical miles mine to ports ~8,7

  14. Slide 14: MOUs signed for more than phase 1 production

    MOU signed for more than phase 1 production For personal use only MOP sales (pa) Wider Europe: Salt sales (pa) • ~250-300 kt MOP • ~200-250 kt salt US East Coast: • ~50 kt MOP Local: Potash MOUs signed • ~200-250 kt salt • ~450-500 kt MOP • ~400-500 kt salt MOP Ameropa 250,000 tpa Africa: Keytrade 3

  15. Slide 15: Project Economics

    For personal use only PROJECT ECONOMICS

  16. Slide 16: Muga Mine – Key Physicals and Financials

    Muga Mine – Key Physicals and Financials For personal use only 2 December 2021 CAPEX phase 1 (500,000 tpa MOP) €398 million CAPEX phase 2 (Additional 500,000 tpa MOP) €209 million Total CAPEX €607 million ROM tonnes 173.7 million tonnes Average plant tonnage feed rate 400 tph K2O grade 10.5% KCl rec

  17. Slide 17: Top Quartile Margins in the Industry

    Top Quartile Margins in the Industry For personal use only European prices continue to trade at a Margin curve forecast for 2024 (real US$) premium to other markets​ 750 200 650 150 550 100 US$/t 450 US$/t 350 50 250 00 150 0 10 20 30 40 50 60 70 -50 Potash Standard MOP bulk fob Vancouver US$/t -100

  18. Slide 18: Low Capex Intensity and Strong Project Economics

    Low Capex Intensity and Strong Project Economics For personal use only Phase 1 capex of €398 million + Phase 2 capex of €209 million MUGA: HALF THE CAPEX INTENSITY OF OTHER GLOBAL DEVELOPMENT PROJECTS (US$ per tonne of potash) 1,800 1,600 Capex intensity $/t 1,400 1,200 1,000 800 600 400 200 - BHP (

  19. Slide 19: CSR and Sustainability

    For personal use only CSR AND SUSTAINABILITY

  20. Slide 20: Industry Leading ESG Credentials

    Industry Leading ESG Credentials For personal use only • Environmental compliance and commitment through DIA award Environmental • Progressively rehabilitate mine: Backfilling and salt sales • Muga will be the only mine not to leave residue on the surface after production Factors • Strong local supp

  21. Slide 21: Recognition for Commitment to Health, Safety and Social Responsibility

    Recognition for Commitment to Health, Safety and Social Responsibility For personal use only Bonus 2018 Member of Ecodes’ Climate Action InnovarSE certificate A health and safety recognition for initiative Receipt of the Cycle of Improvement award having a low accident rate as a result of sustainabl

  22. Slide 22: Appendix

    For personal use only Appendix

  23. Slide 23: Corporate Snapshot

    Corporate Snapshot For personal use only Capital Structure 1.00 60 Share Price (30 November 2021) $0.60 0.90 Shares on Issue 364.4 million 50 0.80 Options & Performance Rights - Volume (100,000 shares) Share price (A$) 0.70 Market Capitalisation $219 million 40 Cash (31 March 2021) $26.5 million 0.6

  24. Slide 24: Strong Board with Global Mining Industry Experience and Robust Governance Processes

    Strong Board with Global Mining Industry Experience and Robust Governance Processes For personal use only Richard Crookes Pauline Carr Ignacio Salazar Independent Non-Executive Director Independent Non-Executive Director MD & Chief Executive Officer Chairman Richard has over 30 years of experience i

  25. Slide 25: Management with strong mining experience and local background

    Management with strong mining experience and local background For personal use only Mike Norris Javier Olloqui Chief Financial Officer Human Resources Mike was Finance Director of Avocet Mining, a Javier has over 25 years of experience in Ignacio Salazar gold producing company listed on the London H

  26. Slide 26: Registered Office and Further Information

    For personal use only ASX:HFR REGISTERED OFFICE 169 Fullarton Road Dulwich SA 5065 Australia SPAIN HEAD OFFICE Avenida Carlos III, 13-15, 1B, 31002 Pamplona, Spain T: +34 948 050 577 | F: +34 948 050 578 FURTHER INFORMATION Ignacio Salazar CEO T: +34 948 050 577 Olivier Vadillo Investor Relations T: