Lydian International Limited

Lydian International — Mines and Money (November 2017)

26 slides from Lydian International's conference presentation, November 2017

  1. Slide 1: Corporate Update November 2017

    TSX: LYD Corporate Update November 2017

  2. Slide 2: Cautionary Statements

    Cautionary Statements Forward Looking Information & Estimates of Reserves and Resources Certain information contained in this presentation, including any information relating to Amulsar's expected future performance, is "forward looking". All statements in this presentation, other than statements of

  3. Slide 3: Amulsar Gold Project: Re-Rating Opportunity

    Amulsar Gold Project Compelling Development Asset Under Construction Re-Rating Opportunity as Construction Milestones De-risk Project Large Scale Operation Low Cost, High Cashflow Average Annual Production All-in Sustaining Costs 225,000 Gold Ozs $579/oz 100% Owned Upside Potential From Current Reso

  4. Slide 4: Lydian International: Capital Structure Established for Development

    Lydian International Capital Structure Established for Development Capital Structure Ordinary Shares LYD Trading Symbols Publicly-traded Warrants LYD.WT Ordinary Shares 700 MM Shares Publicly-traded Warrants 99 MM Outstanding Unlisted Warrants 5 MM Market C$260 MM Capitalization Recent Share Price C

  5. Slide 5: Strong Financial Backing and Analyst Support

    Lydian International Strong Financial Backing and Analyst Support Key Shareholders Analyst Coverage Resource Capital Fund BMO Andrew Breichmanas Orion Mine Finance Management I Limited GMP David Stewart European Bank for Reconstruction & Development National Bank Shane Nagle Franklin Resources, Inc.

  6. Slide 6: Armenia

    Armenia Confluence of Infrastructure, Government & Workforce Located on Armenia’s Primary Infrastructure Corridor • Paved access to site • High-voltage power and water on site • Internet and telecom in place Supportive Government • Mining Right, Environmental Impact Assessment, and Technical Safety

  7. Slide 7: Amulsar: Site Plan

    Amulsar: Site Plan Conventional Open-Pit Mining & Heap Leach Processing Truck Shop Mine Pits Crushing Up to 2,975m Overland Conveyor 2,600m Truck Loadout 1,850m ADR Plant 1,630m Access Road 7 TSX: LYD

  8. Slide 8: Amulsar Operating Scale

    Amulsar Operating Scale Conventional Open-pit Mining & Heap Leach Operation Barren Rock Storage Open-Pit Mining • 2.2 Waste : Ore Ratio • Initial 10-Year Mine Life • Seek expansion from existing M+I+I • Open at depth/laterally Crushing & Screening • 2-Stage crushing • 10.2 Mtpa Overland Conveyor • 3

  9. Slide 9: Amulsar: Economic Profile

    Amulsar: Economic Profile Powerful Economics from Initial 10-Year Life; Open Potential Low-Cost Drivers Economics at $1,250 Gold Efficiencies from Large Scale Operations Initial Capex 1 $370 Million All Oxides Produce 87% Gold Recovery All-in Sustaining Costs 1 $579 / Gold Oz Conventional Mining & P

  10. Slide 10: Strategy for Growth

    Strategy for Growth Current Resources Limited by Drilling – Open at Depth/Laterally Drilling Outside Current 10-Year Pit Boundaries Mineral Resources Outside Current 10-Year Pit Boundaries RED Measured + Indicated BLUE Inferred 10 TSX: LYD

  11. Slide 11: Corporate Strategy for Growth

    Corporate Strategy for Growth Potential from Existing Resources & Future Exploration Gold Mineral Resources Outside Current 10-Year Mine Plan Tonnes Gold Grade Contained (000s) (g/t) Gold (Koz) Measured and Indicated 39,549 0.68 864 Inferred 72,200 0.55 1,280 Target 48 Mt at Reserve Grade Adds 1,000

  12. Slide 12: Amulsar Construction: 80% of Capex Committed

    Amulsar Construction 80% of Capex Committed1 Mine Operations • Four Cat 789D haul trucks, one Cat 6040 hydraulic shovel, and one loader on site and being assembled • Five more 789D haul trucks expected to arrive Q4 2017 • Mine haul road advancing • Now continuous access across Assembly of Cat 789D h

  13. Slide 13: Amulsar Construction: 80% of Capex Committed

    Amulsar Construction 80% of Capex Committed1 Materials Handling System – Crushing, Screening and Conveying • Major components on site • Three secondary cone crushers, primary crusher, apron feeder and motors • Dust collection system • Pouring concrete for crushing and screening plant • Initial steel

  14. Slide 14: Amulsar Construction: Infrastructure

    Amulsar Construction Construction Continues to Advance Infrastructure • Galvanized steel structures for the main 110kV substation switches on site • Main 110kV transformer in final stages of assembly • All plant area transformers shipped from manufacturer • Earthworks for crushing area Construction

  15. Slide 15: Amulsar Construction: Heap Leach Facility

    Amulsar Construction Construction Continues to Advance Heap Leach Facility (HLF) • Topsoil stockpiling and temporary sediment control dam complete • Installation of primary underdrain piping complete and installation of secondary piping network progressing • Earthworks advancing with dam raise, toe-

  16. Slide 16: Amulsar Construction: Processing Plant (ADR)

    Amulsar Construction Construction Continues to Advance Processing Plant (ADR) • Concrete batch plant assembled and operational • Concrete pours for equipment foundations complete and additional concrete work for ADR plant is ongoing • 15 containers of pre-assembled modules have shipped with delivery

  17. Slide 17: Near-term Project Milestones

    Lydian International Near-term Project Milestones Upcoming Accomplishments • Complete major earthworks • Heap leach facility • Mine haul road • Complete civils for primary mining and processing facilities • Continuing fabrication and delivery of mining & processing components • Erect buildings for t

  18. Slide 18: Comparable Development Stage Companies

    Comparable Development Stage Companies Targeting to Re-Rate Central to Construction Strategy Further Upside – 68.8% 1.2x Implied Upside – 79.7% 0.8x 0.7x 0.7x 0.7x 0.7x P / NAV 0.5x 0.5x 0.4x 0.4x Senior Producer Sabina Dalradian Atlantic Gold Lundin Gold Pershing Gold Victoria Belo Sun Lydian Produ

  19. Slide 19: Investment Thesis

    Investment Thesis Re-Rating Opportunity as Construction Milestones De-risk Project Large Scale Operation – average annual production of 225,000 oz Low Cost, High Cashflow Asset – all-in sustaining costs of $579/oz 100% Owned – development project Upside Potential – from current resources and open ex

  20. Slide 20: Thank You

    TSX: LYD THANK YOU

  21. Slide 21: Appendix

    Amulsar Gold Project Appendix 21 TSX: LYD

  22. Slide 22: Board of Directors

    Board of Directors Development Oriented – Independent, Diverse Experience Gordon Wylie, Non-Executive Director & Chair 32 years mining experience; AngloGold-Ashanti Global, Exploration manager Howard Stevenson, President & CEO 25 years global mining experience; former President & COO of Alacer Gold;

  23. Slide 23: Board of Directors (continued)

    Board of Directors (continued) Development Oriented – Independent, Diverse Experience Steve Altmann, Non-Executive Director Managing Director at Morrison Park; former Head of Mining at Desjardins; banking and corporate experience Josh Parrill, Non-Executive Director Resource Capital Funds; formerly

  24. Slide 24: Management

    Management Experienced, Committed to Construction Excellence Howard Stevenson, Hayk Aloyan, M.D. – Lydian Armenia President & CEO • 20 years mineral exploration and • 25 years global mining management experience experience • Armenian metallogenesis and • Alacer Gold President & COO resource speciali

  25. Slide 25: Large Scale Oxide Deposit: Mineral Resource Statement

    Large Scale Oxide Deposit Upside Potential from Inferred Resources Mineral Resource Statement AMC Consultants (UK) Limited - February 27, 2017 Quantity Gold Contained Silver Contained Tonnes Grade Gold Grade Silver Classification (000s) (g/t) (Koz) (g/t) (Koz) Measured 51,500 0.83 1,370 4.7 7,700 In

  26. Slide 26: Large Scale Oxide Deposit: Mineral Reserve Statement

    Large Scale Oxide Deposit Initial 10-Year Mine Plan from 2.6 MM Oz P+P Reserves Mineral Reserve Statement (0.24 g/t gold cutoff) Mine Development Associates, February 27, 2017 Quantity Gold Contained Silver Contained Tonnes Grade Gold Grade Silver Classification (000s) (g/t) (Koz) (g/t) (Koz) Proven

Lydian International — Mines and Money (November 2017) on 6ix