Agl Energy Limited · ASX:AGL

Agl Energy — Corporate Update (February 2015)

21 slides from Agl Energy's corporate update, Feb 11, 2015

  1. Slide 1: Broken Hill Solar Plant Community Information Session

    Broken Hill Solar 1 Plant Community Information Session 11 February 2015

  2. Slide 2: Agenda

    2 Agenda Welcome February CIS 1 2 Review previous actions 3 Overview of project status – AGL / First Solar 4 Employment 5 Project planning 6 Construction community fund 7 Next meeting > Broken Hill Solar Plant > AGL Energy > 11 February 2015

  3. Slide 3: Review actions from previous meeting

    3 2. Review actions from previous meeting Action item CCC Status Who meeting 1 Coordinate panel expressions of interest from the September Closed HO group and to advertise round one community fund 2014 open for applications 2 Provide further information about the assessment November Closed HO proces

  4. Slide 4: Overview of project status

    4 Overview of project status • Adam Mackett (AGL) • Jeff McAuliffe (First Solar) > Presentation title > Author > Date (Verdana 10pt)

  5. Slide 5: AGL overview of project status

    5 2. AGL overview of project status Solar Plant (First Solar) › Construction crews remobilised after the Christmas break. › Progressing structural component of the installation works (posts, tilt brackets and tables). › Deliveries of solar PV modules commenced. › Awarded electrical subcontractor to

  6. Slide 6: AGL overview: connection works

    6 2. AGL overview of project status Connection Works (CPP) › Design approval for the ARTC rail crossing was approved prior to Christmas. › Construction of concrete foundations for pole structures was complete prior to Christmas. › Construction crews remobilised after the Christmas break › Installed

  7. Slide 7: First Solar overview: procurement, contracts and deliveries

    7 3. First Solar overview of project status Procurement, Contracts and Deliveries: › Three packages of work – civil, structural and electrical › Civil Team Engineering awarded structural subcontract › Delivery of structural and electrical items ramping up › Majority of deliveries coming from Adelaid

  8. Slide 8: First Solar overview: construction and waste management

    8 3. First Solar overview of project status Construction › Civil works are complete › 36,000 out of the 68,000 posts have been installed › 35% of tilt brackets are installed › 25% of tables have been installed › Electrical works start in two weeks Waste management › Pallets are being recycled to Ade

  9. Slide 9: Post and tilt installation, table construction

    9 3. First Solar overview of project status Post and tilt installation Table construction > Broken Hill Solar Plant > AGL Energy > 11 February 2015

  10. Slide 10: Post installation

    10 3. First Solar overview of project status Post installation > Broken Hill Solar Plant > AGL Energy > 11 February 2015

  11. Slide 11: First Solar overview of project status

    11 3. First Solar overview of project status > Broken Hill Solar Plant > AGL Energy > 11 February 2015

  12. Slide 12: Employment

    12 Employment • Jeff McAuliffe (First Solar)

  13. Slide 13: Project employment

    13 4. Project employment › Employment is through Hays recruitment. Any employment queries should be directed to paul.harris@hays.com.au or clare.keen@hays.com.au › First Solar engaged Civil Team Engineering as structural contractor for the project Civil Team Engineering – employment: › 250 people in

  14. Slide 14: Project employment: local businesses

    14 4. Project employment › 30 local businesses have been involved in the early stages of the project which include: › Northern Earthmovers › Lawrence Auto Industrial › Silver City Security › Silver Lea Services › Summit Training Services › Bobos Engineering › MBE Electrical > Broken Hill Solar Plant

  15. Slide 15: Project planning

    15 Project planning • Helena Orel • Adam Mackett (AGL)

  16. Slide 16: Community site visit

    16 5. Community site visit c Organised community visit to the site in the coming months (around April) when module installation is underway Small group (about 30) > Broken Hill Solar Plant > AGL Energy > 11 February 2015

  17. Slide 17: Construction Community Fund

    17 Construction Community Fund • Helena Orel (AGL)

  18. Slide 18: Construction Community Fund

    18 5. Construction Community Fund › First round of funding for $25,000 has been allocated to seven projects Broken Hill Chamber of Commerce ($2,500) - to develop an online business and industry engagement survey and business directory for Broken Hill. Broken Hill Mountain Bike Club ($2,200) - to des

  19. Slide 19: Construction Community Fund: next round

    19 5. Construction Community Fund › Next round of funding will be advertised in September 2015 › Ads will run for four weeks › Expect to complete process (assessment / cheque handover) by early November > Broken Hill Solar Plant > AGL Energy > 11 February 2015

  20. Slide 20: Next meeting

    20 Next meeting • Helena Orel (AGL)

  21. Slide 21: Next meeting

    21 6. Next meeting › Any questions? › Next meeting date (proposed for Wednesday 6 May 2015) › Agenda items > Broken Hill Solar Plant > AGL Energy > 11 February 2015

AGL Energy — Corporate Update (February 2015) on 6ix