  1. Slide 1: Iluka Resources Limited

    Iluka Resources Limited South Australia Mining and Exploration Conference Rohan Cobcroft, Exploration Manager Australia December 2014

  2. Slide 2: Disclaimer – Forward Looking Statements

    Disclaimer – Forward Looking Statements Forward Looking Statements This presentation contains certain statements which constitute “forward-looking statements”. These statements include, without limitation, estimates of future production and production potential; estimates of future capital expenditu

  3. Slide 3: Discovery of Jacinth-Ambrosia

    Discovery of Jacinth-Ambrosia

  4. Slide 4: History of Discovery

    History of Discovery • Discovered in 2004 • Good old fashioned exploration • Patience – 4 years to get tenements granted • Persistence: some encouraging intercepts and one more hole beyond the program – 45m of up to 80 per cent HM and 50 per cent Zircon • First HMC produced in November 2009 • Opened

  5. Slide 5: Jacinth-Ambrosia Project Overview

    Jacinth-Ambrosia Project Overview Jacinth-Ambrosia Processing Facility Operational • Ore body 900m wide by 5 km long • Low in moisture, no groundwater, strip ratio 0.5:1 • Ore at average thickness of 20 metres • Mining unit plant in-pit ~1,300tph • Wet Concentrator ~1,000tph • HMC transported 270km

  6. Slide 6: Jacinth-Ambrosia Ore Reserves

    Jacinth-Ambrosia Ore Reserves JORC 2012 Status (Dec-13) Ore HM In-Situ Zircon Ilmenite Rutile (Mt) (Mt) (%) (%) (%) Ore Reserve - proved 119.7 5.1 51 27 4 Ore Reserve - probable 3.4 0.1 51 20 5 Total 123.1 5.2 51 27 4 Note: Refer to Iluka’s Ore Reserves and Mineral Resources Statement 2013, Iluka An

  7. Slide 7: Operational and Project Implementation - What Worked

    Operational and Project Implementation - What Worked ‘Focused on what we control – safety, environment, costs, capital, inventory & stakeholders’ Culture • Adaptive cultural change in 2009 based on leadership, accountability and flexibility • Focused on ‘setting high standards and achieving them’ -

  8. Slide 8: Satellite Deposits – Discovery Timeline

    Satellite Deposits – Discovery Timeline • Jacinth-Ambrosia – 2004 • Tripitaka – 2005 • Typhoon – 2006 • Atacama – 2011 • Sonoran – 2011 • Atacama extension – 2012 Note: Refer to Iluka’s Ore Reserves and Mineral Resources Statement 2013, Iluka Annual Report, Page 133-135 and ASX Release on 30 April 2

  9. Slide 9: Atacama / Sonoran / Typhoon

    Atacama / Sonoran / Typhoon • New production options in the Eucla Basin – Sonoran-Typhoon; and – Atacama. • Immediately adjacent to Jacinth-Ambrosia mine: – can use existing infrastructure; – provide production flexibility; – can be developed sequentially; or – in parallel to boost production. 9

  10. Slide 10: Operational Improvements

    Operational Improvements Tails Management Issues • Significant tailing swell resulting: – in higher volumes stored in off-path TSF; – insufficient mining void available for backfill; • Tails infiltration losses approaching bore field capacity • Groundwater mounding risks around impermeable basement

  11. Slide 11: Operational Improvements

    Operational Improvements Borefield Transfer Pipeline Sustainability • 31km long 644mm ID glass reinforced plastic pipe, buried for entire length, +70 metre ∆RL • Significant accretion of ferrihydrite on internal walls of pipeline occurring since commissioning in 2009 – not anticipated • Accretion ox

  12. Slide 12: Operational Improvements

    Operational Improvements Pipeline Restoration • characterisation of accretion and inspection • video footage • options analysis – selected pigging as only viable option • manage risk of failure Attempt Number 1 • Pigged jammed at 250m with solidified accretion Attempt Number 2 • 750m to 1500m sector

  13. Slide 13: South Australian Regional Contribution

    South Australian Regional Contribution • Jacinth-Ambrosia sole mining operation in region  Iluka: 67 employees, 48 per cent local  Contractors: 89 employees (mining, logistics and services) • Economic contribution*:  292 jobs and $66.1 million in value add to region  additional 646 jobs and $85

  14. Slide 14: Environmental Management

    Environmental Management  Jacinth-Ambrosia mine was the first project in South Australia permitted to be developed in a regional reserve  Iluka strives for environmental and rehabilitation standards that go beyond compliance - proactivity  Research partnerships with leading educational institutio

  15. Slide 15: Jacinth-Ambrosia Land Rehabilitation

    Jacinth-Ambrosia Land Rehabilitation Cell 1 West (in 2013) The Cell 1 Trial Cell 1 West (2014) rehab just completed Cell 1 East ( in 2013) Cell 1 East (2014) 15

  16. Slide 16: Iluka Resources Limited

    Iluka Resources Limited For more information, contact: Robert Porter, General Manager Investor Relations robert.porter@iluka.com +61 3 9225 5008 / +61 (0) 407 391 829 www.iluka.com 16