Centerpoint Energy, Inc (holding Co) · NYSE:CNP
Centerpoint Energy, Inc (holding Co) — Corporate Update (September 2011)
19 slides from Centerpoint Energy, Inc (holding Co)'s corporate update, Sep 6, 2011
Slide 1: 138 kV Springwoods Project Public Meeting
138 kV Springwoods Project Public Meeting Michael J. Pakeltis, P.E. Manager, Reliability Analysis & Technical Support CenterPoint Energy, Transmission Operations September 6, 2011
Slide 2: Overview: Tonight's Presentation
Overview Tonight’s Presentation Facts about CenterPoint Energy Project Details CenterPoint Energy’s Application to the Public Utility Commission (PUC) PUC’s Transmission Line Certification Process Electric & Magnetic Fields Land Acquisition Types of Transmission Structures Project Sc
Slide 3: CenterPoint Energy Houston Electric – An electric delivery company only
CenterPoint Energy Houston Electric – An electric delivery company only Company Facts Does not generate or sell electricity Owns and maintains electric delivery system – towers, poles, and wires 5,000 square-mile electric service territory Serves over 2 million electric customers Regulated
Slide 4: Electric Infrastructure
Electric Infrastructure Proposed Project Infrastructure 4
Slide 5: Proposed Project Preliminary Route Segment Map
Proposed Project Preliminary Route Segment Map Need to establish a new route from a 138 kV transmission line corridor to a new substation site 345kV Cannot connect to 345kV Corridor Many alternatives are proposed Only one multi-segment transmission line route and one substation site will ult
Slide 6: Why is the Project needed?
Why is the Project needed? The proposed 138 kV transmission line New Development Area and substation will support existing customers, area growth, and a large master-planned residential and commercial development under construction west of I-45 and the Hardy Toll Road The new master-planned deve
Slide 7: Project Process Overview
Project Process Overview Seeking approval to construct a 138 kV double-circuit transmission line to one of the proposed alternate CenterPoint Energy Springwoods Substation sites Located in northern Harris County and southern Montgomery Counties Currently gathering information from public and g
Slide 8: Early Stages for Preparing a CCN Application
Early Stages for Preparing a CCN Application Identify study area boundary Gather initial environmental and land-use data from various agencies for the defined study area Identify alternative substation sites Identify preliminary transmission line routing segments Provide diverse geographic
Slide 9: Next Steps in Preparing a CCN Application
Next Steps in Preparing a CCN Application Prepare a Routing Study and Environmental Assessment Assess, tabulate, and consider factors for each preliminary transmission line segment from the following: Information provided at the public meeting Submitted questionnaires Governmental and agen
Slide 10: PUC Certification Process for Transmission Lines
PUC Certification Process for Transmission Lines Process defined by the Public Utility Regulatory Act (PURA) and PUC Substantive and Procedural Rules To start the process, a utility submits a CCN application to the PUC Notice is sent to affected landowners, municipalities, and adjacent utiliti
Slide 11: Electric and Magnetic Fields
Electric and Magnetic Fields Electric and magnetic fields, sometimes referred to as “EMF”, exist wherever there is a flow of electricity Sources of EMF include: Wiring in houses, offices, and schools Electrical appliances and equipment (such as hairdryers, refrigerators, and computers) Pow
Slide 12: Land Acquisition
Land Acquisition If the Project receives PUC approval, CenterPoint Energy will acquire an easement, including access roads and material yards, by mutual agreement with the landowner If a mutual agreement cannot be reached, CenterPoint Energy will begin a condemnation proceeding by filing a petit
Slide 13: What will the transmission line structures look like?
What will the transmission line structures look like? Concrete poles are proposed Right-of-way width varies depending on the adjacent land use 60’ wide in undeveloped areas 50’ wide adjacent to transmission lines 25’ wide adjacent to roadways (aerial only) One alternate structure type wi
Slide 14: What will the transmission line structures look like?
What will the transmission line structures look like? Typical structures shown. Heights will vary with topology. 14
Slide 15: What do the alternate structures look like?
What do the alternate structures look like? Typical structures shown. Heights will vary with topology. Roadways cannot Steel towers can span accommodate steel towers longer distances, requiring fewer structures 15
Slide 16: Project Schedule
Project Schedule See revised schedule at www.centerpointenergy.com/swproject 16
Slide 17: Construction Phases
Construction Phases Transmission line construction is accomplished in several distinct phases, including: Right-of-way preparation (clearing, access, etc.) Foundation installation Structure installation Wire installation Right-of-way clean-up 17
Slide 18: Resource Websites
Resource Websites www.centerpointenergy.com/swproject www.puc.state.tx.us 18
Slide 19: Q&A Session
ge CenterPoint Thank You Our Panel is Ready to Answer Your Questions @e@e@ Please Hand Your Completed Question Forms to the Designated CenterPoint Energy Employees
CenterPoint Energy — Corporate Update (September 2011) on 6ix