Latrobe Magnesium Limited · ASX:LMG

Latrobe Magnesium — Shareholder Meeting (November 2017)

12 slides from Latrobe Magnesium's shareholder meeting presentation, Nov 17, 2017

  1. Slide 1: AGM Presentation November 2017

    For personal use only Latrobe Magnes um AGM Presentation November 2017 Amendment on Page 3 David Paterson ASX: CEO LMG

  2. Slide 2: Presentation contents

    Latrobe Presentation contents Magnes um For personal use only 1. Latrobe 2017 highlights 2. Latrobe project update 3. LMG location and site 4. Vertical Retort construction 5. Financial overview 6. Timetable 2

  3. Slide 3: Latrobe 2017 highlights

    Latrobe 1. Latrobe 2017 highlights Magnes um For personal use only  In July 2017 - acquired the remaining 50% interest in the hydromet process.  In Jan 2017 - completed the preliminary feasibility study.  In March 2017 - finalised an American distribution agreement.  In March 2017 – designed and

  4. Slide 4: Latrobe Project update

    Latrobe 2. Latrobe Project update Magnes um  Documenting an ash supply agreement and an For personal use only MoU with two fly ash sources in the Latrobe Valley and one in Germany expected to be completed within the next month.  Complete vertical retort work by February 2018 with initial results i

  5. Slide 5: LMG site

    Latrobe 3. LMG site Magnes um For personal use only Swop Line from Yallourn Natural Gas Pipeline Swop Line From Hazelwood 320 Tramway Site 5

  6. Slide 6: LMG building Tramway Site Building

    Latrobe 3. LMG building Magnes um For personal use only 6 320 Tramway Site Building

  7. Slide 7: LMG plant layout

    Latrobe 3. LMG plant layout Magnes um For personal use only 7

  8. Slide 8: For personal use only

    For personal use only 8

  9. Slide 9: Vertical Retort Latrobe

    4. Vertical Retort Latrobe Magnes um For personal use only 9

  10. Slide 10: Financial overview

    Latrobe 5. Financial overview Magnes um For personal use only 3,000 Capital Requirements tonnes A$M’s R&D Funding 16 Victorian Grants 6 LMG Equity 12 Federal RJIP Grant 6 ---- Total Project Funding 40 == Capex for 3,000 tpa plant estimated at A$37M with a working capital requirement of 3M. Total fun

  11. Slide 11: Timetable

    Latrobe 6. Timetable Magnes um For personal use only Tasks Timing • Complete Bankable Study March 2018 • Procurement & Permitting June 2018 • Construction – Initial plant July 2018 • Production - Initial plant July 2019 • Expansion Stage 2 July 2020 11

  12. Slide 12: Disclaimer

    Latrobe Disclaimer Magnes um For personal use only • This presentation may contain forward looking statements that are subject to risk factors associated with the magnesium business. • It is believed that the expectations reflected in these statements are reasonable but they may be affected by a var