Slide 1: Pump Energy Utilization Effectiveness
Pump Energy Utilization Effectiveness Eastman Kodak Rochester, NY

Slide 2: Kodak Park
Kodak Park 1300 Acres 150 Manufacturin g Buildings 30 Miles of roads 2 Power Plants Water treatment system Waste treatment system

Slide 3: Eastman Kodak Commitment
Eastman Kodak Commitment 19% Actual 17% Actual 36% Actual

Slide 4: Eastman Kodak Energy Reduction
Eastman Kodak Energy Reduction Kodak Park Annual Energy Input (Billion Btu's) 27000 25000 25,119 24,098 Heat Input (Billion Btu) 23,904 23,659 23000 22,255 21,877 21000 20,996 19000 17000 16.4% Reduction 15000 1997 1998 1999 2000 2001 2002 2003 Year

Slide 5: 2004 - 2008 Environmental Goals
2004 - 2008 Environmental Goals Reduced Natural Resource Product & Employee Emissions Conservation Stewardship Metric 2004 -2008 Metric 2004 -2008 Metric 2004-2008 Priority -15% Mfg -20% Health & KSIR 50% Chemical Waste Safety reduction Emissions LTCR < 0.25 Product Heavy metal Methylene -35% Energy

Slide 6: Pump Energy Utilization Effectiveness Team
Pump Energy Utilization Effectiveness Team Objective: Minimize energy consumption by pumping systems Optimize operation of pumping systems Team Members: Project Management - Flowserve Hydraulic Analyst - Flowserve Kodak Operations Representative Flow measurement – Kodak / Flowserve Pow

Slide 7: Pump Systems Analysis
Pump Systems Analysis Types of Systems Analyzed Open Loops (Tower Water Systems) Closed Loops (Chilled Water Systems) Raw Water Systems (Lake Station) Finished Water Systems (KW Distribution) Methylene Chloride System Boiler Feed Pump Systems Condensate Pump Systems Ash Sluice Pump S

Slide 8: Pump Systems Analysis cont'd
Pump Systems Analysis cont’d Phase I Initial Screening - Observation only 1 hour Phase II Data Acquisition and Analysis 2 hours testing 2 hours preparation 3 hours analysis Phase III Detailed Eng if required (by EK) Phase IV Implementation (by EK) Phase V Verification 2 hours

Slide 9: Pump Systems Analysis cont'd
Pump Systems Analysis cont’d Results Pump Systems Analyzed 122 Cost Savings Identified $2.25 M Electrical Savings Identified 50,100 MWH Savings “Cashed” $568,000 Implementation cost $135,200 System Operational changes Increase reliability

Slide 10: Pump Systems Analysis cont'd
Pump Systems Analysis cont’d Where have we found these savings? Oversized Pump/Impeller leading to throttling Click here for illustration Operational Sequence Click here for sample illustration Worn hydraulic parts (wear rings, impellers) Click here for illustration Control Valves vs.

Slide 11: Recommendations
Kodak 1669 Lake Avenue, Bid. 23,7" FI. Pump Division Rochester, NY 14624 Phone: 685-477-1139 Fax: §85-477-1137 elk 319-441-4198 ~ Flot Ci rat FLOWSERVE were Coxporaton Dae: dug 22,2008 To: Brim Simpson Ce: Bary Bridson, Rail Satingn Georg: Weed, Doug Frozr, Jdn Michaek,AlLopaé George Bozrkard From:

Slide 12: Reports/ Recommendations
Phage Findings ump #2 SW? Big 321) Sheet 3 of 3 Taserp ten ol Tedngs Pump Details G21 2 SW) Sheet 2 of 3 TDP 7 Howsare ANST Sheet 1 of 3 HOC Pump system energy opportunity screening USVI KPH: Beas Symptoms -based approach $0-5 {Only 10 degree Vine Oretiapy (1873 Shak Din.) Bulldirg:|[521 ] Bump No:

Slide 13: Questions????
YZ Questions????

Slide 14: Oversized Pump
Oversized Pump • Chilled Water Pump • 150 HP • Horizontal Split Case

Slide 15: Oversized Pump
Oversized Pump Pump/System Curve B 17 #26 TWP 250 Pump Curve - 15" Dia. 200 Pump Curve Trimmed Impeller Slower Speed 150 TDH - FT System Curve 100 50 Condenser Rating 0 0 500 1000 1500 2000 2500 3000 GPM

Slide 16: Optimum Pump Selection
Optimum Pump Selection Pump Selection • 7 Finished Water Pumps • 450 – 1250 HP • Feeding two 7 mile water mains

Slide 17: Optimum Pump Selection
Optimum Pump Selection High Lift Pumps (GPM/KW) 20 11 HL 15 14 HL GPM / kW 10 12 HL 18 & 19 HL 5 13 & 17 HL 0 0 5,000 10,000 15,000 20,000 Flow Rate - GPM

Slide 18: Worn Hydraulic Parts
Worn Hydraulic Parts Multi Stage Barrel Pump Boiler Feed Service Installed 1966

Slide 19: Worn Hydraulic Parts
Worn Hydraulic Parts 22% Head H-Q Comparison Deterioration 700 Power Comparison Total Developed Head - Ft . 300 600 Current 500 250 400 200 Factory Test HP 300 150 Current Performance 200 100 30% Factory Test 100 50 Excess Power System Curve 0 0 0 100 200 300 400 500 600 700 800 900 1000 0 100 200 3

Slide 20: Flow Regulation
Flow Regulation Vertical Mixed Flow Pump Lake Water Intake 400 HP 7100 Specific Speed

Slide 21: Flow Regulation
Flow Regulation Flow Speed Variable By-Pass Drive 90 400 HP 70 HP 50 HP 80 350 80 400 Pump Curve - 708 RPM HP @ 708 RPM No Power Savings with VFD 70 70 300 350 60 HP @ 665 RPM 60 300 250 - ft - ft 50 50 250 HP HP 200 TDH 40 Pump Curve - 665 RPM 40 200 TDH 150 30 Maximum Flow 30 @ 708 RPM 150 System
Source: Internet Archive copy of flowserve.com
More decks from Flowserve Corporation
Q3 2026 Earnings Presentation22 slides · Oct 29, 2026
Q2 2026 Earnings Presentation23 slides · Jul 30, 2026
Q1 2026 Earnings Presentation22 slides · Apr 30, 2026
Citi's 2026 Global Industrial Tech and Mobility Conference9 slides · Feb 17, 2026
Q4 2025 Earnings Presentation25 slides · Feb 6, 2026
Q3 2025 Earnings Presentation25 slides · Oct 29, 2025