Enlight Renewable Energy Ltd · TASE:ENLT

Enlight Renewable Energy — Q1 2021 Earnings Presentation

17 slides from Enlight Renewable Energy's earnings presentation, February 2022

  1. Slide 1: Financial Statements for Q1 2021

    Slide 1: Financial Statements for Q1 2021

    Financial Statements for Q1 2021 Financial Statements Presentation Blacksmith Project, Serbia

  2. Slide 2: Condensed statements of income, March 21 - Non-GAAP

    Slide 2: Condensed statements of income, March 21 - Non-GAAP

    Condensed statements of income, March 21 - Non-GAAP* NIS millions Q1/21 Q1/20 Change Revenues 88 77 14%+ Gross profit 51 44 +16% Operating profit 41 35 +17% Finance expenses, net (19) (36) -47% Profit before income (1) +23 taxes 22 Million NIS EBITDA 67 59 +14% FFO 46 31 +48% 1 * For the reconciliat

  3. Slide 3: Condensed statements of income, March 21 - IFRS

    Slide 3: Condensed statements of income, March 21 - IFRS

    Condensed statements of income, March 21 - IFRS NIS millions Q1/21 Q1/20 Change Revenues 70 59 +19% Gross profit 43 36 +19% Operating profit 33 27 +22% Finance expenses, net (4) (25) 84%- Profit before income 2 +27 taxes 29 Million NIS 2 +25 Profit for the period 27 Million NIS Cash from operating a

  4. Slide 4: Continued accelerated growth: projects reaching operation in the next two years

    Slide 4: Continued accelerated growth: projects reaching operation in the next two years

    Continued accelerated growth: projects which will reach operation in the next two years Emek Habacha Project, Israel First year revenues* Projected date of operation Projects under construction NIS millions Technology % Stake Output 35-45 Q2/21 Wind 69% 113MW ** Picasso Q3/21 Floating 7 PV 50.1% 17M

  5. Slide 5: Portfolio has grown to 4.8 gigawatts; 2 gigawatts of revenue-generating facilities by 2023

    Slide 5: Portfolio has grown to 4.8 gigawatts; 2 gigawatts of revenue-generating facilities by 2023

    Portfolio has grown to 4.8 gigawatts; 2 gigawatts of revenue-generating facilities by 2023 Picasso Project, Sweden Portfolio Composition Portfolio Growth Rate LTM Storage a significant growth engine MWdc 4,765 1,980 1,610 940 Before the US transaction 4,765 1,960 47%+ Capacity, MWdc Storage capacity

  6. Slide 6: Major events during the quarter

    Slide 6: Major events during the quarter

    Major events during the quarter Western Europe • Picasso: connection to the power grid in Sweden - 113 megawatts (7) • Financial closing of the Bjorn project in Sweden (372 megawatts with total financing of EUR 210 million (6) • Expansion of the Gecama project in Spain from 312 megawatts to 329 mega

  7. Slide 7: ESG updates

    Slide 7: ESG updates

    ESG updates E Environmental • Approximately 200GWh of clean energy produced during the quarter • Approximately 50,000 tons of CO2 emissions saved during the quarter • Equivalent to providing clean energy to 130,000 households or taking approximately 40,000 cars off the road S Social • Joint project

  8. Slide 8: Year of transition: world leaders accelerate the transition to renewable energies

    Slide 8: Year of transition: world leaders accelerate the transition to renewable energies

    Year of transition: word leaders accelerate the transition to renewable energies Blacksmith Project, Serbia The Washington Post, July 2020 (13) 82% of new capacity around the world in 2020 - from renewable energies (12) Biden calls for 100% clean electricity by 2035 260GW Addition from renewables Ur

  9. Slide 9: Picasso project - 113 megawatts in Sweden

    Slide 9: Picasso project - 113 megawatts in Sweden

    Picasso project - 113 megawatts in Sweden Commenced commercial operation in March 2021, expected to conclude run-in tests in the second quarter of 2021 8

  10. Slide 10: Floating solar project - 17 megawatts in the Golan Heights

    Slide 10: Floating solar project - 17 megawatts in the Golan Heights

    Floating solar project - 17 megawatts in the Golan Heights Commercial operation in Q3 2021 9

  11. Slide 11: Emek HaBacha project - 109 megawatts in the Golan Heights

    Slide 11: Emek HaBacha project - 109 megawatts in the Golan Heights

    Emek HaBacha project - 109 megawatts in the Golan Heights Commercial operation in Q3 2021, run-in tests currently underway 10

  12. Slide 12: Selac project - 105 megawatts in Kosovo

    Slide 12: Selac project - 105 megawatts in Kosovo

    Selac project - 105 megawatts in Kosovo Commercial operation in H2 2021 11 Dorot Sun Project, Israel

  13. Slide 13: Gecama project in Spain - 329 megawatts

    Slide 13: Gecama project in Spain - 329 megawatts

    Gecama project in Spain - 329 megawatts* Commercial operation in Q2 2022 12 * The Gecamaproject is in the process of increasing capacity from 312 to 329

  14. Slide 14: Bjorn project - 372 megawatts in Sweden, commencement of construction

    Slide 14: Bjorn project - 372 megawatts in Sweden, commencement of construction

    Bjorn project - 372 megawatts in Sweden, commencement of construction Commercial operation in Q4 2022 13

  15. Slide 15: Beresheet wind project - 189 megawatts in the Golan Heights

    Slide 15: Beresheet wind project - 189 megawatts in the Golan Heights

    Beresheet wind project - 189 megawatts in the Golan Heights Commercial operation in Q1 2023 14

  16. Slide 16: Annex 1 - Reconciliation of the statement of income to the Non-GAAP statement

    Slide 16: Annex 1 - Reconciliation of the statement of income to the Non-GAAP statement

    Annex 1 - Reconciliation of the statement of income for accounting purposes to the Non-GAAP statement according to the fixed assets model Presented below is a reconciliation of the figures reported in the consolidated statements of income for Q1 2021, in which some of the projects in Israel are acco

  17. Slide 17: Annex 2 - Notes and Sources

    Slide 17: Annex 2 - Notes and Sources

    Annex 2 - Notes and Sources 1. The EBITDA indicator is calculated as earnings (revenue from electricity proceeds less operating costs) before interest, taxes, depreciation and amortization, based on the application of the fixed assets model to commercially active projects. 2. Mature facilities: reve

Source: Internet Archive copy of enlightenergy.co.il