Westar Energy — Investor Presentation (March 2013)
59 slides from Westar Energy's investor presentation, Mar 1, 2013
Slide 1: March 2013 Investor Update
1 March 2013 Investor Update March 2013 Investor Update Exhibit 99.1
Slide 2: Forward Looking Disclosures
2 Forward Looking Disclosures Forward-looking statements: Certain matters discussed in this presentation are “forward- looking statements.” The Private Securities Litigation Reform Act of 1995 has established that these statements qualify for safe harbors from liability. Forward-looking statements m
Slide 3: Recent Events
3 • Yearend 2012 results $2.15 per share • Issued 2013 EPS guidance $2.00 to $2.15 • 3% increase to common dividend • 2013 – 2015 CapEx plan • Managing our costs • 2013 Regulatory calendar Recent Events March 2013 Investor Update
Slide 4: Yearend 2012 Results
4 • Retail GWh sales decreased 1.5% – Milder weather than 2011 – Estimate ≈1% weather normalized retail sales growth • Implemented all planned price adjustments (annualized amounts): – Base rates -- $50 million in May – Transmission -- $25 million in January – Environmental -- $19 million in June –
Slide 5: 2013 Earnings Guidance Range
5 • Planned prices adjustments via tracking mechanisms • Expect weather-adjusted retail sales to grow 50 to 100 bp • Combined O&M and SG&A increase ≈5% – YoY change is ≈1% decrease for all items without revenue offsets, i.e. • $30 million for SPP Transmission and Property Taxes • $19 million for pen
Slide 6: 3% Dividend Increase
6 $0.92 $1.00 $1.08 $1.16 $1.20 $1.24 $1.28 $1.32 $1.36 $0.80 $0.90 $1.00 $1.10 $1.20 $1.30 $1.40 2005 2006 2007 2008 2009 2010 2011 2012 2013 3% Dividend Increase • Long-standing dividend payout target of 60%-75% of earnings – 2013 guidance implies payout in middle of range – 9th consecutive annual
Slide 7: Forecast 2013-2015 Capital Investment of $2.3 Billion
7 Forecast 2013 – 2015 Capital Investment of $2.3 Billion March 2013 Investor Update Generation 23% Air Quality Controls 13% La Cygne Environmental 15% Nuclear Fuel 4% Transmission 24% Distribution 18% Other 3%
Slide 8: Managing O&M and SG&A
8 Managing O&M and SG&A • O&M / SG&A increased at CAGR of 6% over last 5 years – Reduced impact to ≈1% excluding items with revenue offsets which include: • SPP transmission expenses • Property taxes • Pension and tree trimming expenses $300 $400 $500 $600 $700 $800 $900 2008 2009 2010 2011 2012 201
Slide 9: 2013 Regulatory Calendar
9 2013 Regulatory Calendar March 2013 Investor Update Transmission Delivery Charge (TDC) Environmental Cost Recovery Rider (ECRR) Energy Efficiency Rider (EER) Abbreviated Rate Case Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Approximate time between filing and implementation
Slide 10: Current Plans
10 Current Plans March 2013 Investor Update
Slide 11: Annualized Rate & Revenue Changes
11 Annualized Rate & Revenue Changes Actual and Estimated 2012 2013 (Estimated) 2014 (Estimated) Base rates ≈$50 million May ≈$34 million Jan Transmission rates (a) ≈$25 million Jan 1 ≈$18 million Jan 1 ≈$22 million Jan 1 ECRR ≈$19 million June 1 ≈$31 million June 1 ≈$13 million June 1 Energy Effici
Slide 12: Major Construction Projects
12 Major Construction Projects • Air Quality Improvements – Jeffrey Energy Center • SCR on single unit to be in-service late 2014 • Will satisfy site-wide NOx limits without an additional SCR – SNCR and low NOx systems – La Cygne Energy Center in-service mid 2015 • Scrubbers, fabric filters, common
Slide 13: Capital Expenditure Forecast 2013-2015
13 Capital Expenditure Forecast 2013 - 2015 Actual Forecast Forecast Forecast Forecast Method of Cost 2012 2013 2014 2015 2013 - 2015 Recovery Generation replacements and other 146.5$ 199.6$ 174.1$ 169.0$ 542.7$ GRC Westar environmental 195.1 118.7 130.0 44.3 293.0 ECRR La Cygne environmental 159.7
Slide 14: Capital Expenditure Forecast 2013-2015 Chart
14 Capital Expenditure Forecast 2013 - 2015 $0 $100 $200 $300 $400 $500 $600 $700 $800 $900 $1,000 2012 2013 2014 2015 M illi on s $810 $888 $785 $642 Air Quality - ECRR Other Transmission 36% 38% 36% 41% La Cygne Bracketed segments represent the transmission and air quality control investments reco
Slide 15: Projected Rate Base 2012-2017
15 Projected Rate Base 2012 – 2017 (in billions) 2012 2013 2014 2015 2016 2017 Base Air Quality Transmission $7.3 $7.0 $6.7 $6.4 $5.9 $5.3 $4.0 $4.5 $4.6 $4.8 $4.9 $5.0 March 2013 Investor Update $0.9 $1.0 $1.2 $1.3 $1.6 $1.8 $0.4 $0.4 $0.5 $0.6 $0.5 $0.5
Slide 16: Environmental
16 Environmental March 2013 Investor Update
Slide 17: Environmental Regulation Summary
17 Cross-State Air Pollution Rule Mercury and Air Toxics Standards Water 316(b) Coal Combustion Waste SO2 National Ambient Air Quality Standard Status Uncertain (Vacated by DC Circuit Court) Final Rule December 2011 Proposed March 2011 Proposed June 2010 Final Rule 2010 Effective DC Court denied EPA
Slide 18: Investment in Air Quality Controls
18 $0.0 $0.5 $1.0 $1.5 $2.0 $0 $50 $100 $150 $200 $250 $300 $350 $400 2005 2006 2007 2008 2009 2010 2011 2012 2013E 2014E 2015E Investment in Air Quality Controls $ M il li o n s A n n u a l In v estme n t $ B il li o n s C u m u lat iv e I n v estme n t $2.0 $1.5 $1.0 $0.5 $0.0 March 2013 Investor
Slide 19: Air Quality Improvement
19 0 10,000 20,000 30,000 40,000 50,000 60,000 70,000 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 Air Quality Improvement March 2013 Investor Update Actual Projected Sulfur Dioxide Nitrogen Oxide Emission Rates (lbs/MWh) Emission Levels (Tons) Project ≈90% reduction Project ≈75%
Slide 20: Westar Coal Fleet Emission Control Equipment
20 Westar Coal Fleet Emission Control Equipment Unit Scrubber Precipitator Fabric Filter Low NOx SCR/SNCR ACI DSI Jeffrey 1 Yes Yes No plans Yes SCR (a) Planned No plans Jeffrey 2 Yes Yes No plans Yes SNCR (a) Planned No plans Jeffrey 3 Yes Yes No plans Yes SNCR Planned No plans La Cygne 1 Yes (b) Y
Slide 21: Mercury and Air Toxics Standards (MATS)
21 • Westar does not view as problematic – No surprises in final rule – Have four years to comply – View as additive to current environmental plans • Incorporated anticipated rules in current compliance plans for Regional Haze and JEC Consent Decree – Largest fleet impact on smallest coal-fired unit
Slide 22: Air Quality Controls
22 Air Quality Control Targeted Emission / Benefit Low NOx Burner Systems NOx Selective Non-Catalytic Reduction NOx Selective Catalytic Reduction NOx Scrubber SO2 Acid gases Small amount of mercury Baghouse Particulate matter Small amount of mercury Metals Electrostatic Precipitator Particulate matt
Slide 23: Transmission
23 Transmission March 2013 Investor Update
Slide 24: Major Transmission Investment
24 Major Transmission Investment • Prairie Wind Transmission • 50/50 JV with ETA • Siting approved June 2011 • Acquiring ROW and clearing • Began construction Aug 2012 • Approximately 110 miles • Estimated completion 2014 • Project cost ≈$180 million March 2013 Investor Update
Slide 25: Investment in Transmission
25 $0.0 $0.5 $1.0 $1.5 $0 $50 $100 $150 $200 $250 2005 2006 2007 2008 2009 2010 2011 2012 2013E 2014E 2015E Investment in Transmission $ M il li o n s A n n u a l In v estme n t $ B il li o n s C u m u lat iv e I n v estme n t March 2013 Investor Update
Slide 26: Potential for High Voltage Transmission Growth
26 Potential for High Voltage Transmission Growth A. JEC to Iatan Energy Center B. Wolf Creek to Swissvale C. Concordia to Salina D. Salina to Hays E. JEC to Swissvale F. Hutchinson to Spearville G. Wichita to Rose Hill H. JEC to Concordia F G A B C E D H March 2013 Investor Update Granted condition
Slide 27: Prairie Wind Transmission Regulation
27 Prairie Wind Transmission Regulation • Received FERC incentives – Recovery of pre-commercial development costs – CWIP recovery in rate base – Allowed ROE of 12.8% • KCC – Siting approved June 2011 • Southwest Power Pool – Regional cost allocation approved by FERC – PWT’s formula rate in effect Ma
Slide 28: Profile
28 Profile March 2013 Investor Update
Slide 29: Strategic Approach
29 Strategic Approach • Embrace uncertainty – Acknowledge inability to predict the future • Value flexibility – Operational – Financial – Regulatory • Leverage actions and strategies around intrinsic advantages • Seek collaborative and constructive approaches to regulation • Value proposition – Prot
Slide 30: Regulatory Approach
30 Regulatory Approach • A sound regulatory and energy policy platform – KCC and FERC • Ultimately results in lower rates for customers March 2013 Investor Update
Slide 31: Favorable Supply Portfolio
31 Favorable Supply Portfolio $33.29 $20.59 $7.28 Uranium Coal Gas Ave. Fuel Cost $19.65/MWh Fuel Mix Coal 47% Gas 36% Wind 9% Uranium 8% MW Capability 6.0¢ 7.0¢ 8.0¢ 9.0¢ 10.0¢ 11.0¢ Westar Energy Kansas City Power and Light (KS) Empire District Electric (KS) C e n ts p e r K W h National Average 8
Slide 32: Diverse Energy Sales
32 Diverse Energy Sales (MWh) Chemical & oil Food processing Aerospace Consumer manufacturing Other Commercial 38% Residential 34% Industrial 28% 39% 17% 16% 15% 13% 12% 18% 8% 7% 3% 4% 48% Other General merchandise Grocery/ Convenience Real estate Health care Government Education March 2013 Investo
Slide 33: Service Territory Economy
33 Service Territory Economy 3 4 5 6 7 8 9 10 11 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec U ne m pl oy m en t % ’s Unemployment (latest 12 months) U.S. KS • Economy stronger than the nation – No big real estate crash – Unemployment remains 2+ pts favorable to nation • Economic development gai
Slide 34: Liquidity and Capitalization
34 Liquidity and Capitalization Target ≈50/50 capital structure Debt 49% Equity 51% Dec 31, 2012 (a) (millions) Long-term, net $2,819 Common 2,896 Total Capitalization $5,715 (a) Capitalization excludes short-term debt and adjustments for VIEs March 2013 Investor Update • Solid investment grade cred
Slide 35: 3% Dividend Increase
35 $0.92 $1.00 $1.08 $1.16 $1.20 $1.24 $1.28 $1.32 $1.36 $0.80 $0.90 $1.00 $1.10 $1.20 $1.30 $1.40 2005 2006 2007 2008 2009 2010 2011 2012 2013 3% Dividend Increase • Long-standing dividend payout target of 60%-75% of earnings – 2013 guidance implies payout in middle of range – 9th consecutive annua
Slide 36: Westar's Value Proposition
36 Westar’s Value Proposition • Solid, transparent business strategy • Strong, experienced utility management team • Thoughtful, disciplined approach to operations, capital planning and financing • Constructive regulatory and policy environment – Results in lower, more gradual price changes for cust
Slide 37: Rates and Regulation
37 Rates and Regulation March 2013 Investor Update
Slide 38: Kansas Regulators
38 • Kansas Corporation Commission – Three-member board appointed by governor • Serve staggered four year terms • Current KCC commissioners – Mark Sievers (R), chairman • Term expires March 2015 – Thomas Wright (D) • Term expires March 2014 – Shari Feist Albrecht (I) • Term expires March 2016 Kansas
Slide 39: Regulatory Approach
39 Regulatory Approach • A sound regulatory and energy policy platform – KCC and FERC • Ultimately results in lower rates for customers March 2013 Investor Update
Slide 40: Methods of Cost Recovery
40 Methods of Cost Recovery Revenue Requirement Method of Recovery Comment 1. Fuel, purchased power and environmental consumables Quarterly adjustment based on forecasted cost, with annual true-up Adjusts prices for actual costs, protecting both customers and investors from mispricing 2. Environment
Slide 41: Retail Energy Cost Adjustment (RECA)
41 Retail Energy Cost Adjustment (RECA) • Provides timely price adjustments for fuel and purchased power costs • Retail rates based on forecast of fuel and purchased power costs and retail sales – Set quarterly – Difference between forecast and actual is deferred • Quarterly approach produces more s
Slide 42: Pension Tracker
42 Pension Tracker • Defer as regulatory asset shortfall between funding of GAAP pension/OPEB expense and pension/OPEB currently authorized in rates • Maintain minimum funding level equal to GAAP pension/OPEB expense • Recover deferred expenses through multi-year amortization as part of next rate ca
Slide 43: Environmental Cost Recovery Rider Mechanics
43 Environmental Cost Recovery Rider Mechanics • ECRR adjusts retail rates annually to reflect capital investments in emission controls – Investments as of December 31 recovered in rates subsequent June – Eliminates need to file a rate case to capture rate base additions • Return of and on capital t
Slide 44: Illustrative ECRR Mechanics
44 Illustrative ECRR Mechanics (1) Illustration reflects only the projects publicly announced and assumes one-half of annual investment in service at year end (2) Illustration uses ≈11.9% pretax return and 4% depreciation recovery (3) Annual ECRR Tariff is effective June 1; assume Jan-May at prior y
Slide 45: Transmission Cost Recovery
45 Transmission Cost Recovery • FERC formula transmission rate – Changes in cost of service reflected in annual update of FERC tariff • Update posted each October using projected test year – Capital expenditures – O&M – Tariff based on year-end consolidated capital structure • FERC transmission chan
Slide 46: Transmission Formula Rate Mechanics
46 Transmission Formula Rate Mechanics • Fixed formula with changing inputs – Updated annually using Form 1 data – Established protocols for updates • Uses projected test year – Rate base (based on 13 month average) – O&M, depreciation and taxes – Cost of debt • Annual true-up incorporated in subseq
Slide 47: Energy Efficiency Initiatives
47 Energy Efficiency Initiatives • Deferred accounting for the cost of energy efficiency initiatives, such as – Smart thermostats – Customer educational programs – Demand response programs • SmartStar Lawrence smart grid project – Installed ≈48,000 “smart” meters – Advanced outage management system
Slide 48: Abbreviated (Limited Scope) Rate Case (ARC)
48 • Obtain permission from KCC to file ARC – Request made in a general rate case (GRC) – Identify scope of proposed ARC • Must file within 12 months of final GRC order • Applicant must adopt from previous rate order: – All regulatory procedures – All regulatory principles – Established rate of retu
Slide 49: Kansas' Renewable Requirements
49 Kansas’ Renewable Requirements • Renewable Portfolio Standard established – Installed capability standard in lieu of energy standard • 10% of peak load by 2011, 15% by 2016 and 20% after 2020 – If generated in Kansas, treated at 110% of requirement – Relief from standard possible if costs would i
Slide 50: Westar Renewables Compliance
50 0 200 400 600 800 1,000 1,200 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 M W Westar Commitment REC Allowance Statuatory Requirement Westar Renewables Compliance Favorable pricing allowed for head start on 2016 statute requirements KCC allowed the 2011 statute requiremen
Slide 51: Statutes for Predetermination and CWIP
51 Statutes for Predetermination and CWIP • Predetermination – Utilities can obtain order establishing ratemaking principles that will apply over the life of the asset • Construction Work in Progress (CWIP) – Utilities can include CWIP in rate cases March 2013 Investor Update
Slide 52: Capital Structure for Ratemaking
52 Capital Structure for Ratemaking (Per Recent Orders) Capitalization Ratio Cost of Capital Weighted Cost of Capital Pre-tax Weighted Cost of Capital Long-term debt 46.97% 6.65% 3.12% 3.12% Preferred 0.40 4.55 .02 .03 Common 52.63 10.00 5.26 8.71 100.00% 8.40% 11.86% Capitalization Ratio Cost of Ca
Slide 53: Background
53 Background March 2013 Investor Update
Slide 54: Westar Energy Legal Structure
54 Westar Energy Legal Structure Kansas Gas and Electric Company Consolidated capital structure is used for ratemaking (Rate regulated utility) (Rate regulated utility) Westar Energy, Inc. Parent Subsidiary Combined company does business under the name “Westar Energy” March 2013 Investor Update
Slide 55: Westar's Generating Resources
55 Westar’s Generating Resources March 2013 Investor Update
Slide 56: Westar's Plants
56 Westar’s Plants Westar's MW Operator Years Installed Pulverized coal Jeffrey Energy Center 1,983 Westar 1978, 1980, 1983 Lawrence Energy Center 534 Westar 1954, 1960, 1971 Tecumseh Energy Center 197 Westar 1957, 1962 LaCygne Station 711 KCPL 1973, 1977 Nuclear Wolf Creek 547 WCNOC (1) 1985 Gas st
Slide 57: Low-Cost Coal Fleet
57 Low-Cost Coal Fleet • Very low fuel cost – PRB coal – Excellent rail arrangements – Proximity to mines • Low embedded capital cost • No high-heat rate obsolete plants $0 $150 $300 $450 $600 $750 $900 $1,050 $1,200 $1,350 JEC 3 JEC 2 JEC 1 LEC 5 LAC 1 LAC 2 TEC 8 LEC 4 TEC 7 LEC 3 Embedded Cost 5,
Slide 58: Westar Energy Coal Fleet
58 Westar Energy Coal Fleet Unit Capacity (MW) WR Share (MW) Age Heat Rate (Btu/kWh) Net Book Value (Millions) $/KW Jeffrey 3 722 664 30 11,193 329$ 495$ Jeffrey 2 715 658 33 11,139 253$ 384$ Jeffrey 1 718 661 35 11,289 255$ 386$ Lawrence 5 374 374 42 10,361 233$ 623$ La Cygne 1 736 368 40 10,936 15
Slide 59: Coal Supply
59 Westar-operated plant fuel supply (80%) • JEC supply under contract through 2020 (10+ million tons/year) – 70% has no market openers – 30% reopened on price every 5 years • Most recent re-pricing effective January 2013 – All volumes have cost escalators – Rail contract through 2013 • LEC/TEC supp