    Hazer Group Limited (ACN 144 044 600) Level 9, 99 St Georges Tce, WA 6000 PO Box Z5511, St Georges Tce, Perth, WA 6831 COMMERCIAL DEMONSTRATION PROJECT INVESTOR PRESENTATION PERTH, AUSTRALIA; 7 AUGUST 2020: Hazer Group (ASX:HZR) is pleased to provide the following Hazer Commercial Demonstration Proj

  2. Slide 2: Hazer Commercial Demonstration Project Final Investment Decision Approved

    HAZER COMMERCIAL DEMONSTRATION PROJECT FINAL INVESTMENT DECISION APPROVED HAZER GROUP LTD ASX : HZR AUGUST 2020 1

  3. Slide 3: Disclaimer

    DISCLAIMER Important Information This presentation has been prepared by Hazer Group Limited (“Hazer” or To the maximum extent permitted by law, Hazer and its related bodies “the Company”) corporate, directors, officers, employees, advisers and agents disclaim all This presentation is not a financial

  4. Slide 4: The Hazer Process

    THE HAZER PROCESS Low cost, low emissions process to create two high value, high demand products • Hazer Process – low emission path to create two high value products utilizing methane feedstock and iron ore catalyst • hydrogen; 99.99% + purity • synthetic graphite; 80 – 95% TGC • Strong market dyna

  5. Slide 5: The Hazer Process

    THE HAZER PROCESS Producing two sustainable and valuable products without creating CO2 in the process 25% Hydrogen 75% Carbon Hazer Methane Process composition Hydrogen (gas) =$ Iron-ore process catalyst Graphite (carbon) =$ CH4 2H2 + C * CO2 abatement potential : 100 - 150 t CO2 (equiv) / t Hydroge

  6. Slide 6: Hazer Development History

    HAZER DEVELOPMENT HISTORY Advancing towards commercial production, backed by extensive research & pilot testing 2007 2010 & 2015 2015 - 2020 2018 - 2020 May 2019 June 2019 Research commences Hazer Group Research collaboration Pilot Plant Test Signed MOU with Primero appointed at the University of es

  7. Slide 7: Hazer Commercial Demonstration Project

    HAZER COMMERCIAL DEMONSTRATION PROJECT First fully integrated larger scale demonstration of the Hazer Process • Capacity - 100 tonne p.a fuel cell grade hydrogen capable of being used as a low emission transport fuel, for power generation or clean industrial applications • Feedstock – Biogas – metha

  8. Slide 8: ARENA Grant Funding of $9.41M

    ARENA GRANT FUNDING OF $9.41M Australian Government support for commercial development of a novel Australian technology • Australian Renewable Energy Agency (ARENA) is a Federal Government agency established to drive the competitiveness and adoption of renewable energy • Hazer has executed a binding

  9. Slide 9: Funding Package Overview

    FUNDING PACKAGE OVERVIEW Project fully funded and on target to commence hydrogen production mid 2021 • CAPEX budget $17M – fully funded by a combination Cash runway of Hazer cash resources, ARENA grant funding and supports business Senior Secured Loan Facility development activities and • CAPEX esti

  10. Slide 10: Hazer CDP – Schedule and Milestone

    HAZER CDP – SCHEDULE AND MILESTONE Q1 FY21 Q2 FY21 Q3 FY21 Q4 FY21 July 20 October 20 January 21 May 21 Project FID announced Complete Detailed Commence Onsite Commence Pre – Design & Award of Installation Commissioning July 20 Contract Packages Appointment of Primero Mid CY 2021 Group as engineerin

  11. Slide 11: Summary

    SUMMARY Completion of the CDP is the major step to demonstrate the scale- up of the Hazer technology for commercial applications • First larger-scale, fully integrated, continuous application of the Hazer Process; builds on two years of successful pilot programs in NSW & WA • Binding agreements in p

  12. Slide 12: Appendix

    APPENDIX

  13. Slide 13: Corporate Overview

    CORPORATE OVERVIEW Capital Structure Share price & volume Shares on Issue 136.3m Market Capitalisation @$0.425 $57.9m Cash @ 30 June 2020 $17.2m Total Options (strike prices from $0.40 to $1.20) 25.6m Share Register 8% Mineral Resources 5% Andrew Cornejo 19% Top 20 ex substantial shareholders 68% Ot

  14. Slide 14: Strong Management Team with Project Exp.

    STRONG MANAGEMENT TEAM WITH PROJECT EXP. Engineering, Technical, Marketing and Corporate expertise GEOFF WARD EMMA WALDON DR ANDREW CORNEJO LUC KOX MARK EDWARDS Chief Executive Officer & CFO & Company Co-Founder & Chief Commercial Manager Chief Operating Officer Managing Director Secretary Technical

  15. Slide 15: Experienced, Independent Board

    EXPERIENCED, INDEPENDENT BOARD Commercial, Technical, Contract and Regulatory expertise TIM GOLDSMITH DR ANDREW HARRIS DANIELLE LEE GEOFF WARD Chairman Non-Executive Director Non-Executive Director Chief Executive Officer & Managing Director • Over 20 years as Partner • Lead Director of the • Corpor