Eldorado Gold Corporation · TSX:ELD
Eldorado Gold — Investor Presentation (August 2010)
29 slides from Eldorado Gold's investor presentation, August 2010
Slide 1: Eldorado Gold Corporation
Eldorado Gold Corporation 7 wn Kistadag mine, Turkey z Jinfeng mine, China ee Tanjianshanmaltepehina White Mountain mine, China ar»
Slide 2: Global Presence
Global Presence Eldorado Gold is a Canadian-based, international gold producer with 4 operating mines, 2 mines under construction, a late-stage development project and an extensive 2010 exploration program. We operate in Turkey, China, Brazil, Greece and surrounding regions. 2
Slide 3: Kişladağ mine
Kişladağ mine Uşak Province, Turkey The largest gold mine in Turkey. 3
Slide 4: Kişladağ mine
Kişladağ mine 6.8 million oz in P+P gold reserves 10.3 million oz in M+I gold resources Continued exploration activities have been replacing and increasing mineral resources and reserves. 4
Slide 5: Kişladağ mine
Kişladağ mine Commenced commercial production in July 2006. Planned to produce 265,000 oz of gold in 2010 at a cash operating cost of $310/oz. 5
Slide 6: Kişladağ mine
Kişladağ mine Implementation of expansion project during 2010 will result in increase production commencing in 2011. 6
Slide 7: Kişladağ mine
Kişladağ mine In 2011, production is planned to be 270,000 to 280,000 oz of gold at a cash operating cost of $300 to $320/oz. 7
Slide 8: Jinfeng mine
Jinfeng mine Guizhou Province, China The second largest gold mine in China. 8
Slide 9: Jinfeng mine
Jinfeng mine 3.2 million oz in P+P gold reserves 4.3 million oz in M+I gold resources 9
Slide 10: Jinfeng mine
Jinfeng mine Commenced commercial production in September 2007. 2010 production is planned to be 190,000 oz of gold at a cash operating cost of $450/oz. 10
Slide 11: Jinfeng mine
Jinfeng mine 2011 production is expected to increase to 200,000 to 220,000 oz of gold at a cash operating cost of $370 to $390/oz. 11
Slide 12: Tanjianshan mine
Tanjianshan mine Qinghai Province, China Consists of 2 separate deposits: Qinlongtan (QLT) and Jinlonggou (JLG). 12
Slide 13: Tanjianshan mine
Tanjianshan mine 710,000 oz of P+P gold reserves 916,000 oz of M+I gold resources Continued exploration activities have been replacing and increasing our mineral resources and reserves. 13
Slide 14: Tanjianshan mine
Tanjianshan mine In 2009 we discovered a new mineralization zone, the 323 zone, which resource estimate will be released in 2010. 14
Slide 15: Tanjianshan mine
Tanjianshan mine Commenced commercial production in February 2007. 2010 production is planned to be 105,000 oz of gold at a cash operating cost of $420/oz. 15
Slide 16: Tanjianshan mine
Tanjianshan mine In 2009 we successfully completed the sulphide circuit and roaster commission while continued to operate to plan. 16
Slide 17: White Mountain mine
White Mountain mine Jilin Province, China 790,000 oz of P+P gold reserves 1.1 million oz of M+I gold resources 17
Slide 18: White Mountain mine
White Mountain mine An underground mine using a sub-level and cut-and-fill stoping mining method. Commenced commercial production in January 2009. 18
Slide 19: White Mountain mine
White Mountain mine 2010 production is planned to be 65,000 oz of gold at a cash operating cost of $460/oz. 19
Slide 20: White Mountain mine
White Mountain mine Management is reviewing options to increase underground production to utilize excess capacity in the mill. 20
Slide 21: Efemçukuru project
Efemçukuru project Izmir Province, Turkey 1.5 M oz of P+P gold reserves 1.7 M oz of M+I gold resources 21
Slide 22: Efemçukuru project
Efemçukuru project Construction is ongoing with commissioning and production planned to start in 2011. 22
Slide 23: Efemçukuru project
Efemçukuru project Exploration will continue on parallel veins within the epithermal system. Ore body is open down dip and along strike. 23
Slide 24: Eastern Dragon project
Eastern Dragon project Heilongjiang Province, China Gold-silver vein deposit 24
Slide 25: Eastern Dragon project
Eastern Dragon project 747,000 oz of P+P gold reserves 852,000 oz of M+I gold resources 6.6 M oz of P+P silver reserves 8.3 M oz of M+I silver resources 25
Slide 26: Eastern Dragon project
Eastern Dragon project Gold production is expected to begin in 2011. 26
Slide 27: Eastern Dragon project
Eastern Dragon project An aggressive drill program is planned for 2010 to explore already identified parallel structures within the exploration license. 27
Slide 28: Perama Hill project
Perama Hill project Thrace Province, Greece 966,000 oz of P+P gold reserves 1.4 M oz of M+I gold resources 28
Slide 29: Perama Hill project
Perama Hill project Construction is anticipated to commence in 2011. Average annual production is expected to be 110,000 oz of gold at an average cash operating cost of $278/oz. 29