  1. Slide 1: Boral Hall Quarry Community Meeting

    BORAL HALL QUARRY Community meeting Boral Hall Quarry, Kaveneys Rd, Jeir via Murrumbateman 6 December 2012

  2. Slide 2: Agenda

    Boral Hall Quarry Community Meeting – 6 December 2012 AGENDA Welcome and introductions Boral personnel: - Mark McCluskey – Boral Hall Quarry Manager - Paul Jackson - Stakeholder Relations Manager (NSW/VIC), Boral Property Group - Dave Hall – Boral Hall Quarry Supervisor Previous meeting (15 March 20

  3. Slide 3: Introduction of New Quarry Manager

    Boral Hall Quarry Community Meeting – 6 December 2012 INTRODUCTION OF NEW QUARRY MANAGER Mark McCluskey - Started with Boral in August - Originally from London - Married with a 5-month-old daughter - Background predominantly in quarrying and asphalt operations - Worked for eight years in the UK and

  4. Slide 4: Boral Hall Quarry General update

    Boral Hall Quarry Community Meeting – 6 December 2012 BORAL HALL QUARRY General update Since the last meeting: - Production currently at 140 000t - Market significantly slowed Sep, Oct & Nov due to ACT elections (slow down of Govt work pending results) - Quarry is running 3 days a week to supply dem

  5. Slide 5: Boral Hall Quarry – Facts & Figures

    Boral Hall Quarry Community Meeting – 6 December 2012 BORAL HALL QUARRY – FACTS & FIGURES - Boral Hall Quarry is a $5.5 million per year operation, with a significant proportion of operational expenditure directed to local businesses. - On haulage alone, $1.5 million per year is spent with 16 operat

  6. Slide 6: Dust Management

    Boral Hall Quarry Community Meeting – 6 December 2012 DUST MANAGEMENT Monitoring • 5 monitors based at set locations around the quarry • Collects the airborne dust –sent to an external laboratory • Samples is broken down into Insoluble solids and soluble solids • Soluble is salts, pollen (dissolves

  7. Slide 7: Section 96 Application - Update

    Boral Hall Quarry Community Meeting – 6 December 2012 SECTION 96 APPLICATION - UPDATE Since our last meeting: - Section 96 modification application was presented to Yass Valley Councillors at meeting of 8 August. - Item was deferred until after Local Government elections in September. - Requests mad

  8. Slide 8: New Kaveneys Rd-Barton Hwy Intersection

    Boral Hall Quarry Community Meeting – 6 December 2012 NEW KAVENEYS RD-BARTON HWY INTERSECTION 8

  9. Slide 9: General Business / Thank you for your attendance

    Boral Hall Quarry Community Meeting – 6 December 2012 GENERAL BUSINESS General business - Next blast will be carried out on 12 December- all local resident will be contacted. - Next meeting of Yass Valley Council on 19 December- decision expected on our Section 96 application. Site contact details -