Stelco Holdings Inc

Stelco — Corporate Update (November 2020)

10 slides from Stelco's corporate update, Nov 4, 2020

  1. Slide 1: Hamilton Works Community Liaison Committee Meeting Q3 2020

    Hamilton Works Community Liaison Committee Meeting Q3 2020 4 November 2020

  2. Slide 2: Agenda

    Agenda 1. Introductions 2. General Update 3. Performance under O.Reg. 419/05 Site Specific Standard Order – Particulates 4. Coalfield Dust Management Update 5. Community Feedback 6. Proposed 2021 Meeting Dates 7. Adjournment

  3. Slide 3: Site-Specific Standard Order (Particulates): Performance Review – Daily

    Site-Specific Standard Order (Particulates): Performance Review – Daily Date Doors Lids Off-takes (% Leaks) (% Leaks) (% Leaks) 2015 Thresholds 54% 2% NA (July 2 start) 2016 Thresholds 32% 2% NA 2017-2019 Thresholds 10% 2% 5% 2020 Thresholds 5% 1% 4% July – Sept Range 0 – 6.72% 0 – 1.23% 0 – 2.50% (

  4. Slide 4: Site-Specific Standard Order (Particulates): Performance Review – 30 Day Rolling Averages

    Site-Specific Standard Order (Particulates): Performance Review – 30 Day Rolling Averages Date Doors Lids Off-takes Charging (% Leaks) (% Leaks) (% Leaks) (sec) (log avg) 2015 Limits 38% 0.8% 25% 12 sec (July 2 start) 2016 Limits 22.5% 0.8% 15% 12 s 2017-2019 Limits 7% 0.8% 4.2% 12 s 2020 Limits 4%

  5. Slide 5: Performance Review – Daily Observations – Pushing Emissions

    Site-Specific Standard Order (Particulates): Performance Review – Daily Observations – Pushing Emissions Date Pushing Emission (opacity %) 2015 Limit (July 2 start) ≥ 50% 2016 – 2018 ≥ 50% 2019 ≥ 40% 2020 ≥ 30% July – Sept Range 0 – 33.33% (Average) (12.94%) July – Sept Operational Adjustments (1 ex

  6. Slide 6: Performance Review – Additional Items

    Site-Specific Standard Order (Particulates): Performance Review – Additional Items • There were no community complaints to report • MECP to provide verbal comments

  7. Slide 7: Coal Field Dust Management Update

    Coal Field Dust Management Update Goal • Improved dust management on Stelco’s Coal Storage Dock Background • Dust control was with mobile water tankers that kept the coal piles wet with water sprays. Solution • Fixed sprinkler system • Effective trial with 2 sprinklers in 2019. Result • Installation

  8. Slide 8: Community Feedback

    Community Feedback STELCO } +

  9. Slide 9: Proposed 2021 Meeting Dates

    Proposed 2021 Meeting Dates • Wed. Jan. 27, 2021 • Wed. Apr. 28, 2021 • Wed. July 28, 2021 • Wed. Oct. 27, 2021

  10. Slide 10: Thank You.

    | STELCO | 9 The Steel Company of Canada Thank You. stelco.com