Slide 1: Power Quality
Power Quality Mary Santori, P.E. Senior Engineer September 12, 2013 1
Slide 2: Topics discussed
Topics discussed Causes of Disturbances Normal utility operations that can cause problems with sensitive equipment How Xcel Energy works with customers on power quality issues Reliability Key Indices and Outage Causes Preventive Maintenance 2
Slide 3: Causes of disturbances
Causes of disturbances On-site interference Caused by loads inside a facility affecting the power in such a way as to cause other loads to malfunction Neighboring interference Caused by loads outside a facility affecting the power in such a ways as to cause other loads to malfunction Natur
Slide 4: Normal utility operations that can cause problems with sensitive equipment
Normal utility operations that can cause problems with sensitive equipment Protective devices operating under fault (i.e. breakers, fuses, reclosers) Normal equipment operation (i.e. capacitor bank switching) Single phase events (one phase of a three phase service is out) – Recommend phase pro
Slide 5: Typical Electric Utility Distribution Layout
Typical Electric Utility Distribution Layout From Transmission System Breaker Breaker Breaker Breaker Fuse 1 Fuse 2 Feeder A Feeder B XX Recloser Customer X Feeder C Fuse 3 Fuse 4 Customer Y Customer Z Feeder D 5
Slide 6: Typical Electric Utility Capacitor Bank Switching Waveform at Customer
Typical Electric Utility Capacitor Bank Switching Waveform at Customer 6
Slide 7: Process for power quality issues
Process for power quality issues Gather background information from customer Try and correlate disturbance to utility events Set Recording Meters if Needed Review Findings and Discuss Mitigations 7
Slide 8: Step 1: Review Issue With Customer
Step 1: Review Issue With Customer What happened? Dates and times (important to keep log) Note anything else that happened in facility at the same time Discuss customer’s electrical layout If customer has monitoring, note location of meters (service entrance ideal) 8
Slide 9: Step 2: Correlate Disturbance to Xcel Energy Electrical System
Step 2: Correlate Disturbance to Xcel Energy Electrical System If 0 volt condition, review outage logs If voltage sag condition, review outages on transmission system and neighboring taps and feeders If voltage sag or surge condition, review distribution lines device operation (i.e. capacitor
Slide 10: Step 3: Set Recording Meters if Needed
Step 3: Set Recording Meters if Needed Monitor current and voltage at customer’s transformer or service entrance Possibly monitor at neighboring customers 10
Slide 11: Step 4: Review Findings and Discuss Mitigations
Step 4: Review Findings and Discuss Mitigations After reviewing monitoring data, may need to repeat Step 2 Note current and voltage relationship Utility mitigation may include investigating malfunctioning equipment (cap bank, voltage regulator, etc..) Customer mitigation may include installi
Slide 12: Reliability Indices Reported to the MN PUC
Reliability Indices Reported to the MN PUC (many different formats) SAIFI – System Average Interruption Frequency Index Total Number of Sustained Customer Interruptions Total Number of Customers CAIDI – Customer Average Interruption Duration Index Total Customer Minutes of Sustained Outages
Slide 13: Outages Causes (by customer minutes)
Outages Causes (by customer minutes) Minnesota YTD December 2012, Internal Normalization Method Includes Partial Restoration 18,000,000 100% Customer Minutes 16,000,000 90% Cumulative % n = 80,714,261 80% 14,000,000 Cu sto m er M in utes 70% 12,000,000 Cum u lative % 60% 10,000,000 50% 8,000,000 40%
Slide 14: Preventive Maintenance Efforts
Preventive Maintenance Efforts Vegetation Management – Continual Condition Assessment/5-Year Maintenance Cycle Infrared Testing – Semiannual Condition Assessment Substation Transformers Circuit Breakers Surge Arrestors Bushings Regulators Animal Control – Ongoing/Condition Based Ca
Slide 15: Customer Reliability Opportunities
Customer Reliability Opportunities Customer owned back-up generation UPS Auto or Manual Transfer Phase Loss Protection Transient Voltage Surge Suppression 15
Slide 16: Power Quality Consultants
Power Quality Consultants (Note: Xcel Energy does not recommend any one consultant) EPRI, Mark Stephens, 865-218-8022 Hunt Electric, 651-646-2911 OlympiaTech, 763-559-1900 Parsons Electric, 763-571-8000 ColliSys, 763-535-6000 Hypertect, 651-631-0172 16