Pasinex Resources Ltd. · CSE:PSE
Pasinex Resources — Corporate Update (September 2026)
13 slides from Pasinex Resources's corporate update, September 2026
Slide 1: September 2026 Operational Updates
OPEN TO INVESTMENT CSE : PSE | FSE : PNX September 2026 Operational Updates Phenomenal High-Grade Zinc (30 TO 50%) Low Economic Risk, Low Capital, Quick to Cash Flow
Slide 2: Disclaimer
Disclaimer The information contained in this presentation is provided by Pasinex Resources Limited. (“Pasinex”) for informational purposes only and does not constitute an offer to issue or arrange to issue, or the solicitation of an offer to issue, securities of Pasinex or other financial products.
Slide 3: In-Situ Theoretical Value of Pinargozu Zinc Sulphide and Zinc Carbonate Material Mined
IN-SITU THEORETICAL VALUE OF PINARGOZU ZINC SULPHIDE AND ZINC CARBONATE MATERIAL MINED Not commercially realizable as before recovery losses, element deductions in sales, smelting and refining charges, transportation charges, marketing and sales costs, and other commercial factors Zinc Sulphide Sold
Slide 4: Pinargozu
Pinargozu 28KM NORTH OF KOZAN, TÜRKIYE 10+ YEAR PRODUCTION HISTORY
Slide 5: Production Plan | Pinargozu
Production Plan | Pinargozu SULPHIDE 645 Level Production will begin Sept 7, 2026 410 PROJECT 690 Level Production will begin after discharge of water 670 Level Up to date 105-meter 663 Level progress completed 685 Level CARBONATE 720 Level First drill location ready Sept 18, 2026 717 Level 735 Leve
Slide 6: Sulphide Production | Pinargozu
Sulphide Production | Pinargozu In the +541 Pınargözü Gallery, production of the ore at the +670 level has been completed. In Desandre-2 at the +645 level, development of the preparation gallery toward the ore has started. Production of sulphide zinc ore is planned to begin on September 7, 2026. The
Slide 7: Sulphide Production, T1 & T2 | Pinargozu
Sulphide Production, T1 & T2 | Pinargozu In the +541 Pınargözü Gallery, the down-dip continuity of the mineralization observed at the +575 level is being investigated through the T1 project at the +593 level. In the T2 project, a 5-meter advance in the N40 direction is planned in order to reach the
Slide 8: Oxide Production | Pinargozu
Oxide Production | Pinargozu Development of exploration and production galleries for oxide zinc mining is ongoing at five levels (735, 720, 717, 685, and 663m). Previous drilling has confirmed the presence of oxide ore in these areas. Oxide ore production will begin in areas where the production gal
Slide 9: What's Next? | Pinargozu
What’s Next? | Pinargozu High Grade Zinc Detected in Deeper Portion - Drilling & Mining Plan Drilling in previous years intersected 1.5 metres of high- grade zinc mineralization (44% Zn) at the 420-metre level. The 410 project was designed as a 700-metre gallery to support production and exploration
Slide 10: Sarikaya
Sarikaya KAYSERI PROVINCE, TÜRKIYE ZINC GRADES RANGING FROM APPROX. 30% TO 50%
Slide 11: Underground Drilling | Sarikaya
Underground Drilling | Sarikaya Underground diamond drilling is ongoing within a previously mined gallery at the Sarıkaya project. A total of 16 drill holes have been completed, with cumulative drilling reaching 1,400 meters. Holes SUD_012 and SUD_013 intersected sulphide zinc mineralization at two
Slide 12: Soil Sampling | Sarikaya
Soil Sampling | Sarikaya At the Sarıkaya project, a total of 334 soil samples are planned on a 100 m × 100 m grid to identify zinc veins that may be concealed beneath soil cover and do not outcrop at surface. To date, 236 samples have been collected, with 98 remaining. The samples will also be analy
Slide 13: Rock Sampling | Sarikaya
Rock Sampling | Sarikaya To date, a total of 109 rock samples have been collected from mineralized rocks identified during geological mapping at the Sarıkaya project. The samples were analyzed at ALS Laboratories, and the assay results were received on September 14, 2026. Of the samples analyzed, 25