  1. Slide 1: T&Cs OPA and SA

    T&Cs OPA and SA

  2. Slide 2: Federal Grid Code triggered the need to split up roles and responsibilities

    The entry into force of the Federal Grid Code triggered the need to split up the roles and responsabilities between the NEW actors Outage Planning Agent (OPA) and Scheduling Agent (SA) in a regulated contract. These roles and responsabilities are today consolidated in the non-regulated CIPU contract

  3. Slide 3: Agenda: T&Cs OPA and SA

    Agenda : T&Cs OPA and SA 1. Dispositions of Federal Grid Code 2. Roles and responsibilities 3. Technical units in scope of contracts 4. T&Cs structure and content

  4. Slide 4: 1. Dispositions of Federal Grid Code

    1. Dispositions of Federal Grid Code

  5. Slide 5: Dispositions Federal Grid Code: OPA / SA

    Dispositions Federal Grid Code : OPA / SA • Article 244 of the Federal Grid Code : • Article 249 of the Federal Grid Code : • Elia shall determine the Contract for Outage • Elia shall determine the Contract for Scheduling Planning Agent (“OPA Contract”) Agent ( “SA Contract”) • submit it for approva

  6. Slide 6: Dispositions Federal Grid Code: OPA / SA

    Dispositions Federal Grid Code : OPA / SA • Article 243 of the Federal Grid Code • Article 246 and 248 of the Federal Grid Code • Outage planning obligation for following Technical • Scheduling obligation for following Technical Units: Units: • PGM or ESD B, C, D connected to the • PGM or ESD B, C,

  7. Slide 7: Dispositions Federal Grid Code: OPA / SA

    Dispositions Federal Grid Code : OPA / SA • Article 243 of the Federal Grid code • Article 249 of the Federal Grid Code • T&C OPA shall define the type of information T&C SA shall exchange that need to be provided regarding the • define the type of information exchange that need availability plans.

  8. Slide 8: 2. Roles and responsibilities

    2. Roles and responsibilities

  9. Slide 9: Historical roles & responsibilities

    Historical roles & responsibilities Balance Grid User Access Holder Balance Responsible Party CIPU signatory AS provision Availability plans FCR/R1 Scheduling aFRR/R2 Bidding for mFRR/R3 redispatching Mvar Ancillary Non-reserved flexibility Service for balancing Black Start Service 9

  10. Slide 10: Current roles & responsibilities

    Current roles & responsibilities Balance Grid User Access Holder Responsible party Balance (& BRPsource) CIPU signatory AS provision Mvar Black Start BSP AS provision Non-CIPU: FCR/R1 Balancing Service BRPBSP* aFRR/R2 Provider mFRR/R3 AS provision FCR/R1 aFRR/R2 (pilot) mFRR/R3 New 10

  11. Slide 11: Future roles & responsibilities (final vision)

    Future roles & responsibilities (final vision) Balance Responsible Grid User Access Holder Balance Partysource Balance Service Balance Responsible Provider PartyBSP * FCR/R1 Reserved aFRR/R2 & non- reserved mFRR/R3 Scheduling Agent Scheduling Focus of these T&C SA and T&C OPA Bidding for is not to i

  12. Slide 12: iCAROS: Moving to new Roles

    Moving to new Roles ARP CIPU Large Generation Availability Redispatching Free balancing (TSO- Present Scheduling connected) plans flexibility bids iCAROS T&C Outage T&C T&C BSP Planning Agent Scheduling Agent Generation Availability Redispatching Free balancing TSO/DSO Scheduling Load plans flexibil

  13. Slide 13: Transition Period (Federal Grid Code – Art. 377)

    Transition Period (Federal Grid Code – Art. 377) o The Federal Grid Code foresees a transitory period between the current scheme (BRP and CIPU contract) and the target scheme (independent roles of OPA and SA, and respective T&Cs) o The modalities of the transition , which can be gradual, are set by

  14. Slide 14: 2. Technical units in scope of contracts

    2. Technical units in scope of contracts

  15. Slide 15: Outage Planning Agent: pragmatic approach for transition period

    OUTAGE PLANNING AGENT: pragmatic approach for transition period Step 1 POWER GENERATING MODULE (PGM) or ENERGY DEMAND FACILITIES STORAGE DEVICE (ESD) 25 MW or more 1 – 25 MW • Connected to Elia Simplified  Availability Grid directly or information status Mandatory through CDS : exchanges based defa

  16. Slide 16: Scheduling Agent: pragmatic approach for transition period

    SCHEDULING AGENT: pragmatic approach for transition period Step 1 POWER GENERATING MODULE (PGM) or ENERGY DEMAND FACILITIES STORAGE DEVICE (ESD) 25 MW or more 1 – 25 MW  Active power schedules in • Connected to day-ahead (DA) Elia Grid directly or through CDS : and intraday (ID) Mandatory default r

  17. Slide 17: 3. T&Cs structure and content

    3. T&Cs structure and content

  18. Slide 18: Terms & Conditions OPA / SA – Version

    Terms & Conditions OPA / SA – Version 1 Regulated Contracts Non-regulated Contracts T&C OPA T&C SA General Terms and Conditions for Ancillaries and Grid Losses Contract OPA Contract SA General Conditions General Conditions CIPU Contract CIPU Offshore Contract Specific Conditions Specific Conditions

  19. Slide 19: OPA/SA Contracts

    OPA/SA Contracts Scheduling Agent Contract Art 244 and 249 of Federal Grid Code specify the minimum set (Federal Grid Code - Art 249 §2) of obligations to be integrated in the OPA and SA Contracts 1. Conditions for technical units and scheduling agents respectively, ensuring compliance with SOGL 2.

  20. Slide 20: Current CIPU Contract

    Current CIPU Contract - 6 procedures in a calendar cycle: exchange of information on statuses, technical information, power schedules and bid prices (for redispatching and balancing) - Remuneration/compensation linked to change of statuses for planning and to the requested change of power schedule i

  21. Slide 21: From CIPU to OPA/SA

    From CIPU to OPA/SA OPA SA Procedures are kept and exchange of information is splitted in line with Procedure Listed SOGL and Federal Grid Code: Procedure Revision Statuses  OPA Contract comprises all and statuses that impact availability Procedure Stand-by Technical plans, together with technical

  22. Slide 22: Transposition of CIPU Contract in OPA / SA Contracts

    Transposition of CIPU Contract in OPA / SA Contracts Titles OPA/SA Articles OPA Contract Articles SA Contract Current CIPU Contract DEFINITIONS Definitions Definitions CONDITIONS FOR Conditions for OPA Conditions for SA PARTICIPATION Conditions for Technical Units Conditions for Technical Units PROC

  23. Slide 23: Summary of submitted T&C OPA and T&C SA

    Summary of submitted T&C OPA (including OPA Contract) and T&C SA (including SA Contract) - Regulation of planning, scheduling and redispatching : transposition of current non- regulated CIPU Contract to regulated OPA and SA - Use of new SOGL terminology - Fusion of CIPU and CIPU Offshore in the resp