Slide 1: Rye Park Wind Farm CCC Meeting June 2024
RYE PARK WIND FARM CCC MEETING JUNE 2024
Slide 2: Contents
CONTENTS 1. ACTION UPDATE 2. PROJECT UPDATE AND SCHEDULE OF WORKS 3.TRANSITION TO OPERATIONS 4. ENVIRONMENT AND COMPLIANCE 5. STAKEHOLDERS AND COMMUNITY 6. PROJECT BENEFITS RPWF CCC Presentation 2
Slide 3: Stakeholder & Community Engagement: Action Update
STAKEHOLDER & COMMUNITY ENGAGEMENT ACTION UPDATE No. Action Who Status Code of Conduct forms – sign and return the new 1 All CLOSED Code of Conduct form Rye Park Wind Farm 3
Slide 4: Schedule of Works: Indicative Schedule
SCHEDULE OF WORKS INDICATIVE SCHEDULE Project Programme: • Construction commenced 1 December 2021 • Public Road upgrades – complete • Civil works – complete • Commissioning – ongoing • Provisional Operations (63 turbines) – June 2024 • Full Operations (66 turbines) - Date to be confirmed once the re
Slide 5: Schedule of Works: Transport, Road Upgrades & Schedule
SCHEDULE OF WORKS TRANSPORT, ROAD UPGRADES & SCHEDULE Transport update: • OSOM deliveries are complete. • Project vehicles are now limited to demobilisation movements (transport of plant and equipment) and light vehicles to transport operational personnel to site. • Demobilisation of remaining plant
Slide 6: Project Update: Works on Site
PROJECT UPDATE WORKS ON SITE • 66 of 66 wind turbines now fully erected • 66 of 66 tower bases installed • 100% of main components delivered • 63 of 66 wind turbines are hot commissioned (electrically connected and generating). The last 3 turbines are not able to complete their testing and commissio
Slide 7: Transition to Operations
TRANSITION TO OPERATIONS Operational staff are mobilising to site under the delivery team Formal handover will commence for a smooth transition and inductions are currently underway for: • All operations Mark Pring, Landholder Manager • Landowner Management • Community engagement (including CCC) Thi
Slide 8: Environment & Safety Compliance
ENVIRONMENT & SAFETY COMPLIANCE COMPLIANCE Safety • No recordable incidents since last meeting • Quarterly internal HSE audit conducted April 24 Environmental • No incidents recorded since previous CCC. Complaints and Compliance • Complaints register is updated and published monthly on website • 1 x
Slide 9: Environment & Compliance
ENVIRONMENT & COMPLIANCE COMPLIANCE Biodiversity Management • On-site rehabilitation monitoring activities are continuing. • Final clearing calculations finalised in October 2023 with an overall 16% reduction in disturbance. • The majority of biodiversity offset credits have been retired by the proj
Slide 10: Environment & Compliance: Operational Facilitation
ENVIRONMENT & COMPLIANCE OPERATIONAL FACILITATION Development Consent Modification Request Additional Site Access Points • Tilt is currently assessing a request from our operations and maintenance contractor (Vestas) to seek modification to Development Consent to allow for: 1. Construction of a smal
Slide 11: Stakeholder & Community Engagement: Feedback, Enquiries & Complaints
STAKEHOLDER & COMMUNITY ENGAGEMENT FEEDBACK, ENQUIRIES & COMPLAINTS Communication • Newsletter (final construction newsletter was be distributed week commencing 3 June 2024). • Monthly construction updates focused on public road upgrades and completion of OSOM deliveries • Monthly landholder communi
Slide 12: Project Benefits: Benefit Sharing
PROJECT BENEFITS BENEFIT SHARING Benefit Sharing initiatives update • AGCareers Day – March 2024 • Country Education Fund – Boot Bash • Country Education Fund – Grants • Funding will now transition to Community Enhancement Funding via the following Councils: In accordance with the Development Consen
Slide 13: Discussion